A   B   C   D   E   F   G   H   I   K   L   M   O   P   Q   R   S   T   U   V   W   X    

power-supply

Paper Title Other Keywords Page
MOPCH097 CERN Proton Synchrotron Working Point Control Using an Improved Version of the Pole-face-windings and Figure-of-eight Loop Powering CERN, controls, injection, synchrotron 264
 
  • R.R. Steerenberg, J.-P. Burnet, M. Giovannozzi, O. Michels, E. Métral, B. Vandorpe
    CERN, Geneva
  The working point of the CERN Proton Synchrotron, which is equipped with combined function magnets, is controlled using pole-face-windings. Each main magnet consists of one focusing and one de-focusing half-unit on which four pole-face-winding plates are mounted containing two separate coils each, called narrow and wide. At present they are connected in series, but can be powered independently. In addition, a winding called the figure-of-eight loop, contours the pole faces and crosses between the two half units, generating opposite fields in each half-unit. The four optical parameters, horizontal and vertical tune and chromaticity, are adjusted by acting on the pole-face-winding currents in both half units and in the figure-of-eight loop, leaving one physical quantity free. The power supply consolidation project opened the opportunity to use five independent power supplies, to adjust the four parameters plus an additional degree of freedom. This paper presents the results of the measurements that have been made in the five-current mode together with the influence of the magnetic nonlinearities, due to the unbalance in the narrow and wide winding currents, on the beam dynamics.  
 
MOPCH114 Progress on Dual Harmonic Acceleration on the ISIS Synchrotron acceleration, synchrotron, proton, controls 309
 
  • A. Seville, D.J. Adams, D. Bayley, N.E. Farthing, I.S.K. Gardner, M.G. Glover, A. Morris, B.G. Pine, J.W.G. Thomason, C.M. Warsop
    CCLRC/RAL/ISIS, Chilton, Didcot, Oxon
  The ISIS facility at the Rutherford Appleton Laboratory in the UK is currently the most intense pulsed, spallation, neutron source. The accelerator consists of a 70 MeV H- Linac and an 800 MeV, 50 Hz, rapid cycling, proton Synchrotron. The synchrotron beam intensity is 2.5·1013 protons per pulse, corresponding to a mean current of 200 μA. The synchrotron beam is accelerated using six, ferrite loaded, RF cavities with harmonic number 2. Four additional, harmonic number 4, cavities have been installed to increase the beam bunching factor with the potential of raising the operating current to 300 μA. As ISIS has a busy user schedule the time available for dual harmonic work has been limited. However, much progress has been made in the last year and encouraging results have been obtained. This paper reports on the hardware commissioning and beam tests with dual harmonic acceleration.  
 
MOPCH164 Status of the Diamond Storage Ring Radio Frequency System DIAMOND, controls, storage-ring, pick-up 445
 
  • M. Jensen, M. Maddock, S.A. Pande, S. Rains, A. F. Rankin, D. Spink, A.V. Watkins
    Diamond, Oxfordshire
  • J. Alex, M. Mueller
    Thomson Broadcast & Multimedia AG, Turgi
  • B. A. Aminov
    CRE, Wuppertal
  • M. Pekeler
    ACCEL, Bergisch Gladbach
  The installation and commissioning of the Diamond Storage Ring RF system is nearing completion. Diamond will initially operate with two RF high power amplifiers and two cavities. The key components in each RF system are a 300 kW amplifier implemented through the combination of four 80 kW IOTs, a 500 MHz superconducting cavity providing up to 2 MV of accelerating voltage and an advanced analogue IQ Low Level RF (LLRF) system to control the cavity frequency, voltage and phase. We present here an update on the recent installation and early commissioning results of the RF systems.  
 
MOPLS023 Status of Fast IR Orbit Feedback at RHIC RHIC, feedback, dipole, injection 589
 
  • C. Montag, J. Cupolo, J. Glenn, V. Litvinenko, A. Marusic, W. Meng, R.J. Michnoff, T. Roser, C. Schultheiss, J.E. Tuozzolo
    BNL, Upton, Long Island, New York
  To compensate modulated beam-beam offsets caused by mechanical vibrations of IR triplet quadrupoles at frequencies around 10 Hz, a fast IR orbit feedback system has been developed. We report design considerations and recent status of the system.  
 
MOPLS090 Design of a Strip-line Extraction Kicker for CTF3 Combiner Ring kicker, impedance, simulation, CTF3 762
 
  • I. Rodriguez, F. Toral
    CIEMAT, Madrid
  • L. García-Tabarés
    CEDEX, Madrid
  • A. Ghigo, F. Marcellini
    INFN/LNF, Frascati (Roma)
  The new CLIC test facility (CTF3) is the latest stage to prove the technical feasibility of the CLIC project. An extraction kicker is necessary for the combiner ring, and it will be a strip-line type device due to lower coupling impedances and straightforward fabrication. The field uniformity together with a correct beam dynamics are the most challenging issues of this design. The main parameters of the kicker are analytically calculated using standard analytic formulae. The numeric modelling and simulation of several possible straight sections are reported, and the characteristic impedance is matched with the 50 Ω load. The field homogeneity, the kick angle and the scattering parameters are calculated in a 3D finite element model. Several manufacturing issues for the first prototype are also outlined.  
 
TUPCH025 Precision RF Gun Phase Monitor System for the VUV-FEL laser, gun, electron, acceleration 1052
 
  • H. Schlarb, N. Heidbrook, H. Kapitza, F. Ludwig, N. Nagad
    DESY, Hamburg
  For RF photo-injectors, the properties of the high brightness beam critically depend on the synchronization between the RF gun acceleration phase and the photo-cathode laser. At the VUV-FEL, the phase stability is determined by operating the RF gun close to zero-crossing RF phase. This allows the conversion of phase variations into charge variations which then is readout by a precision charge measurement system based on toroids. In this paper, we discuss the limitation of this method. Resolution reduction of the charge measurement system due to electro-magnetic-interference is discussed in detail.  
 
TUPCH131 High Power Test of MA Cavity for J-PARC RCS impedance, synchrotron, proton, acceleration 1322
 
  • M. Yamamoto, M. Nomura, A. Schnase, F. Tamura
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • S. Anami, E. Ezura, K. Hara, C. Ohmori, A. Takagi, M. Toda, M. Yoshii
    KEK, Ibaraki
  • K. Hasegawa
    JAEA, Ibaraki-ken
  We have been constructing the RF system for the J-PARC RCS. Almost all of the power supplies and the tube amplifiers have been constructed, and the cavities are under construction. All of them are tested at the experimental hall before installing into the J-PARC RCS building. We test the hybrid cavity scheme to realize the optimum cavity Q-value. The results of the test are described.  
 
TUPCH152 MICE RF Test Stand factory, target, controls, emittance 1379
 
  • P.A. Corlett, A.J. Moss, J.F. Orrett
    CCLRC/DL/ASTeC, Daresbury, Warrington, Cheshire
  The Muon Ionization Cooling Experiment (MICE) RF test stand is being assembled at Daresbury Laboratory. This will provide a test bed for power amplifiers to produce the 2MW 200MHz RF for the MICE experiment RF cavities. Initial design and proposed layout of the RF system are described.  
 
TUPCH153 IOT Testing at the ERLP ERLP, controls, klystron, DIAMOND 1382
 
  • J.F. Orrett, S.R. Buckley, P.A. Corlett, A.J. Moss
    CCLRC/DL/ASTeC, Daresbury, Warrington, Cheshire
  • S. Rains
    Diamond, Oxfordshire
  The testing of Inductive Output Tubes (IOT) at 1.3GHz is underway for use on the Energy Recovery Linac Prototype (ERLP) being constructed at Daresbury Laboratory. A 50KV high voltage power supply (HVPS) has been commissioned and characterised for use as a test RF supply. This will be used to power the ERLP RF system in both continuous and pulse modes of operation. First results are presented of the IOTs and the use of the HVPS system.  
 
TUPCH154 RF Amplifier for Next Generation Light Sources controls, monitoring, cathode, vacuum 1385
 
  • J.S. Przybyla, E. Radcliffe
    e2v Technologies, Essex
  This paper describes the design concepts and development issues around generating a compact 16kW 1.3GHz RF amplifier for use in the next generation of light sources. These amplifiers need to be operated for extended periods to maximise use of the facility and so high reliability and availability are of key importance. Equally important are the capabilities to have extensive self-monitoring and fault prediction, autonomous operation, low heat dissipation to air, and easy maintenance. The design and development of such an RF amplifier based on the latest e2v technologies 1.3GHz inductive output tube (IOT) will be described. The RF amplifier equipment makes extensive use of commercially available products and industry collaborations to produce an amplifier that meets all the requirements yet can be manufactured and operated in a most cost effective manner. Prototype equipment will be shown at EPAC 06.  
 
TUPCH162 Operation Results of 1 MW RF Systems for the PEFP 20 MeV Linac klystron, rfq, proton, linac 1402
 
  • K.T. Seol, Y.-S. Cho, H. S. Kim, H.-J. Kwon
    KAERI, Daejon
  • K.R. Kim
    PAL, Pohang, Kyungbuk
  The PEFP 20 MeV linear accelerator is composed of a 3 MeV RFQ and 20 MeV DTL. Two sets of 1MW, 350MHz RF systems drive the RFQ and DTL. The RF system can perform a 100% duty operation. The TH2089F klystron is used as an RF source. During the test operation, only the driving RF signal of the klystron was operated in pulse mode, while the electron beam was maintained in DC mode. The klystron power supplies and cooling systems were also operated in 100% duty mode. In this paper, the operation results of 1 MW RF systems including klystron power supply and cooling system are discussed and propose possible options to improve the operation conditions based on the results.  
 
TUPCH200 Amplitude Linearizers for PEP-II 1.2 MW Klystrons and LLRF Systems klystron, controls, feedback, impedance 1480
 
  • D. Van Winkle, J. Browne, J.D. Fox, T. Mastorides, C.H. Rivetta, D. Teytelman
    SLAC, Menlo Park, California
  The PEP-II B-factory has aggressive current increases planned for luminosity through 2008. At 2.2 A (HER) on 4 A (LER) currents, longitudinal growth rates will exceed the damping rates achievable in the existing low level RF and longitudinal low mode feedback systems. Klystron gain non-linearity has been shown to be a key contributor to these increased growth rates through time domain non-linear modeling and machine measurements. Four prototype klystron amplitude modulation linearizers have been developed to explore improved linearity in the LLRF system. The linearizers operate at 475 MHz with 15 dB dynamic range and 1 MHz linear control bandwidth. Results from lab measurements and high current beam tests are presented. Future development progress and production designs are detailed.  
 
TUPLS076 Beam Extraction of 150 MeV FFAG extraction, septum, kicker, KEK 1672
 
  • M. Aiba, Y. Mori, H. Nakayama, K. Okabe, Y. Sakamoto, A. Takagi
    KEK, Ibaraki
  • R. Taki
    GUAS/AS, Ibaraki
  • Y. Yonemura
    Kyushu University, Fukuoka
  A beam extraction from FFAG accelerator was performed for the first time at KEK 150MeV proton FFAG synchrotron. The purpose of 150MeV FFAG project is to establish a working prototype for various applications. The beam extraction is thus one of important goals. The extraction is based on fast extraction methode using kicker and pulse septum working at 100Hz. A rapid cycling is also our focus to take advantages of FFAG accelerator. Beam extraction experiment was successful under 100Hz operating. The details of experiment will be presented in this paper.  
 
TUPLS106 Pulsed Bending Magnet of the J-PARC MR TESLA, synchrotron, simulation, KEK 1747
 
  • K. Koseki, H. Kobayashi, H. Nakayama, K.O. Okamura, M.J. Shirakata, M. Tawada
    KEK, Ibaraki
  Japan Proton Accelerator Research Complex (J-PARC) is under construction with a collaboration between Japan Atomic Energy Agency (JAEA) and High Energy Accelerator Research Organization (KEK). The J-PARC consists of a 180 MeV linac, a 3 GeV rapid-cycle synchrotron (RCS) and a 50 GeV synchrotron (MR). The bunch trains, which extracted from the RCS, is delivered both to the “Materials and Life Science Facility” and to the MR, two beam transport lines, 3-NBT and 3-50BT, are constructed. The switching of bunch trains is performed by a pulsed bending magnet. The field strength of 1.21 Tesla with rise and fall time of less than 40 msec is required. It was found that an effect induced by eddy current, which flows at thick end-plates, disturbs the flatness of the magnetic field. A simple compensation circuit has been adopted for a cure. A result from a field measurement, which shows a sufficient flatness, is presented.  
 
TUPLS107 Operation of the Opposite-Field Septum Magnet for the J-PARC Main-Ring Injection septum, injection, vacuum, dipole 1750
 
  • I. Sakai, Y. Arakaki, K. Fan, Y. Saito, M. Tomizawa, M. Uota
    KEK, Ibaraki
  • A.K. Kawasaki, H. Mori, A. Tokuchi
    NICHICON, Shiga
  • Y. Morigaki, A. Nishikawa
    IHI/Yokohama, Kanagawa
  The opposite field septum magnet system has been applied to the injection system of the J-PARC 50-GeV proton synchrotron. The features of the system are a force-free structure, easy pulse excitation and the possibility of a large-aperture, thin-septum structure. The septum magnet has the structure of an inside-vacuum to eliminate the thickness of the vacuum-chamber walls and electric-insulation layer to make the septum thickness as thin as possible. However the magnet cores and return coils are outside of the vacuum to reduce the out-gassing rate of the vacuum system. Finally, the larger beam aperture than the full acceptance of the ring and larger separation angle can be obtained at the septum magnet for low-loss injection. In this paper we will introduce the methods to eliminate the error fields caused by fabrication errors and eddy current with pulse excitation and stability of high current power supply of 50 kA.  
 
TUPLS111 Experimental Results of the Shift Bump Magnet in the J-PARC 3-GeV RCS injection, extraction, linac, controls 1762
 
  • T. Takayanagi, Y. Irie, J. Kamiya, M. Kinsho, M. Kuramochi, O. Takeda, T. Ueno, M. Watanabe, Y. Yamazaki, M. Yoshimoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  The shift bump magnet produces a fixed main bump orbit to merge the injection beam into the circulating beam. In order to control the injection beam for the short injection time (500 microseconds) with sufficient accuracy, the shift bump magnet needs a wide uniform magnetic field and the high speed exciting pattern of the high current. The magnetic field design and the structural analysis of the shift bump magnets have been performed using three-dimensional electromagnetic analysis code and mechanical analysis code, respectively. The magnetic field distributions were measured with a long search coil, thus giving a BL product over a magnet gap area. The temperature distributions at the various points of the magnet were measured by thermocouples over 24 hours till they saturated. General trend of these measurements agrees well with calculations.  
 
TUPLS136 Air Temperature Analysis and Improvement for the Technical Zone at TLS controls, vacuum, simulation, storage-ring 1825
 
  • J.-C. Chang, J.-R. Chen, Z.-D. Tsai
    NSRRC, Hsinchu
  • M. Ke
    NTUT, Taipei
  This paper presents the air temperature analysis and control improvement for the technical zone, where many critical instrumentations of power supply, rf, vacuum and control apparatuses are located, at the Taiwan Light Source (TLS). The technical zone with circular shape is located on the core area of the storage ring. The diameter and height of the technical zone are 28.5m and 3m, respectively. Totally 13 temperature sensors are installed in this zone to online record the air temperature history. Because of insufficient cooling capacity and poor air circulation of the air-conditioning (A/C) system, the air temperature may reach to 30 degrees C, and spatial air temperature difference may be more than 7 degrees C. To cope with those problems, a computational fluid dynamics (CFD) code is applied to simulate the spatial temperature distribution. The A/C cooling capacity will be increased, and the air exit and exhaust distribution will be modified according to the simulated results.  
 
WEPCH023 Longitudinal Coherent Oscillation Induced in Quasi-isochronous Ring synchrotron, electron, storage-ring, closed-orbit 1972
 
  • Y. Shoji, Y. Hisaoka, T. Matsubara, T. Mitsui
    NewSUBARU/SPring-8, Laboratory of Advanced Science and Technology for Industry (LASTI), Hyogo
  Noise sources, which excite longitudinal coherent oscillation is discussed. Especially in a quasi-isochronous electron storage ring an identification of the noise sources is important to obtain an extremely short bunch. One possible source is a well-known rf noise in the acceleration field. The other is a magnetic field ripple, which changes a path-length for a revolution. The analytical formula for the longitudinal coherent oscillation is explained. It contains the path-length oscillation, which had never been considered. The third is a beam itself, probably be a coherent radiation loss. The driving term is not symmetric along the energy axis, then the oscillation amplitude depends on the higher order momentum compaction factor.  
 
WEPCH047 Procedures and Accuracy Estimates for Beta-beat Correction in the LHC LHC, quadrupole, simulation, coupling 2023
 
  • R. Tomas, O.S. Brüning, S.D. Fartoukh, M. Giovannozzi, Y. Papaphilippou, F. Zimmermann
    CERN, Geneva
  • R. Calaga, S. Peggs
    BNL, Upton, Long Island, New York
  • F. Franchi
    GSI, Darmstadt
  The LHC aperture imposes a tight tolerance of 20% on the maximum acceptable beta-beat in the machine. An accurate knowledge of the transfer functions for the individually powered insertion quadrupoles and techniques to compensate beta-beat are key prerequisites for successful operation with high intensity beams. We perform realistic simulations to predict quadrupole errors in LHC and explore possible ways of correction to minimize beta-beat below the 20% level.  
 
WEPCH139 WISE: An Adaptative Simulation of the LHC Optics LHC, simulation, CERN, quadrupole 2248
 
  • P. Hagen, M. Giovannozzi, J.-P. Koutchouk, T. Risselada, S. Sanfilippo, E. Todesco, E.Y. Wildner
    CERN, Geneva
  The LHC beam dynamics requires a tight control of the magnet field quality and geometry. As the production of the magnets advances, decisions have to be made on the acceptance of possible imperfections. To ease decision making, an adaptative model of the LHC optics has been built, based on the current information available (e.g. magnetic measurements at warm or cold, magnet allocation to machine slots) as well as on statistical evaluations for the missing information (e.g. magnets yet to be built, measured, or for non-allocated slots). The uncertainties are included: relative and absolute measurement errors, warm-to-cold correlations for the fraction of magnets not measured at cold, hysteresis and power supply accuracy. A pre-processor generates instances of the LHC ring for the MADX program, with the possibility of selecting various error sources. A post-processor computes ranges for relevant beam optics parameters and distributions. This approach has been applied to the expected beta-beating, to the possible impact of permeability issues in some quadrupole collars, to the geometrical displacements of the multipolar correctors and to prioritize the magnetic measurement programme.  
 
WEPCH192 Compact Electron Linear Accelerator RELUS-5 for Radiation Technology Application electron, vacuum, controls, feedback 2385
 
  • D.A. Zavadtsev, A.I. Fadin, A.A. Krasnov, N.P. Sobenin
    MEPhI, Moscow
  • A.A. Zavadtsev
    Introscan, Moscow
  The electron linear accelerator for radiation technology application is designed to meet the following main requirements: 3-5 MeV energy, 3-6 microsecond pulse width, and 1 kW average beam power. The accelerating system is a 0.5 m long S-band standing wave on-axis coupled biperiodic structure. A 35-40 kV electron gun with spherical cathode is used as the injector. The RF generator is a 2.5 MW peak power 4 kW average power magnetron. The generated frequency is stabilized by a high Q-factor accelerating system connected into feed-back of the magnetron. The magnetron is fed by a compact 45-55 kV IGBT based modulator. The accelerator is controlled through a PLC-based control system.  
 
WEPLS114 Progress on the MICE Tracker Solenoid vacuum, radiation, emittance, superconductivity 2646
 
  • M.A. Green, S.P. Virostek
    LBNL, Berkeley, California
  • W. Lau, S.Q. Yang
    OXFORDphysics, Oxford, Oxon
  This report describes the 400 mm warm bore tracker solenoid for the Muon Ionization Cooling Experiment (MICE). The 2.923 m long tracker solenoid module includes the radiation shutter between the end absorber focus coil modules and the tracker as well as the 2.780 meter long magnet cryostat vacuum vessel. The 2.554 m long tracker solenoid consists of two sections, a three-coil spectrometer magnet and a two-coil matching section that matches the uniform field 4 T spectrometer solenoid into the MICE cooling channel. The two tracker magnets are used to provide a uniform magnetic field for the fiber detectors that are used to measure the muon beam emittance at the two ends of the cooling channel. This paper describes the design for the tracker magnet coils and the 4.2 K cryogenic coolers that are used to cool the superconducting magnet. Interfaces between the magnet and the detectors are discussed.  
 
WEPLS118 The 3Hz Power Supplies of the SOLEIL Booster dipole, booster, SOLEIL, synchrotron 2652
 
  • P. Gros, S. Bobault, A. Loulergue
    SOLEIL, Gif-sur-Yvette
  SOLEIL is a 2.75 GeV new third generation synchrotron radiation facility under construction near Paris. The injector system is composed of a 100 MeV electron Linac pre-accelerator followed by a full energy (2.75 GeV) booster synchrotron. A repetition rate of 3Hz is required for the booster for the filling of the Storage Ring together with the need for discontinuous operation for top-up filling mode. Based on digital regulation loop, the four power supplies (2 for the dipoles 600 A x 1000 V and 2 for the quadrupoles 250 A x 450 V) reach the current tracking tolerance specification of 10-3. The aim of this paper is to describe the main issues from the loads to the mains network through the power converters that are essential to reach the required performances.  
 
WEPLS119 Power Converters for the ISIS Second Target Station Project (TS-2) controls, septum, proton, pulsed-power 2655
 
  • S.L. Birch, A. Morris, S.P. Stoneham
    CCLRC/RAL/ISIS, Chilton, Didcot, Oxon
  The Extract Proton Beamline to the ISIS second target station will require magnets to be powered by ac/dc power converters. A total of 50 magnets, quadrupole and dipole, require high stability dc current converters over a large dynamic range from several kW to 600kW. There is also a requirement for two 10Hz pulsed magnets to extract the proton beam from the present 50Hz target beamline, and hence specially designed power supplies are necessary. This paper describes the selection process, types of topology considerations and final selections.  
 
WEPLS122 Multiphase Resonant Power Converter for High Energy Physics Applications controls, radio-frequency, feedback, klystron 2658
 
  • M.J. Bland, J. Clare, P. W. Wheeler
    University of Nottingham, Nottingham
  Accelerators used for experiments in high-energy physics require very high power radio frequency sources to provide the energy needed to accelerate the particles. The RF power needs to be stable and predictable such that any variation in the supplied RF power has a limited and acceptable impact on the accelerated beam quality. This paper considers the design of a "long-pulse" modulator supply rated at 25kV, 10A (250kW peak power, duty ratio 10%, 25kW average power, pulse length ≈ 1 − 2ms). The supply is based on direct modulation of a multi-phase resonant power supply, fed by an active rectifier. The objectives of the development are to produce a compact power supply, with low stored energy and with high power quality at the utility supply. The paper provides a brief overview of the technology, followed by a discussion of the design choices. Initial results from the laboratory prototype will be included.  
 
WEPLS123 Initial Experimental Results of a New Direct Converter for High Energy Physics Applications controls, radio-frequency, booster, target 2661
 
  • D. Cook, M. Catucci, J. Clare, P. W. Wheeler
    University of Nottingham, Nottingham
  • C. Oates
    Areva T&D, Stafford
  • J.S. Przybyla, R. Richardson
    e2v Technologies, Essex
  This paper presents practical results for a new type of power supply for high energy physics CW applications. The converter is a direct topology operating with a high frequency (resonant) link. Losses are minimised by switching at zero current. High operating frequency reduces the filter and transformer size. The transformer uses the latest nano-crystalline materials to further reduce losses. Where possible, circuit elements are incorporated into the transformer to reduce the physical size of the converter. Design of this transformer to accommodate the insulation, VA rating and circuit elements is non-trivial. The Radio Frequency power generated is stable and predictable, whilst the reduced energy storage in filter components removes the need for crowbar circuits. Potential benefits of this converter when compared to conventional approaches are discussed. These include reduced energy storage, reduced turn-on time and enhanced energy density when compared with existing topologies. Preliminary practical results are promising and are presented along with simulation results.  
 
WEPLS125 Diamond Storage Ring Magnet Power Converters controls, dipole, quadrupole, sextupole 2667
 
  • R.J. Rushton, C.A. Abraham, J.A. Dobbing
    Diamond, Oxfordshire
  • F. Cagnolati, G. Facchini, M.P.C. Pretelli, V.R. Rossi, L. Sita
    O.C.E.M. S.p.A., Bologna
  • C. Rossi
    CASY, Bologna
  The DC Magnet Power Converter requirements for the Storage Ring of the Diamond Project are described together with performance, commissioning and initial operating experience. In addition to meeting the required performance, emphasis during the design phase was placed on reliability and minimising the mean time to repair a power converter. A modular design, built-in redundancy, EMC filtering and testing, component de-rating and standardisation have all been adopted. The power modules for the 200A supplies were subject to highly accelerated stress screening. All converters are switched mode with full digital control and a common control interface. Every power converter appears identical to the Controls Network, from the lowest power corrector up to the 800 kW Storage Ring Dipole Converter.  
 
WEPLS126 CNAO Resonance Sextupole Magnet Power Converters controls, sextupole, proton, ion 2670
 
  • M.F. Farioli, F. Burini, S. Carrozza, M. Cavazza, S. Minisgallo, M.P.C. Pretelli, G. Taddia
    O.C.E.M. S.p.A., Bologna
  • D. Bagnara, M. Spera, A. Tilli, M. Toniato
    CASY, Bologna
  • I. De Cesaris
    CNAO Foundation, Milan
  • M. Incurvati, C. Sanelli
    INFN/LNF, Frascati (Roma)
  The CNAO Resonance Sextupole Magnet Power Converter requirements for the Storage Ring of the CNAO Project are described together with performance and initial operating experience. In particular the achieved performances will be compared with the specification and the extensive modelling that was done during the design phase. Not only the tight required performances were emphasized during the design phase but also particular attention was put on reliability and minimization of the repairing time (MTTR). Some fundamental criteria, like component de-rating and standardisation, have also been taken into account during the component choice phase. All converters adopt the switching technology with full digital control and a common control interface, that, as for the other CNAO power converters, uses the same digital controller, under licence from the Diamond Light Source.  
 
WEPLS127 CNAO Storage Ring Dipole Magnet Power Converter 3000A / ±1600V controls, dipole, synchrotron, simulation 2673
 
  • M.P.C. Pretelli, F. Burini, S. Carrozza, M. Cavazza, M.F. Farioli, S. Minisgallo, G. Taddia
    O.C.E.M. S.p.A., Bologna
  • I. De Cesaris
    CNAO Foundation, Milan
  • M. Incurvati, C. Sanelli
    INFN/LNF, Frascati (Roma)
  • F. Ronchi, C. Rossi, M. Spera, M. Toniato
    CASY, Bologna
  This paper will describe the design and simulations of the CNAO Dipole Power Converter rated 3000A / ±1600V. The Power Converter will feed the 16+1 synchrotron bending dipole magnets of the CNAO Storage Ring. The actual design confirms how the choice of a 24-pulses, 4 bridges series-parallel connected, active filter, bipolar voltage, meets the stringent requested technical specification ( 10-5 of maximum current for the output current residual ripple and setting resolution). The extensive modelling will also be presented. The design includes the strength of the topology design, component de-rating and component standardisation. As the other CNAO power converters, the Storage Ring Dipole Power Converter uses the same digital controller, under licence from the Diamond Light Source.  
 
WEPLS128 The Italian Hadrontherapy Center (CNAO): A Review of the Power Supply System for Conventional Magnets synchrotron, dipole, quadrupole, controls 2676
 
  • M. Incurvati, C. Sanelli
    INFN/LNF, Frascati (Roma)
  • L. Balbo, N. Balbo, A. Tescari
    EEI, Vicenza
  • F. Burini, S. Carrozza, M. Cavazza, M.F. Farioli, S. Minisgallo, M.P.C. Pretelli, G. Taddia
    O.C.E.M. S.p.A., Bologna
  • I. De Cesaris
    CNAO Foundation, Milan
  A hadron (Carbon/Proton) medical centre based on a synchrotron accelerator dedicated to the cure of deep tumours is under construction in Pavia (Italy) under the joint responsibility of CNAO (Centro Nazionale di Adroterapia Oncologica) and INFN (Istituto Nazionale di Fisica Nucleare). This paper describes the power supply system, made up of about 200 units designed by LNF, and whose converters for the synchrotron ring and related low, medium and high energy transfer lines are now under construction by the major Italian companies. The power supplies requirements and electrical characteristics will be reported describing the most interesting topologies that fulfill the requested performances together with the main features of each power supply topology. Synchrotron dipoles, quadrupoles, sextupoles and resonance sextupole power supplies have tight characteristics with respect to precision class (current resolution, residual ripple, short-long term stability, etc.) that range from 5 ppm to 500 ppm, fast dynamical response with bandwidth up to some hundreds hertz, high power from tens of kW to many MW and output current ranging from hundreds of A to 3 kA.  
 
WEPLS129 Upgrade Scheme for the J-PARC Main Ring Magnet Power Supply KEK, linac, synchrotron, extraction 2679
 
  • H. Sato, K. Koseki, K.O. Okamura, t.s. Shintomi
    KEK, Ibaraki
  Japan Proton Accelerator Research Complex (J-PARC) is under construction at the Tokai campus of Japan Atomic Energy Agency (JAEA) as a joint project between KEK and JAEA. The accelerator complex, which is constructed as a 200 MeV linac, a 3 GeV RCS synchrotron, and a main ring in phase I. The main ring magnet power supply is constructing as the energy of 40 GeV in phase I and will upgrade up to 50 GeV in phase II. A large amount of pulse electric power, which is + 115 MW and -55 MW peak-to-peak, is required for 50 GeV operation and this large pulse power will give unallowable disturbances to a power network. In order to compensate the disturbances to allowable level, we need some energy storage system. A SMES system will be one of the promising means for the purposes as well as the fly-wheel system. We will describe some energy storage system and also the increasing of repetition rate without energy storage system.  
 
WEPLS131 Programmable Power Supply for Distribution Magnet for 20-MeV PEFP Proton Linac controls, proton, extraction, damping 2682
 
  • S.-H. Jeong, J. Choi, H.-S. Kang, D.E. Kim, K.-H. Park
    PAL, Pohang, Kyungbuk
  The distribution magnet is powered by bipolar switching-mode converter that is employed IGBT module and has controlled by a DSP (Digital Signal Process). This power supply is operated at 350A, 5 Hz programmable stair output for beam distribution to 5 beamlines of 20-MeV PEFP proton linac. Various applications for the different power supply are made simple by software. This paper describes the design and test results of the power supply.  
 
WEPLS132 New Magnet Power Supply for PAL Linac linac, controls, quadrupole, damping 2685
 
  • S.-C. Kim, J. Choi, K.M. Ha, J.Y. Huang, J.H. Kim, S.H. Kim, I.S. Ko, S.S. Park
    PAL, Pohang, Kyungbuk
  Since the completion of PLS in 1994, PLS Linac magnet power supply(MPS) has been operated for 12 years with 12-bit resolution and 0.1% stability. Improvement in the resolution and the reliability of the Linac MPS is highly required now for the stable beam injection and 4th generation light source research. To improve MPS, we developed new compact MPS of 16-bit resolution and 20ppm stability using four-quadrant switching scheme with 50kHz MOSFET switching device. Bipolar MPS for corrector magnet consists of main power board, control power board, regulator board and CPU board. Size of each board is only 100mm width and 240mm depth. Unipolar MPS for quadrupoles and solenoid magnets is composed by parallel-operation of two main power boards, doubling the current output. Output of MPS is 10V, ±10A for the bipolar and 50V, 50A for the unipolar magnet. In this paper, we report on the development and characteristics of the new MPS for PAL linac.  
 
WEPLS133 Stability Study of Superconductor Magnet Power Supplies at TLS controls, superconducting-magnet, insertion, insertion-device 2688
 
  • Y.-C. Chien, K.-T. Hsu, C.-S. Hwang, C.-Y. Liu, K.-B. Liu
    NSRRC, Hsinchu
  In this paper, performance of three power supplies schemes driving the newly-developed Superconducting Wave Length Shifter Magnet at TLS is investigated. Due to the inherent structure of the Superconducting Magnet, the main and two accessory trimming power supplies are physically correlated with each others. Due to the inherent structure, in order to achieve high performance control of the magnet, slew rate control of the main power supply and the proper operation sequence have to be properly managed, otherwise, small current disturbance can occurs, which may disgrade the stability of the performance of Superconducting Magnet.  
 
WEPLS134 Design and Modeling of the Step Down Piezo Transformer impedance, controls, simulation, feedback 2691
 
  • C.-Y. Liu, Y.-C. Chien, K.-B. Liu
    NSRRC, Hsinchu
  The energy conversion and the step down voltage waveform of the piezo transformer are required to achieve optimal working condition of the resonate frequency. To meet this requirement, a reliable and precise instrument is needed to scan the resonated point of the piezo transformer such that the piezo transformer's output performance can meet required specification. In this paper, design and modeling of a new step down piezo transformer deployed in NSRRC is described. This step down piezo transformer is capable of delivering energy conversion with high efficiency performance, which is better than traditional transformer, and the voltage transfer ratio is correct. The simulation circuit model used to develop driver circuit of the piezo transformer is also included in the design of this new step down transformer. It has been tested and proven to be working well in power conversion with excellent efficiency and reliability.  
 
WEPLS136 Pulsed Magnet Power Supplies for Improved Beam Trajectory Stability at the APS septum, booster, injection, extraction 2697
 
  • B. Deriy, L. Emery, A.L. Hillman, G.S. Sprau, J. Wang
    ANL, Argonne, Illinois
  New power circuit and control electronics have been implemented in the septum power supplies at the Advanced Photon Source (APS). The goal was to meet a low pulse-to-pulse relative amplitude jitter of about ± 5·10-4 for trajectory stability in the booster-to-storage ring transport line. The original power supply design produced a jitter of ± 15e-4, which made injection tuning difficult. The jitter for the two new booster pulsed magnet supplies is now 1.1e-4, as inferred by a beam-based statistical analysis. A common design was made for all of the septum magnet power supplies at the APS. The system, regulation algorithms, the results achieved, and the current regulation stability issues will be discussed.  
 
WEPLS143 SLS Operation Management: Methods and Tools controls, SLS, feedback, diagnostics 2715
 
  • A. Lüdeke
    PSI, Villigen
  Users of 3rd generation synchrotron light sources desire not only a high flux on their samples and sub-micron beam stability, they expect at the same time a beam availability close to 100 percent. To reach and maintain a very high availability put special demands on the operation management of a light source. We will illustrate the procedures used at the Swiss Light Source (SLS) to deal with beam interruptions and explain the tools used for operation management.  
 
THPCH102 Fast Global Orbit Feedback System in SPEAR3 feedback, controls, undulator, diagnostics 3035
 
  • A. Terebilo, T. Straumann
    SLAC, Menlo Park, California
  New digital global orbit feedback system is under commissioning in SPEAR3 light source. The system has 4kHz sampling rate and 200Hz bandwidth. Correction algorithm is based on Singular Value Decomposition (SVD) of the orbit response matrix. For performance tuning and additional flexibility when adding or removing correctors and BPMs, we implemented an independent PID control loop for every orbit eigenvector used. This paper discusses performance of the new system and some advantages of multiple PID loops in the eigenvector space versus a single PID loop working on the raw orbit error.  
 
THPCH117 Synchronized Data Monitoring and Acquisition System for J-PARC RCS monitoring, controls, beam-losses, synchrotron 3077
 
  • H. Takahashi, Y. Ito, Y. Kato, M. Kawase, H. Sakaki, T.S. Suzuki
    JAEA, Ibaraki-ken
  • M. Sugimoto
    Mitsubishi Electric Control Software Corp, Kobe
  J-PARC RCS* is a proton synchrotron with an extreme high power of 1MW, and delicate care must be taken to suppress radiation due to beam loss. The RCS injects each beam pulse of 25 Hz into the MLF** and the MR*** in a predefined order. Furthermore, the different beam control parameters are required for the MLF and the MR. Therefore, in order to reduce beam loss, synchronicity of data is indispensable. For this reason, control data monitoring and acquisition must be made separately for each beam pulse, distinguishing the destination in the control system. The data, which require synchronicity monitoring and acquisition, are such as beam position data (BPM**** data). We select mainly these data, and we are developing the synchronized data monitoring and acquisition system based on RM*****, WER******. The status of development and some test results for this system will be presented in this report.

*Rapid-cycling Synchrotron **Materials and Life Science Facility ***50 GeV Main Ring ****Beam Position Monitor *****Reflective Memory ******Wave Endless Recorder

 
 
THPCH118 Development of the Event Notice Function for PLC controls, target 3080
 
  • M. Kawase, H. Takahashi
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
  • T. Ishiyama
    MELCO SC, Tsukuba
  A lot of equipment which controls in J-PARC accelerator composition machinery using PLC (Programmable Logic Controller) exists. The transmitting method to upper control systems, such as interlock information on accelerator composition apparatus, state changes information, and information on the right of control operation, is not performed by polling. The event notice function is used and it transmits to the upper control system. In the case of polling, information is transmitted to the upper control system to a number "msec" order. In the case where the event notice function is used, an event can be interrupted at the time of event generating, and information can be transmitted to a target to the upper control system at it. By the J-PARC control system, it makes it possible to transmit the information on state change (event) to the upper control system immediately from PLC by using the rudder sequence program which the rudder sequence program for apparatus control detected change of a state, and mounted the event notice by using this event notice function. The J-PARC control system which mounted the event notice function is reported.  
 
THPCH123 New Control System for Nuclotron Main Power Supplies controls, extraction, monitoring, quadrupole 3089
 
  • V. Volkov, V. Andreev, E. Frolov, V. Gorchenko, V. Karpinsky, A. Kirichenko, A.D. Kovalenko, S. Romanov, A. Tsarenkov, B. Vasilishin
    JINR, Dubna, Moscow Region
  • D. Krusinsky, L. Ondris
    IMS SAS, Bratislava
  New control and monitoring system for Nuclotron main power supplies was designed in order to substantially extend functionality of the existing equipment and software. The lattice bending (BM), focusing (QF) and defocusing (QD) magnets are powered by two supplies. The BM magnetic field shape is set by pulse function generator that produces a reference burst (Bo-train) with 0.1 Gs resolution. This train controls pattern analog function generator based on a 18-bit DAC. A real B-train from the reference magnet and corresponding analog function are used for feedback loop. The current magnetic field of BM is used as reference function for the focusing and defocusing magnets. A scaling 16-bit multiplied DAC is used to set required ratio IBM/IQFD during accelerator cycle. A 16-bit data acquisition card provides measurement of all analog signals. Digital I/O boards are applied to set and read status of the power supplies, accompanying subsystems and interlocks. Timing modules provide the trigger pulses both for the system internal needs and for synchronizing of the accelerator subsystems and experimental setups.  
 
THPCH144 The Upgrading of the TLS Injector Bumper and Septum Power Supplies for Top-up Operation extraction, septum, booster, controls 3128
 
  • C.-S. Fann, K.-T. Hsu, S.Y. Hsu, J.-Y. Hwang, K.-K. Lin, K.-B. Liu, Y.-C. Liu
    NSRRC, Hsinchu
  Due to the inevitable requirement of routine top-up mode operation at TLS (Taiwan Light Source), the reliability of all components in TLS injector has been reevaluated in the past several months. Among all possible subsystems to be reinforced, the bumper and septum power supplies revealed urgent need of upgrading while operated continuously in the user shifts. In this report, the modification of the charging mechanism of the pulsed power supplies is described. The modular feature of the newly built units provides fast replacement capability in case of components failure. The unified specifications for all components have greatly reduced the effort in preparing spare parts. The test results of these units are presented in this report.  
 
THPCH146 Solid State Modulators for the International Linear Collider (ILC) klystron, linear-collider, collider, controls 3131
 
  • M.A. Kempkes, N. Butler, J.A. Casey, M.P.J. Gaudreau, I. Roth
    Diversified Technologies, Inc., Bedford
  Diversified Technologies, Inc. (DTI) is developing two solid-state modulator designs for the International Linear Collider with SBIR funding from the U.S. Department of Energy. This paper will discuss design tradeoffs, energy storage requirements and alternatives, and the construction and test status of both ILC designs. The first design is a 150 kV hard switch, employing an innovative energy storage system, which must provide 25 kJ per pulse at very tight voltage regulation over the 1.5 millisecond pulse. DTI's design uses a quasi-resonant bouncer (with a small auxiliary power supply and switch) to maintain the voltage flattop, eliminating the need for massive capacitor banks. The second design builds upon earlier DTI work for the 500 kV, 500 A NLC modulators. It uses a solid-state Marx bank, with ~10 kV stages, to drive the ILC klystron. Staggered turn-on of the Marx stages provides voltage regulation without the need for large capacitor banks.  
 
THPCH171 Control System of the Superconducting Insertion Device at TLS controls, insertion, insertion-device, cryogenics 3197
 
  • J. Chen, K.-T. Hsu, S.Y. Hsu, K.H. Hu, C.H. Kuo, D. Lee, C.-J. Wang
    NSRRC, Hsinchu
  There are three superconducting insertion devices installed at Taiwan Light Source. Two is under construction. These insertions enhance hard X-ray production to satisfy the research requirement of X-ray community. The control system is implemented to support the operation of all these superconducting insertion devices. The control system coordinate the operation of the main power supply and the trimming power supply to charge/discharge the magnets and provide essential interlock protection for the coils and vacuum ducts. Friendly user interface supports routine operation. Various applications are also developed to aid the operation of these insertion devices. Design consideration and details of the implementation will be summary in this report.  
 
THPCH177 Design and Construction of the PEFP Timing System for a 20 MeV Proton Beam proton, extraction, controls, rfq 3212
 
  • Y.-G. Song, Y.-S. Cho, H.M. Choi, I.-S. Hong
    KAERI, Daejon
  • K.M. Ha, J.H. Kim
    PAL, Pohang, Kyungbuk
  The timing system of the PEFP requires synchronization for the accelerator and for the multipurpose beam line. The system is based on an event distribution system that broadcasts the timing information globally to all the equipment. Fast I/O hardware of the timing system is to distribute appropriate timing signals to accelerator systems, including the Injector, RFQ, DTL, and user's facilities. Signals to be distributed include the synchronized pulse triggers and event information of RF system and switching magnet power supplies for the 20MeV proton beam extraction.  
 
THPCH187 Analysis and Reduction Electromagnetic Interference to ICTs Caused by Pulsed Power Supply Excitation in NSRRC kicker, injection, electron, storage-ring 3239
 
  • Y.-H. Liu, J.-C. Chang, J.-R. Chen, Y.-C. Lin
    NSRRC, Hsinchu
  The purpose of this paper is to eliminate the Electromagnetic Interference (EMI) from kicker power supply. Analyses of the EMI source and the propagation path are the beginning missions. The radiated and conducted EMI both affected the Integral Current Transformer (ICT) normal operation because of the space limitation for TLS in NSRRC. The ICT is to measure injection efficiency, thus, ICT located just behind the kickers and using the common girder. The EMI signals therefore are much higher than the electron beam currents, and the integral values of the sensor are not correct. For reducing and eliminating the interference of electromagnetic waves, a hybrid segregation and grounding method was used. The EMI wrapper was enclosed the ICT and its high frequency amplifier separately to prevent the radiated EMI from the space. The grounding paths provided the possible stray current dredge to the ground loop. It reduced the stray current spread to the subsystems next to the kickers. The EMI therefore reduced 99%, and the injection efficiency could be calculated successfully. The elimination of the EMI from kicker itself will be the next step in the future.  
 
THPLS043 Status of SESAME vacuum, dipole, lattice, storage-ring 3383
 
  • G. Vignola, A. Amro, M. Attal, H. Azizi, A. Kaftoosian, F. Makahleh, M.M. Shehab, H. Tarawneh, S. Varnasseri
    SESAME, Amman
  An overview of the status of SESAME is presented. SESAME is a third generation light source facility, with an e-beam energy of 2.5 GeV, located in Allan, Jordan. The emittance is 26 nm.rad and 12 straights are available for insertion devices. The injector consists of a 22.5 MeV microtron and 800 MeV booster synchrotron, with a repetition rate of 1 Hz. The conceptual design of the accelerator complex has been frozen, and the engineering design is in progress. The phase I scientific program for SESAME has also been finalized, and it foresees 6 beam lines, including 2 IR ports. The construction of the SESAME building is in progress, and the beneficial occupancy is expected by the end of 2006. The completion of the accelerators complex construction is scheduled for the end of 2009.  
 
THPLS045 Construction Status of the SSRF Project booster, vacuum, storage-ring, linac 3389
 
  • Z. Zhao
    SINR, Jiading, Shanghai
  • H. Ding, H. Xu
    SINAP, Shanghai
  The Shanghai Synchrotron Radiation Facility (SSRF), an intermediate energy third generation light source, is under construction at Zhang-Jiang Hi-Tech Park in Shanghai. Its main and auxiliary buildings are scheduled to be completed in October 2006, and this will be followed by the SSRF accelerator installations from October 2006 to March 2008. This paper presents the final design and the current construction status of the SSRF project.  
 
THPLS099 Fast Kicker Systems for the SOLEIL Booster Injection and Extraction, with Full Solid-state Pulsed Power Supplies kicker, extraction, injection, vacuum 3505
 
  • P. Lebasque, M. Bol, C. Herbeaux, J.-P. Lavieville, J.L. Marlats
    SOLEIL, Gif-sur-Yvette
  The Booster of SOLEIL needs injection and extraction kicker systems with fast transition times, good flat top and low jitter, to allow a satisfactory injection efficiency of the Storage Ring injection. So all the kicker systems have been optimised, to fulfil specifications and to permit the use of solid state switching electronics. This contribution presents the ceramic vacuum chambers and magnets design, the specific pulse forming scheme and the realisation of the pulsed power supplies working up to 20 kV. Electrical and magnetic measurements results of kickers systems are given, and also its operation status from the first SOLEIL Booster injection in July 2005.