Keyword: power-supply
Paper Title Other Keywords Page
MOPC005 352.2 MHz – 150 kW Solid State Amplifiers at the ESRF cavity, booster, klystron, HOM 71
 
  • J. Jacob, G. Gautier, M.L. Langlois, J.M. Mercier
    ESRF, Grenoble, France
 
  The ESRF has ordered seven 352.2 MHz – 150 kW Solid State Amplifiers (SSA) from the French company ELTA, with a design derived from the existing SSA developed by SOLEIL. The first four SSA will be commissioned by the end of 2011 and will be connected to the two booster cavities in Winter 2012 providing in total 600 kW in 10 Hz cycles. Thanks to anti-flicker capacitor banks with a total of 3 F in the 280 V DC power supply, up to only 350 kW will be drawn from the mains as compared to 1200 kW for the former klystron transmitter. The three remaining SSA will be received in 2012 and will feed three new single cell HOM damped cavities on the storage ring. The analysis of the market had shown that an alternative to klystrons needed to be investigated to guarantee the long term operation of the ESRF. SSA can be operated with a number of RF modules lost and are therefore intrinsically highly redundant. In parallel to the production by industry of this first batch of SSA, the ESRF is developing its own amplifier modules and proposing an alternative way to combine typically hundred RF modules using a single cavity combiner.  
 
MOPC127 Development of High RF Power Solid State Amplifiers at SOLEIL storage-ring, cavity, booster, klystron 376
 
  • P. Marchand, M.E. El Ajjouri, R. Lopes, F. Ribeiro, T. Ruan
    SOLEIL, Gif-sur-Yvette, France
 
  In SOLEIL, 5 solid state amplifiers provide the required 352 MHz RF power: 1 x 35 kW for the booster (BO) cavity and 4 x 190 kW for the 4 superconducting cavities of the storage ring (SR). Based on a design fully developed in house, they consist in a combination of a large number of 330W elementary modules (1 x 147 in the BO and 4 x 724 in the SR) with MOSFET transistors, integrated circulators and individual power supplies. After 5 years of operation, this innovative design has proved itself and demonstrated that it was an attractive alternative to the vacuum tube amplifiers, featuring an outstanding reliability and a MTBF > 1 year. In the meantime, thanks to the acquired expertise and the arrival of the 6th generation transistors, SOLEIL has carried out developments which led to doubling the power of the elementary module (700 W at 352 MHz and 500 MHz), while improving the performance in terms of gain, efficiency and thermal stress. This approach was also extended to frequencies from the FM to L band. The increasing interest for this technology has led SOLEIL to collaborate with several other laboratories and conclude a transfer of know-how with the French company, ELTA-AREVA.  
 
MOPC135 IFMIF-EVEDA RF Power System controls, linac, LLRF, cavity 394
 
  • D. Regidor, A. Arriaga, J.C. Calvo, A. Ibarra, I. Kirpitchev, J. Molla, P. Méndez, A. Salom, M. Weber
    CIEMAT, Madrid, Spain
  • M. Abs, B. Nactergal
    IBA, Louvain-la-Neuve, Belgium
  • P.-Y. Beauvais, M. Desmons, A. Mosnier
    CEA/DSM/IRFU, France
  • P. Cara
    Fusion for Energy, Garching, Germany
  • S.J. Ceballos, J. de la Cruz
    Greenpower Technologies, Sevilla, Spain
  • Z. Cvetkovic, Z. Golubicic, C. Mendez
    TTI, Santander, Spain
  • J.M. Forteza, J.M. González, C.R. Isnardi
    Indra Sistemas, San Fernando de Henares, Spain
  • D. Vandeplassche
    SCK-CEN, Mol, Belgium
 
  The IFMIF/EVEDA Accelerator Prototype will be a 9 MeV, 125 mA CW deuteron accelerator to validate the technical options for the IFMIF accelerator design. The Radiofrequency Quadrupole (RFQ), buncher cavities and Superconducting Radiofrequency Linac (SRF Linac) require continuous wave RF power at 175 MHz with an accuracy of ±1% in amplitude and ±1° in phase. Also the IFMIF/EVEDA RF Power System has to work under pulsed mode operation (during the accelerator commissioning). The IFMIF/EVEDA RF Power System is composed of 18 RF power generators feeding the eight RFQ couplers (200 kW), the two buncher cavities (105 kW) and the eight superconducting half wave resonators of the SRF Linac (105 kW). The main components of each RF power chain are the Low Level Radio Frequency system (LLRF), three amplification stages and a circulator with its load. For obvious standardization and scale economies reasons, the same topology has been chosen for the 18 RF power chains: all of them use the same main components which can be individually tuned to provide different RF output powers up to 200 kW. The studies and the current design of the IFMIF/EVEDA RF Power System are presented in this contribution.  
 
MOPO002 Fast Orbit Correction for the ESRF Storage Ring storage-ring, feedback, diagnostics, controls 478
 
  • E. Plouviez, F. Epaud, J.M. Koch, K.B. Scheidt
    ESRF, Grenoble, France
 
  Today, at the ESRF, the correction of the orbit position is performed with two independent systems: one to deal with the slow movements and one to correct the motion in a range of up to 200Hz but with a limited number of fast BPMs and steerers. This later will be removed and one unique system will cover the frequency range from DC to 200Hz using all the 224 BPMs and the 96 steerers. Indeed, thanks to the procurement of the Liberas Brilliance and installation of new AC power supplies, it is now possible to access all the Beam positions at a frequency of 10 kHz and to drive a small current in the steerers in a 400Hz bandwidth. The first tests of correction of the beam position have been performed and will be presented. This new orbit correction system is also a powerful diagnostics system: the measurement and survey of the Ring's lattice parameters is possible thanks to the high measurement rate of very high resolution position data. Results of this will also be presented.  
 
MOPO010 Orbit Feedback System for the MAX IV 3 GeV Storage Ring feedback, vacuum, storage-ring, simulation 499
 
  • M. Sjöström, J. Ahlbäck, M.A.G. Johansson, S.C. Leemann, R. Nilsson
    MAX-lab, Lund, Sweden
 
  The paper describes the current orbit correction system design for the 3 GeV storage ring at the MAX IV laboratory, a light source facility under construction in Lund, Sweden. The orbit stability requirements for the 3 GeV storage ring are tight at roughly 200 nm vertical position stability in the insertion device (ID) straight sections. To meet this the ring will be equipped with 200 beam position monitors (BPMs) and 380 dipole corrector magnets, 200 in the horizontal and 180 in the vertical plane. The feedback loop solution, one slow orbit feedback (SOFB) loop and one fast orbit feedback (FOFB) loop in fast acquisition mode at 10,000 samples/second, will be presented. The paper will also discuss the various boundary conditions specific to the MAX IV 3 GeV storage ring design, such as a Cu vacuum chamber, and the impact on the corrector design.  
 
MOPO039 B-train Performances at CNAO dipole, feedback, synchrotron, extraction 568
 
  • M. Pezzetta, G. Bazzano, E. Bressi, L. Falbo, C. Priano, M. Pullia
    CNAO Foundation, Milan, Italy
  • O. Coiro, G. Franzini, D. Pellegrini, M. Serio, A. Stella
    INFN/LNF, Frascati (Roma), Italy
  • G. Venchi
    University of Pavia, Pavia, Italy
 
  The commissioning of CNAO, the Italian Centre of Oncological Hadrontherapy, with proton beams is completed. The real-time measurement of the synchrotron dipole field with the so-called B-train, together with its electronic systems and related software and firmware are here described. An additional magnet, powered in series with the synchrotron dipoles, is equipped with a special coil that measures the field integral variation along the beam nominal path. The voltage induced in the coil is digitized with a fast ADC and numerically integrated by an FPGA. The field integral is then distributed to the users every time that the equivalent field changes by 0.1 G. The measured B field ranges from 0 to 1.6 T with maximum ramps of 3 T/s. The B-train system will be used to provide feedback in field to the dipole power supply. It will handle the limited bandwidth of the active filter, the B-field lag in the magnets and will avoid current jumps.  
 
MOPS005 Beam Dynamics Simulations of J-PARC Main Ring for Upgrade Plan of Fast Extraction Operation simulation, beam-losses, injection, proton 598
 
  • Y. Sato, K. Hara, S. Igarashi, T. Koseki, K. Ohmi, C. Ohmori, M. Tomizawa
    KEK, Ibaraki, Japan
  • H. Hotchi
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken, Japan
 
  Beam loss simulations under space charge effects are necessary to seek higher intensity proton beams. This paper presents simulations for fast extraction operation of Japan Proton Accelerator Research Complex (J-PARC) Main Ring. For upgrade plan, increasing protons per bunch and making higher repetition pattern are considered. Their optimal balance is discussed to minimize beam losses for aimed beam power considering space charge effects. We found that to optimize RF voltage pattern is a strong key to reduce beam losses for higher repetition. As benchmark works, we compare our simulations with the measured beam loss in our past operation.  
 
TUXA01 Status and Challenges of the China Spallation Neutron Source linac, DTL, rfq, dipole 889
 
  • S. Fu, H. Chen, Y.W. Chen, Y.L. Chi, H. Dong, L. Dong, S.X. Fang, K.X. Huang, W. Kang, J. Li, L. Ma, H.F. Ouyang, H. Qu, H. Sun, J. Tang, C.H. Wang, Q.B. Wang, S. Wang, T.G. Xu, Z.X. Xu, X. Yin, C. Zhang, J. Zhang
    IHEP Beijing, Beijing, People's Republic of China
 
  The accelerator complex of China Spallation Neutron Source (CSNS) mainly consists of an H linac of 80 MeV and a rapid-cycling synchrotron of 1.6 GeV. It operates at 25 Hz repetition rate with an initial proton beam power of 100 kW and is upgradeable to 500kW. The project will start construction in the middle of 2011 with a construction period of 6.5 years. The CSNS accelerator is the first large-scale, high-power accelerator project to be constructed in China and thus we are facing a lot of challenges. This paper presents the current status of CSNS project and summarizes the technology development during the past several years.  
slides icon Slides TUXA01 [3.444 MB]  
 
TUODB03 Innovative Design of the Fast Switching Power Supplies for the SOLEIL EMPHU Insertion and its Fast Correctors controls, undulator, simulation, permanent-magnet 982
 
  • F. Bouvet, D. Aballea, R. Ben El Fekih, S. Bobault, M. Bol, Y. Bouanani, Y. Dietrich, A. Hardy, F. Marteau
    SOLEIL, Gif-sur-Yvette, France
 
  A new electromagnetic/permanent magnets helical undulator has been designed and is under commissioning at SOLEIL. For a fast switching of the photon polarization, it requires a power supply able to switch between +/–350 A within 50 ms, without any current overshoot and with a very good current resolution over the full scale (50 ppm). The in-house design is based on two full switching bridges with interleaved commands. Combined with a regulation scheme using sophisticated algorithms, such a design enables to reach a high control bandwidth, permitting fast transitions. Such a fast and accurate system needs well performing digital control electronics. We chose the digital control cards developed at Paul Scherrer Institute (Villigen CH) for the SLS (Swiss Light Source). The components, measurements, interlocks, control interfaces, and electronic cards were developed and assembled together at SOLEIL. This paper will present the main lines of this development and the performances achieved during the EMPHU insertion commissioning. The design of the fast power supplies (±20 A) needed for corrector magnets of this insertion will also be presented.  
slides icon Slides TUODB03 [3.017 MB]  
 
TUPC068 SOLEIL Beam Orbit Stability Improvements feedback, booster, synchrotron, photon 1156
 
  • N. Hubert, Y.-M. Abiven, F. Blache, F. Briquez, L. Cassinari, J.-C. Denard, J.-F. Lamarre, P. Lebasque, N. Leclercq, A. Lestrade, L.S. Nadolski
    SOLEIL, Gif-sur-Yvette, France
 
  The electron beam orbit stability has been significantly improved at synchrotron SOLEIL. Low frequency noise sources have been localized and identified: the fans installed on the storage ring to cool down the ceramic chambers of the kickers, shaker and FCT, were slightly wobbling the electron beam orbit at 46, 50, 54 and 108 Hz. The localization method and the solutions that will allow reducing the noise from 0.8 μm RMS down to 0.3 μm are presented. Besides, a new 160 m long beamline, NANOSCOPIUM, is being installed on a canted straight section. Its photon beam position stability requirements are very tight calling for the following improvements: addition of 2 more BPMs and fast correctors in the orbit feedback loops, new INVAR stands for BPM and XBPM integrating Hydrostatic Level System sensors. The paper is also discussing other projects that did or will contribute to improving the beam orbit stability: installation of 145 temperature sensors on the storage ring, a new analog feedforward correction system for insertion devices, and the use of the bending magnet X-BPM measurements in the slow and fast orbit feedback loops.  
 
TUPC089 New Digital NMR System for an Old Analyzing Magnet controls, cyclotron, feedback, resonance 1215
 
  • Z. Kormány, I. Ander
    ATOMKI, Debrecen, Hungary
 
  The analyzing magnet of the ATOMKI cyclotron measures the beam energy with high precision and can lower its energy spread to ~5x10-4. The highly stable magnetic field is achieved by a NMR-feedback in the control loop of the power supply. The original analog system was designed and built over 25 years ago applying mainly obsolete, partly nowadays unavailable components. Maintaining and keeping the system running required increasing efforts every year. A new digital system has been developed to replace the old one. Except the high-frequency signal domain (HF oscillator and preamplifier) it performs every processing digitally. Its heart is a mixed-signal microcontroller that generates the signals for the NMR-probe, measures the amplitude and frequency of the oscillation, evaluates the demodulated signal and controls the power supply. A fast NMR-pulse detection algorithm was developed; as a result the embedded program can perform all measuring, detecting and controlling tasks in real-time. A PC connects to the controller, sends commands and displays the received signals and status data. The control software allows easy handling of the complete system with nearly automated operation.  
 
TUPS061 CERN Safety Alarm Monitoring controls, monitoring, site, fibre-optics 1674
 
  • H. Nissen, S. Grau
    CERN, Geneva, Switzerland
 
  The CERN Safety Alarm Monitoring system acquires safety alarms and safety information generated by CERN safety equipment such as fire and gas detectors, evacuation, emergency stops and other safety related systems, which are located in both surface and underground areas of CERN sites and accelerators. Currently there are 22170 alarms from 1025 safety equipments. This information is transmitted in a high priority and diversely redundant way to the CERN Safety Control Room for immediate intervention of the CERN Fire Brigade. The system was designed based on two main standards, the EN 50136 and IEC 61508 and was commissioned in 2003. In 2009 it was decided to launch a consolidation project in order to upgrade both hardware and software. The consolidation project includes deployment of a private CERN wide fiber optic TCP/IP network for the transmission of safety alarms, an upgrade of the SCADA software, a database upgrade and the replacement of all computers. In this paper the system is presented, the ongoing consolidating work is detailed and the middle and long term improvement plans for the system are described.  
 
TUPS064 Construction Status of the Utility System for the 3GeV TPS Storage Ring storage-ring, status, controls, booster 1683
 
  • J.-C. Chang, J.-R. Chen, Y.-C. Chung, C.K. Kuan, K.C. Kuo, J.-M. Lee, Y.-C. Lin, C.Y. Liu, I. Liu, Z.-D. Tsai
    NSRRC, Hsinchu, Taiwan
 
  The construction of the utility system for the 3.0 GeV Taiwan Photon Source (TPS) has been contracted out in the end of 2009. The whole construction of the utility system is scheduled to be completed in the end of 2012. Total budget of this construction is about four million dollars. The utility system includes the electrical power, cooling water, air conditioning, compressed air and fire control systems. The TPS construction site is located adjacent to TLS. Some areas of TPS and TLS are overlapped. Under tight schedule, limit budget and geographic constrains, it is a challenge to complete the utility system construction of TPS on time, on budget, and to specification. This paper presents some main issues and status of the utility system construction for the TPS storage ring.  
 
TUPS071 Performance of the Protection System for Superconducting Circuits during LHC Operation radiation, extraction, interlocks, instrumentation 1701
 
  • R. Denz, Z. Charifoulline, K. Dahlerup-Petersen, R. Schmidt, A.P. Siemko, J. Steckert
    CERN, Geneva, Switzerland
 
  The protection system for superconducting magnets and bus-bars is an essential part of the LHC machine protection and ensures the integrity of substantial elements of the accelerator. Due to the large amount of hardwired and software interlock channels the dependability of the system is a critical parameter for the successful exploitation of the LHC. The paper will report on observed failure modes, present fault statistics and discuss the overall performance of the protection system during LHC operation in 2010 and 2011. Foreseen measures for further improvements and operational results obtained with already implemented system upgrades will be described.  
 
WEPC055 Beam Orbit and Power Converter Stability at the CR emittance, dipole, antiproton, closed-orbit 2139
 
  • A. Dolinskii, C. Dimopoulou, O.E. Gorda, S.A. Litvinov, F. Nolden, M. Steck, H. Weick
    GSI, Darmstadt, Germany
 
  For the isochronous mode operation of the CR with reference to have good properties of the mass measurements we study the sources of the beam orbit fluctuation and as consequence power converter requirements for the CR operated at BR=13 Tm. This papaer presents a summary of the different factors causing beam orbit variation, which leads to reduction of the mass measurements precision. The requirements to the power converters have been addressed.  
 
WEPC153 ISHN Ion Source Control System Overview and Future Developments controls, ion, ion-source, plasma 2340
 
  • M. Eguiraun, I. Arredondo, J. Feuchtwanger, G. Harper, M. del Campo
    ESS-Bilbao, Zamudio, Spain
  • J. Jugo
    University of the Basque Country, Faculty of Science and Technology, Bilbao, Spain
  • S. Varnasseri
    ESS Bilbao, Derio, Spain
 
  Funding: The present work is supported by the Basque Government and Spanish Ministry of Science and Innovation.
ISHN project consist on a Penning ion source which will deliver up to 65 mA of H beam pulsed at 50 Hz with a diagnostics vessel for beam testing purposes. The present work summarizes the control system of this research facility, and presents its future developments. ISHN consist of several power supplies for plasma generation and beam extraction, including auxiliary equipment and several diagnostics elements. The control system implemented with LabVIEW is based on PXI systems from National Instruments, using two PXI chassis connected through a dedicated fiber optic link between HV platform and ground. Source operation is managed by a real time processor, while additional tasks are performed by means of an FPGA. In addition, the control system uses a MySQL database for data logging, by means of a LabVIEW application connected to such DB. The integration of EPICS into the control system by deploying a Channel Access Server is the ongoing work, several alternatives are being tested. Finally, a high resolution synchronization system has been designed, for generating timing for triggers of plasma generation and extraction as well as data acquisition for beam diagnostics.
 
 
WEPC156 Virtual Power Supply Control Environment for the TPS Project controls, EPICS, quadrupole, storage-ring 2349
 
  • Y.-S. Cheng, Y.-T. Chang, J. Chen, P.C. Chiu, K.T. Hsu, K.H. Hu, C.H. Kuo, C.-Y. Liao, C.Y. Wu
    NSRRC, Hsinchu, Taiwan
 
  The Taiwan Photon Source (TPS) is the latest generation of 3 GeV synchrotron light source which has been under construction since 2010. The control system infrastructure of TPS project is based upon the EPICS framework. In order to develop the control applications before power supplies of magnets delivered, it is necessary to set up the virtual control environment to develop high level application programs for the power supplies of magnets in advance. The high level application programs include operation process, degauss process and etc. for power supplies of magnet. The soft-IOCs (Input Output Controller) and various database records are needed to be built to simulate the power supply control environment. In addition, the operation interfaces of power supply will be designed and integrated according to location properties. The efforts will be described at this report.  
 
WEPC169 BPM System Interlock for Machine Protection at SOLEIL photon, undulator, vacuum, electron 2379
 
  • J.-C. Denard, C. Herbeaux, M. Labat, V. Leroux, A. Loulergue, J.L. Marlats
    SOLEIL, Gif-sur-Yvette, France
 
  SOLEIL, a third generation light source, has its Beam Position Monitors (BPM) processed by the LIBERA electronics built by Instrumentation Technologies. This electronics initiated and specified by SOLEIL features a fast hardware interlock output for machine protection. Although interlocks are available in both horizontal and vertical planes, it was initially thought that only the vertical interlocks would be useful. Actually, the high photon beam power densities (up to 1kW/mm2) generated by the in-vacuum undulators could damage vacuum chamber elements in case of corrector power supply failures in horizontal or vertical plane. Crotch absorbers, XBPMs and their upstream absorbers were designed on the basis that they will be protected with interlock thresholds not tighter than ±1mm. This approach was also applied for specifying the apertures of the XBPMs and of their upstream absorbers. More recently tracking simulation has shown that the crotch absorber apertures downstream the new canted undulators needed special attention.  
 
WEPO012 Calculation, Design and Manufacturing of a Resistive Quadrupole for the ESS-Bilbao Transfer Lines quadrupole, linac, acceleration, DTL 2418
 
  • I. Rodríguez, F.J. Bermejo, J.L. Munoz, D. de Cos
    ESS Bilbao, Bilbao, Spain
 
  The first stage of the ESS-Bilbao LINAC will accelerate H+ and H− high current beams up to 50 MeV for different applications. After the last acceleration step in the DTL, the beam will either be transported to the experimental laboratories by the means of several transfer lines, or continue to a further acceleration step in spoke cavities. The first design of one of the quadrupoles that focus the beam along the transfer lines is presented. The quadrupoles will have an aperture of 63 mm and 20 T/m maximum gradient, featuring a short iron yoke of 100 mm. All the quadrupoles of the transfer lines are expected to be similar in order to simplify the design and manufacturing processes. The iron yoke is small and highly saturated, and an optimization of the 3D harmonics in the load-line is developed to fulfil the field quality specifications. The required current density is high (about 8.2 A/mm2), therefore a water cooled hollow conductor is used to cool down the coils. The cooling and power supply requirements are calculated in this paper. The most important manufacturing indications are also presented.  
 
WEPS013 Results of the Nuclotron Upgrade Program ion, vacuum, heavy-ion, acceleration 2508
 
  • A.V. Eliseev, N.N. Agapov, A.V. Alfeev, V. Andreev, V. Batin, D.E. Donets, E.D. Donets, E.E. Donets, E.V. Gorbachev, A. Govorov, V. Karpinsky, V.D. Kekelidze, H.G. Khodzhibagiyan, A. Kirichenko, A.D. Kovalenko, O.S. Kozlov, N.I. Lebedev, I.N. Meshkov, V.A. Mikhailov, V. Monchinsky, S. Romanov, T.V. Rukoyatkina, A.O. Sidorin, I. Slepnev, V. Slepnev, A.V. Smirnov, A. Sorin, G.V. Trubnikov, B. Vasilishin
    JINR, Dubna, Moscow Region, Russia
  • O.I. Brovko, A.V. Butenko, N.V. Semin, V. Volkov
    JINR/VBLHEP, Moscow, Russia
 
  The Nuclotron upgrade – the Nuclotron-M project, which had been started in 2007, involved the modernization of almost all of the accelerator systems, using beam time during seven runs devoted to testing newly installed equipment. Following the project goals, in March 2010 Xe ions were accelerated to about 1.5 GeV/u. In December 2010, the stable and safe operation of the magnetic system was achieved with a main field of 2 T. The successful completion of the project paves the way for further development of the Nuclotron-based Ion Collider fAcility (NICA).  
 
WEPS020 Study of an Energy Upgrade of the CERN PS Booster booster, injection, extraction, emittance 2526
 
  • K. Hanke, O. Aberle, M. E. Angoletta, W. Bartmann, S. Bartolome, C. Bertone, A. Blas, J. Borburgh, D. Bozzini, A.C. Butterworth, C. Carli, P. Dahlen, T. Dobers, A. Findlay, R. Folch, N. Gilbert, J. Hansen, T. Hermanns, S. Jensen, P. Le Roux, L.A. Lopez Hernandez, E. Mahner, A. Masi, B. Mikulec, Y. Muttoni, A. Newborough, D. Nisbet, M. Nonis, S. Olek, M.M. Paoluzzi, S. Pittet, B. Puccio, V. Raginel, I. Ruehl, J. Tan, B. Todd, W.J.M. Weterings, M. Widorski
    CERN, Geneva, Switzerland
 
  CERN’s LHC injector chain will have to deliver beams with ultimate brilliance as the LHC is heading for increased luminosity in the coming years. In order to overcome bottlenecks in the injector chain, an increase of the beam transfer energy from the CERN Proton Synchrotron Booster (PSB) to the Proton Synchrotron (PS) has been investigated as a possible upgrade scenario. This paper gives an overview of the technical solutions and summarizes the conclusions of the feasibility study.  
 
WEPS096 Injection Energy Recovery of J-PARC RCS injection, beam-losses, impedance, septum 2730
 
  • N. Hayashi, H. Hotchi, J. Kamiya, P.K. Saha, T. Takayanagi, K. Yamamoto, M. Yamamoto, Y. Yamazaki
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken, Japan
 
  The J-PARC RCS is a high beam power Rapid-Cycling Synchrotron (RCS). The original designed injection energy is 400MeV, although presently it is 181MeV, and its beam power is limited to 0.6MW. Works to recover the Linac energy are ongoing and injection magnets power supplies upgrade are required in the RCS. In order to achieve 1MW designed beam power, new instrumentation is also planned simultaneously. Activities related injection energy recovery in the J-PARC RCS is presented.  
 
THPC063 A 2.9 Tesla Room Temperature Superbend Magnet for the Swiss Light Source at PSI storage-ring, dipole, vacuum, synchrotron 3038
 
  • A.L. Gabard, D. George, M. Negrazus, L. Rivkin, V. Vrankovic
    PSI, Villigen, Switzerland
  • Y. Kolokolnikov, P. Vobly
    BINP SB RAS, Novosibirsk, Russia
 
  The Swiss Light Source (SLS) at the Paul Scherrer Institute (PSI) in Villigen, Switzerland, is a 3rd generation synchrotron light source. With an energy of 2.4 GeV, it provides high brightness photon beams for research in materials science, biology and chemistry. The SLS storage ring contains 36 room temperature bending magnets, all of which produce light for experimental use; at the design energy of 2.4 GeV, they have a maximum magnetic field of 1.4 Tesla. Light is produced along the entire bending arc but can only be transferred to the external experimental facilities from selected short portions of the beam path. In cooperation with the Budker Institute for Nuclear Physics (BINP) in Novosibirsk, Russia, three of these magnets were replaced with new room temperature magnets with short regions of high magnetic field up to 2.9 Tesla. This enabled the production of intense light beams at shorter wavelengths than from the existing magnets. The critical energy of the 2.9 T magnet is 11.1 keV, compared to the 5.4 keV of the normal bend. This paper describes the design, including the multiple restraints, together with the measurement and commissioning of these so-called superbends.  
 
THPC139 Study of a Pulsed Sextupole Magnet Injection System for LNLS injection, sextupole, kicker, pulsed-power 3212
 
  • X.R. Resende, F.C. Arroyo, R.H.A. Farias, L. Liu, A.R.D. Rodrigues, P.P. Sanchez, G. Tosin
    LNLS, Campinas, Brazil
 
  An injection system consisting of a pulsed sextupole magnet (PSM) is being considered for Sirius, the project of a new 3rd generation 3 GeV synchrotron source in development in Brazil. This novel injection scheme will be implemented and tested in the existing UVX ring. This will also serve as an opportunity to get acquainted with the new technology and become ready for Sirius. On this paper we report on the ongoing PSM study at LNLS. In particular, details of injection dynamics calculations, magnet and pulsed power supply designs are described, as well as machine preparations for experimental tests in the UVX storage ring.  
 
THPC151 The 65 mm Period Electromagnetic/Permanent Magnets Helical Undulator at SOLEIL permanent-magnet, undulator, electron, wiggler 3239
 
  • F. Marteau, P. Berteaud, F. Bouvet, L. Chapuis, M.-E. Couprie, J.P. Daguerre, T.K. El Ajjouri, J.-M. Filhol, P. Lebasque, J.L. Marlats, A. Mary, K. Tavakoli
    SOLEIL, Gif-sur-Yvette, France
 
  SOLEIL prepares a new 65 mm period Electromagnetic/Permanent Magnets Helical Undulator (EMPHU), with a rapid switching at 5 Hz of the polarization required for dichroïsm experiments. The vertical field Bz is produced by coils fed by a fast switching power supply (designed and built in house), with a maximum current of 350 A and a polarity switching time shorter than 100 ms. The coils consist of 25 stacked copper layers shaped by water jet cutting. The current flows in 16 layers and 9 of them are cooled with thermal drain to a water piping. 4 additional power supplies feed 2 types of correction coils for the dynamic compensation of the field integrals, besides the ones for the termination. 1.28 T remanence NdFeB permanent magnets generate the horizontal field Bx. Peak Bz and Bx in the helical configuration reach 0.24 T at 14.7 mm minimum gap. Thermal modelling and measurements aim at keeping the magnet temperature constant. The static magnetic configuration was optimised using the IDBuilder software and the trajectory were checked for insuring a good reproducibility of the photon beam pointing when sweeping from one helicity to the other.  
 
THPC160 A Superconducting Switch for Insertion Devices with Variable Period Length insertion, insertion-device, undulator, wiggler 3266
 
  • T. Holubek, T. Baumbach, S. Casalbuoni, S. Gerstl, A.W. Grau, M. Hagelstein, D. Saez de Jauregui
    Karlsruhe Institute of Technology (KIT), Karlsruhe, Germany
  • C. Boffo, W. Walter
    BNG, Würzburg, Germany
 
  Superconducting insertion devices (IDs) are very attractive for synchrotron light sources since they offer the possibility to enhance the tuning range and functionality significantly by period length switching. Period length switching can be realized by employing two or more individually powerable subsets of superconducting coils and by reversing the current in a part of the winding. So far, the first demonstration mock-up coil allowing period length tripling was fabricated and tested successfully. Here, we report on the feasibility of a superconducting switch operating at 4.2 K, immersed in a liquid Helium bath as well as under conduction cooled conditions.  
 
THPO001 Design Power Supply Considerations to Compensate Booster Power Supply Effects on the SOLEIL Storage Ring booster, storage-ring, controls, dipole 3335
 
  • J.-P. Lavieville, R. Ben El Fekih, S. Bobault, D. Muller, L.S. Nadolski
    SOLEIL, Gif-sur-Yvette, France
 
  Top-up injection mode has been routinely in operation since March 2009 for various bunch filling patterns at Synchrotron SOLEIL. The electron beam stored current is maintained within 1%. At each injection the 3 Hz booster power supplies are ramped up and down over 10 seconds every 3 minutes in average. During this time DC and AC perturbations are observed on the storage ring horizontal closed orbit. Typically, the beamline source points can be shifted up to 10-20 μm and the amplitude of the 3Hz frequency is multiplied by a factor 9. The origin of these perturbations lies in the imperfect compensation of the magnet currents circulating along the booster ring located inside the storage ring. To compensate these disturbances, a wire loop was installed in the booster cable tray fed by an in-house developed power supply. Its output current is driven by direct measurement of the main currents of the booster dipole, quadrupole, sextupole power supplies with a proper amplitude and phase shift. This paper presents the determination of the compensation needs according to beam measurements, the original design and the performance reached when this power supply is acting.  
 
THPO003 Rapid-cycling Power Supplies for the J-PARC RCS Sextupole Magnets sextupole, synchrotron, proton, linac 3338
 
  • Y. Watanabe
    JAEA, Ibaraki-ken, Japan
  • T. Adachi, S. Igarashi, H. Someya
    KEK, Ibaraki, Japan
  • N. Tani
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken, Japan
 
  The rapid-cycling synchrotron of the Japan Proton Accelerator Research Complex requires 18 sextupole magnets with three families for the chromaticity correction. One family consists of six focusing sextupole magnets, and other two families consist of six defocusing sextupole magnts. An individual power supply excited for each family and the current pattern is a DC-biased sinusoidal of a frequency of 25 Hz. This paper describes design and test results of the sextupole magnet power supplies.  
 
THPO004 An Active Power Filter Based on Wavelet Analysis controls, simulation, electron, background 3341
 
  • X.L. Guo
    Private Address, Beijing, People's Republic of China
  • X.L. Guo
    IHEP Beijng, Beijing, People's Republic of China
 
  As modern accelerator demands a magnet supply with a much higher stability, it is important to improve the quality of the magnet supply. An effective method to improve the output performance active power filter (APF) applied in current supply is proposed. To lowdown the harmonic constituents, the APF circuit generates a harmonic current, which added to the current from the main power supply, to countervail the ones in the supply’s current. At end of this paper, a simulation result is given to prove the effect of APF.  
 
THPO005 A Dipole Power Supply Based on Multi-lever Inverter Technique controls, dipole, status, ion 3343
 
  • Y.X. Chen, D.Q. Gao, Y.Z. Huang, R.K. Wang, H.B. Yan
    IMP, Lanzhou, People's Republic of China
 
  By applying multi-lever inverter technique to ion accelerator power supply, it can provide steady current in wide range, increase the power supply’s equivalent output frequency, then further promote power supply’s response capability and reduce the output ripple current. This article firstly by giving a detailed introduction of composite and basic working process of dipole power supply which also applied the technique mentioned above, interpret the working principle of multi-lever inverter, and illustrate its advantages. However, applying this technique will make controller more complicated, which need to be overcome by digital regulator technique. And meanwhile digital regulator technique can improve the power supply's performance. The second part of this article briefly introduces the overall scheme of digital regulator. And at last, this article illustrate the dipole power supply meet to design target and make some improvement by using the practical results to prove that applying multi-level inverter technique into accelerator power supply is practicable and beneficial.  
 
THPO006 A Digital Power Supply Control Model in Heavy-ion Accelerator based on Dual Nios Cores controls, ion, heavy-ion, pick-up 3346
 
  • R.K. Wang, Y.X. Chen, D.Q. Gao, Y.Z. Huang, H.B. Yan, H.H. Yan, Z.Z. Zhou
    IMP, Lanzhou, People's Republic of China
  • R.K. Wang
    Graduate University, Chinese Academy of Sciences, Beijing, People's Republic of China
 
  According to the features of digital power supply and the requirements of pulse mode,this paper introduces a Digital Power Supply Control Mode(DPSCM) in Heavy-Ion Accelerator based on dual Nios cores,which meets the requirements of two basic running modes. The new method develops a system on-chip based on dual Nios cores by using SOPC technology in the Altera EP2C70 FPGA. Compared with traditional DPSCM,the dual Nios cores run simultaneously and cooperate well. As a result,the efficiency of the system is remarkably improved. Further,cores in parallel can realize reference waveforms switch in pulse mode effectively. We choose a 1150A/185V power supply as test bench. The Experimental result indicates that the system can realize the function of pulse mode,and the stability and tracking error meet the design requirements.  
 
THPO007 Operation Status of SSRF Power Supplies and Interlocks for Top-up Operation controls, storage-ring, HOM, quadrupole 3349
 
  • R. Li, C.L. Guo, M.M. Huang, T.J. Shen
    SINAP, Shanghai, People's Republic of China
 
  Digital switching mode magnet power supplies are used in SSRF accelerators which have been operating since 2008. Summary of the operation and maintenance of these power supplies will be shared over here. The availability of the power supplies is increased steadily over the past 4 years. And the power supplies interlocks for the SSRF top-up operation will be also introduced in this paper.  
 
THPO011 Practical Experience with Self-optimizing, High Dynamic Control of Accelerator Magnet Power Supplies controls, proton, resonance, feedback 3355
 
  • H. Jäckle
    PSI, Villigen, Switzerland
  • F. Jenni, X.H. Ke
    FHNW, Windisch, Switzerland
 
  In 1999, the first fully digitally controlled magnet power supplies were commissioned at PSI (Paul Scherrer Institute, Switzerland). Today, approximately 1000 of them are in use at PSI and a multiple of that worldwide. An extended PI structure is used for control. PI control is very effective and simple to use but the attainable dynamic performance is usually limited by the higher order characteristics of the output filter and the load. For the future we expect increasing requirements from highly dynamic applications, such as beam orbit feedback systems and fast scanning magnets for proton irradiation of tumors. Therefore, a self-optimizing power supply control system was developed in collaboration with the University of Applied Sciences Northwestern Switzerland. It is based on the second generation of PSI digital power electronics controller, which allows more complex control algorithms and higher sampling rates. This paper presents the achieved dynamic performance of the new control structure for various types of power supplies and magnets and compares them with the dynamic performance obtained using standard PI control.  
 
THPO012 Using a High Precision Programmable DC Power Supply of TPS Magnet quadrupole, controls, storage-ring, sextupole 3358
 
  • Y.S. Wong, J.C. Huang, K.-B. Liu, W.S. Wen
    NSRRC, Hsinchu, Taiwan
 
  Taiwan government had been announcement to set up a third-generation synchrotron radiation light source in February 2010. It should be installed with 1032 sets of magnet power supplies for the storage ring and 152 sets for the injector. In the storage ring, high precision DC power supply for 48 dipoles magnets , 240 quadrupole magnets and 168 sextupole magnets. The main windings of quadrupole and sextupole magnets are powered by individual power supplies. In the booster rings, one set of dynamic power supply for the dipole magnets and four sets for quadrupole magnets run at the biased 3Hz quasi sinusoidal wave. The Taiwan photon source (TPS) plan was completed indication national synchrotron radiation research central (NSRRC) technical capability to build at its present site in seven years a 3~3.3 GeV electron energy, 518 meter circumference, low-emittance synchrotron storage ring which will offer one of the world's brightest synchrotron x-ray sources, provide cutting-edge experimental facilities and novel multidisciplinary scientific research opportunities, enhance world-class academic research, as well as create Taiwan's scientific research marvels in the twenty-first century.  
 
THPO013 Development of a DSP-based Digital Control Three Phase Shunt Active Power Filter for Magnet Power Supply System controls, simulation, sextupole, storage-ring 3361
 
  • B.S. Wang, K.-B. Liu, Y.S. Wong
    NSRRC, Hsinchu, Taiwan
 
  There will be 240 quadruple and 168 sextuple magnet power supplies installed in TPS storage ring, power factor of these power supplies is an important issue to be concerned. A digital control three-phase shunt active power filter (APF) for quadruple and sextuple magnet power supplies is implemented and the power factor is better than 0.98. The APF power stage employs a three-phase switch-mode rectifier (SMR) to reduce the input current harmonics distortion and correct the power factor. The digital control circuit of the three-phase shunt active power filter is implemented by using a multi-channel 12 bits analog-to-digital converter、high resolution Pulse Width Modulated (PWM) and a TMS320F28335 digital signal processor (DSP). The system configuration is described in three function blocks include principle of compensation、design of the snubber protective circuit and control strategies. Finally, the feasibility and validity of proposed scheme is simulated with Matlab simulink and verified by the homemade digital control three-phase shunt active power filter.  
 
THPO014 Analysis and Compensator Design of Magnet Correction Power Supply controls, feedback, simulation 3364
 
  • Y.S. Wong, J.C. Huang, K.-B. Liu
    NSRRC, Hsinchu, Taiwan
 
  This paper presents a new method for the analysis and design of compensators for magnet correction (MC) power supply. The system has to need controllers to satisfy required gain and phase margin specifications and compensator by adding to circuit controller and switch. The gain-phase margin tester method can transform of the controller and find solutions on the figure. According to circuit frequency response and transfer function by theory analysis and simulation design new method compensators to improved anti-disturbance and stability of the system.  
 
THPO015 External Energy Dump for Superconducting Magnet of the Uni-polar Power System controls, superconductivity, simulation, HOM 3367
 
  • Y.S. Wong, K.-B. Liu, W.S. Wen
    NSRRC, Hsinchu, Taiwan
 
  This thesis focuses on the design of superconducting discharge energy circuit structure in Uni-polar power supply [1]~[3]. Superconductivity is an electrical resistance of exactly zero which occurs in certain materials below a characteristic temperature [4]. It’s operation at the steady state in constant temperature area. When Rise up resistance and temperature of superconductivity will have been dissipates function. Uni-polar power supply has needed to design discharge energy circuit when superconductor reduces the current. To make use release the energy transfers to external circuit keep the constant temperature with the superconductivity. The superconducting coil wingding has a total length magnetic period of 56.56cm, total magnet length of 478.9cm and vertical (horizontal) magnetic field of 18.7T.  
 
THPO016 Design and Implementation the LLC Resonant Transformer impedance, simulation, controls 3370
 
  • C.-Y. Liu, Y.S. Wong
    NSRRC, Hsinchu, Taiwan
 
  The energy and dc to dc conversion voltage waveform of the LLC resonant transformer are required to achieve optimal working condition of the resonant region frequency. To meet this requirement, a reliable and precise instrument is needed to scan the resonant cure of the LLC resonant transformer such that its output power performance can meet the required specification. In this paper, the design and model of a new LLC resonant transformer deployed in NSRRC is described. This LLC resonant transformer is capable of delivering energy conversion with high efficiency performance, which is better than traditional transformer, and the voltage transfer ratio is depended on the resonant Frequency. Using the simulation circuit model to develop a power converter of it is also included in the design of this new LLC resonant transformer. It has been tested and proven to be working well in power conversion with excellent efficiency and performance.  
 
THPO017 Improvement of Output Current Characteristics for Bira MCOR30 Correction Magnet Power Supply controls, HOM, feedback, storage-ring 3373
 
  • J.C. Huang, K.-B. Liu, Y.S. Wong
    NSRRC, Hsinchu, Taiwan
 
  The correction magnet power supplies installed at the Taiwan light source (TLS) are Bira Systems’ MCRO 30 power modules, a full-bridge configuration power stage converting the unregulated DC bulk power into a bi-polar current source. The MCOR 30 is theoretically regulated under a very fine control method, with this control method the Bira MCOR 30 should overcome the zero crossover distortion of a standard H-Bridge PWM schemes is used and result in a low frequency noise signature on the output when the magnet current is close to zero. The PWM control circuitry embedded in MCOR 30 theoretically but not really fulfills the purpose what the MCOR 30 want to achieve. With a home-made PWM control circuitry installed into MCOR 30, the width of real pulses can smoothly drop to zero, the MCOR 30 could output current not only with a low frequency noise signature but also much with higher bandwidth of frequency response and much lower Total Harmonic Distortion no matter what output current is demanded.  
 
THPO018 N+1 Redundancy Power Supply System by Paralleling Current Converter Modules with Digital Regulation Control controls, feedback, simulation, storage-ring 3376
 
  • B.S. Wang, K.-B. Liu, Y.S. Wong
    NSRRC, Hsinchu, Taiwan
 
  The N+1 redundancy power supply system is fulfilled with adopting the Bira System MCOR30s as a platform, eight pieces of Bira MCOR 30 power converter boards are installed at crate 2512 and outputs are connected together, the output current of these paralleled eight Bira MCOR 30 power converters are regulated by an external homemade digital control circuit. With homemade digital control circuit, these paralleled eight Bira MCOR 30 power converter modules could deliver up to 240A/30V with ±20ppm precision and stability. The digital regulation control circuit of the N+1 redundancy power supply system is implemented by using a multi-channel DAC5868 16-bits digital-to-analog converter (DAC)、a high speed AD8382 18-bits analog-to-digital converter and a TMS320F28335 digital signal processor (DSP). The update reference voltage frequency of DAC is 83.3 kHz. A DCCT is used as the current feedback component and the output current ripple of the N+1 redundancy power supply system is lower than 20ppm which is beyond the requirement of current TLS quadruple and sextuple power supplies and qualified to be used in the future TPS facility.  
 
THPO019 TPS Fast Corrector Magnet Power Converter feedback, booster, controls, monitoring 3379
 
  • Y.D. Li, K.-B. Liu
    NSRRC, Hsinchu, Taiwan
 
  With the increasing demand of the current output accuracy on the TPS(Taiwan Photon Source) project, the MCOR 30 correction power supplies used in current TLS ring are no longer sufficient to meet the TPS requirement. Therefore, power supply group developments a high-precision low output current power supply with a DCCT as an output current feedback component for correction magnets of the future TPS ring. During the research and development experiment phase, we found the DCCT is more possible damaged than the other components. With keeping the architecture of the high-precision low output current power supply, but the DCCT output current feedback component is replaced with a current sensing Shunt resistor. This paper will discuss the design methods of utilizing several different types current sensing Shunt resistor to reduce the cost of power supply and the probability of damage, and improve frequency response of power supply.  
 
THPO021 A New Control System for the ISIS Main Magnet Power Supply controls, status, target, synchrotron 3385
 
  • J. Ranner, T.E. Carter, S. West
    STFC/RAL/ISIS, Chilton, Didcot, Oxon, United Kingdom
 
  The ISIS pulsed neutron and muon source at the Rutherford Appleton Laboratory in Oxfordshire is a world-leading centre for research in the physical and life sciences. At the heart of the ISIS accelerator is a proton synchrotron which uses a ring of dipole and quadrupole magnets connected in series and configured as a White Circuit*. The circuit allows the magnets to be fed with an AC current superimposed on a DC current. A recent upgrade to the main magnet power supply** involved the replacement of the original AC supply, a motor-alternator set, with a bank of four 300kVA UPS (uninterruptible power supplies) which had been modified to allow the output voltage to be varied using serial commands. However, when initially tested, this method was unable to produce the required stability in the main magnet current. This paper describes the further modifications to the UPS units to achieve the required stability and the development of a LabVIEW control system which manages the data acquisition and analysis, the communication to the UPS, interlock equipment and user interface, and provides a low latency control loop to the UPS and DC bias power supplies.
* M.G. White et al., “A 3-BeV High Intensity Proton Synchrotron”, CERN Symp.1956 Proc., p525.
** S. West, J.W. Gray, W.A. Morris, “Upgrade of the ISIS Main Magnet Power Supply”, EPAC 2004 p1467.
 
 
THPO022 Risk Assessment of the Chopper Dipole Kicker Magnets for the MedAustron Facility dipole, controls, kicker, radiation 3388
 
  • T. Kramer, T. Stadlbauer
    EBG MedAustron, Wr. Neustadt, Austria
  • M.J. Barnes, M. Benedikt, T. Fowler
    CERN, Geneva, Switzerland
 
  The MedAustron facility, to be built in Wiener Neustadt (Austria), will provide protons and ions for both cancer therapy and research. Different types of kicker magnets will be used in the facility, including fast beam chopper dipoles: these allow the beam to be switched on and off for routine operational reasons or in case of emergency. One of the main requirements for the beam chopper system is reliability. A criticality analysis, to chart the probability of failure modes against the severity of their consequences of the fault, has been carried out for the chopper dipole system. This “Failure Mode, Effects, and Criticality Analysis” (FMECA), has been used to highlight failure modes with relatively high probability and severity of consequences: conservative ratings of critical components and appropriate redundancy, together with measurements and interlocks, have been used to reduce the probability and criticality of faults. This paper presents the results of the FMECA.  
 
THPO027 Novel Switching Power Supply utilizing SiC-JFET and its Potential for the Digital Accelerator induction, synchrotron, extraction, high-voltage 3400
 
  • K. Okamura, T. Iwashita, K. Takayama, M. Wake
    KEK, Ibaraki, Japan
  • K. Ise
    Tohoku Electric Power Co., Sendai, Japan
  • Y. Osawa
    SUN-A Corporation, Miyoshi-City, Japan
  • K. Takaki
    Iwate university, Morioka, Iwate, Japan
 
  Funding: Japan Science and Technology Agency
New induction synchrotron system using an induction cell has been developed and constructed at KEK*. We refer to the accelerator using the induction acceleration system combined with digitally controlled PWM power supply as "Digital Accelerator". In that system, the switching power supply is one of the key devices which realize digital acceleration. The requirements of the switching power supply are high voltage (2 kV) and high repetition frequency (1 MHz). In the present system, we used series connected MOSFETs as the switching device and obtained successful operation. However, series connection gives large complexity and less reliability. Among the various switching devices, a SiC-JFET is the promising candidates that substitute existing silicon MOSFET because it has ultrafast switching speed and voltage blocking capability**. Therefore, we have started to develop new device in collaboration with device manufacturers. Switching and heat removal performance of the newly developed SiC-JFET and a future plan will be presented at the conference.
* T. Iwashita et al., “KEK Digital Accelerator”, Phys. Rev. ST-AB, published in 2011.
** K. Ise et al., IEEE Trans. Plasma Sci., pp. 730-736 (2011).
 
 
THPO028 Upgrade Design of the Bump System in the J-PARC 3-GeV RCS injection, linac, betatron, resonance 3403
 
  • T. Takayanagi, N. Hayashi, M. Kinsho, Y. Watanabe
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken, Japan
 
  The 3-GeV RCS aims at providing at least 300 kW output beam power with the injection beam at 181 MeV. In the second stage, the upgrade of the LINAC beam energy to 400 MeV was funded and started in March 2009. This plan will be completed in 2012. Consequently, the 3-GeV RCS will aim at 1 MW beam power. The injection bump system of the RCS is composed of the shift bump-magnets, the horizontal paint bump-magnets and the vertical paint magnets.  
 
THPO036 Final Layout and Test Results of the Disconnect Switch for ALS Storage Ring RF System Power Supply high-voltage, klystron, vacuum, fibre-optics 3421
 
  • S. Kwiatkowski, K.M. Baptiste, J. Julian, M.E. Kennedy
    LBNL, Berkeley, California, USA
  • J. Miszczak
    SLCJ, Warsaw, Poland
 
  Funding: Work supported by the Director, Office of Science, Office of Basic Energy Sciences, Materials Science and Engineering Division, of the Department of Energy under contract No. DE-AC02-05CH11231.
ALS is the 1.9 GeV third generation synchrotron light source which has been operating since 1993 at Berkeley National Lab. The new RF system, which is now under construction will use two TH 2161B 300kW klystrons to power two single cell RF cavities. In the new design the existing conventional crow-bar klystron protection system will be replaced with the fast disconnect switch. The switch consist 24 high voltage IGBTs connected in series, equipped with static and dynamic balancing systems. The main advantage of using this new technology is faster action and virtually no stress for the components of the high voltage power supply. This paper will show the final lay-out and the test results of the production unit.
 
 
THPS048 Design of Electrostatic Septa and Fast Deflector for MedAustron septum, cathode, synchrotron, injection 3532
 
  • J. Borburgh, T. Fowler, A. Prost
    CERN, Geneva, Switzerland
  • T. Kramer, T. Stadlbauer
    EBG MedAustron, Wr. Neustadt, Austria
 
  For the MedAustron facility, under construction in Wiener Neustadt, three electric field deflectors are developed in collaboration with CERN. A fast deflector is used in the Low Energy Beam Transfer line to chop the beam. The chopped beam is swept onto a Faraday cup for measurement purposes and to stop beam being sent towards the synchrotron. Electrostatic septa are used for the multi turn injection of protons and ions as well as for the slow extraction from the synchrotron. Novel design features for MedAustron include an inversed cathode/anode support and high voltage feedthroughs rated at 150 kV. The possibility for a higher voltage will significantly improve the conditioning process of the septa surfaces. This paper describes the requirements of these devices as well as the mechanical design and strategies adopted for their power supplies.