MOPOW055 | Injection Using a Non-linear Kicker Located in the Existing Injection Straight at Diamond Storage Ring | injection, kicker, storage-ring, optics | 840 |
|
|||
Injection studies using a non-linear kicker for the Diamond storage ring have been carried out previously*. These studies have been recently extended to investigate whether the non-linear kicker can be located in the injection straight downstream of the septum and outside the existing dipole kicker bump. If so, injection with a non-linear kicker becomes independent of the optics used, making it suitable for use in both standard and low alpha mode. With this configuration, the existing injection scheme could also be left in place, leaving open the possibility to study both schemes in situ before potentially removing the existing dipole kickers at a later date. In order to operate with the non-linear kicker, the injected beam needs to exit the transfer line at an angle of 3mrad; this has been successfully demonstrated during machine development time. The concept and feasibility studies of this scheme are presented in this paper.
* T. Pulampong, et al., Proc. IPAC 2013, Shanghai, WEPWA065, (2013) |
|||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-MOPOW055 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
TUOBA01 | Beam Commissioning of SuperKEKB | optics, coupling, vacuum, detector | 1019 |
|
|||
In this report, we describe the machine operation in the first 3 months of the Phase 1 commissioning of SuperKEKB. The beam commissioning is smoothly going on. Vacuum scrubbing, the optics corrections and others are described. | |||
![]() |
Slides TUOBA01 [9.346 MB] | ||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-TUOBA01 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
TUPMB017 | The Injection Septum Magnet for the Collector Ring (FAIR) | injection, vacuum, operation, lattice | 1145 |
|
|||
Collector Ring is one of the key installations of the FAIR project (Darmstadt, Germany). It is dedicated for stochastic cooling of incoming beams of antiprotons and rare ions. Additionally there is a mode of operation for experiments in the ring. Beams for all modes of operation are injected through one transfer channel. Extremely high acceptance of the ring (240 mm*mrad) leads to large apertures of all magnetic elements including the septum magnet. Meanwhile planned parameters of the magnetic field and magnetic field quality are comparatively strict. The present state of the design of the pulsed injection septum for the CR is presented in this article together with the concept of the injection system. | |||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-TUPMB017 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
TUPMR039 | The Development of a New High Field Injection Septum Magnet System for Main Ring of J-Parc | injection, operation, power-supply, flattop | 1337 |
|
|||
We are improving the Main Ring (MR) for beam power of 750 kw which is the first goal of J-PARC. The repetition period of the fast extraction must be short to 1.3 second from the current period of 2.48 second for the improvement of the beam power. It is necessary to exchange a high field injection septum magnet which will be installed at the injection line from RCS to MR and its power supply, because the current injection septum system can not be operated with 1.3 second repetition. Since confirmed the large leakage field around current circling beam line of the injection magnet, we must improve the shielding structure which make low leakage field. We started the development of the new injection septum magnet and its power supply in 2013. It can operate with 1 Hz repetition and the low leakage field which its order is 10-4 of the gap field. The new Injection septum magnet and the new power supply were constructed in Winter of 2014. We had many improvement of the magnet and power supply. We will install the new injection septum magnet system in this summer. In this presentation, we will report the detail of the results of its performance. | |||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-TUPMR039 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
TUPMR040 | The Development of a New Low Field Septum Magnet System for Fast Extraction in Main Ring of J-PARC | operation, power-supply, vacuum, extraction | 1340 |
|
|||
The J-PARC Main Ring (MR) is being upgraded to improve its beam power to the design goal of 750 kW. One important way is to reduce the repetition period from 2.48 s to 1.3 s so that the beam power can be nearly doubled. We need to improve the septum magnets for fast extraction. We are improving the magnets and their power supplies. The present magnets which is conventional type have problem in durability of septum coil by its vibration, and large leakage field. The new magnets are eddy current type. The eddy current type does not have septum coil, but has a thin plate. We expect that there is no problem in durability, we can construct the thin septum plate, the leakage field can be reduced. The output of the present power supply are pattern current which of flat top is 10 ms width, the new one is short pulse which of one is 10 us. The short pulse consists of 1st and 3rd higher harmonic. We can expect that the flatness and reproducibility of flat top current can be improved. The calorific power can be also reduced. This paper will report the field measurement results with the eddy septum magnet systems. | |||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-TUPMR040 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
TUPMR047 | Conceptual Design Considerations for the 50 TeV FCC Beam Dump Insertion | extraction, kicker, collimation, optics | 1356 |
|
|||
Safely extracting and absorbing the 50 TeV proton beams of the FCC-hh collider will be a major challenge. Two extended straight sections (ESS) are dedicated to beam dumping system and collimation. The beam dumping system will fast-extract the beam and transport it to an external absorber, while the collimation system will protect the superconducting accelerator components installed further downstream. The high stored beam energy of about 8.5 GJ per beam means that machine protection considerations will severely constrain the functional design of the ESS and the beam dump line geometry, in addition to dominating the performance specifications of the main sub-systems like kickers and absorber blocks. The general features, including concept choice, optics in the ESS and beam dump line, passive protection devices, layout and integration are described and discussed. | |||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-TUPMR047 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
WEPMR056 | Septum Magnet using a Superconducting Shield | shielding, extraction, radiation, dipole | 2402 |
|
|||
A field-free region can be created within a dipole magnet using a superconducting shield, which maintains persistent eddy currents induced during the ramp-up of the magnet. We will study the possibility to realize a high-field superconducting septum magnet using this principle. Properties of different configurations will be presented, and compared to the requirements of the FCC dump system. | |||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-WEPMR056 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
WEPMW011 | Stable Spin Direction Investigations in RHIC | kicker, extraction, emittance, injection | 2442 |
|
|||
Funding: Work supported by Brookhaven Science Associates, LLC under Contract No. DE-AC02-98CH10886 with the U.S. Department of Energy. Beam and spin dynamics investigations are part of the preparations and studies regarding RHIC collider runs, they are part as well of the efforts dedicated to improving stored beam polarization, and in view of the eRHIC EIC project. Some recent studies and their outcomes are discussed. |
|||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-WEPMW011 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
WEPOW024 | Commissioning of SESAME Booster | booster, injection, quadrupole, extraction | 2880 |
|
|||
Commissioning of the 800 MeV booster of SESAME light source started in December 2013. The 38.4 m circumference booster is a part of SESAME injector which includes also a 20 MeV classical microtron as a pre-injector that is in operation since 2012. The main results and experience obtained during the commissioning period are reported in this paper. | |||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-WEPOW024 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
THPMR016 | Horizontal Phase Space Shaping for Optimized Off-axis Injection Efficiency | injection, sextupole, optics, lattice | 3424 |
|
|||
With the introduction of top-up operation at the ESRF it becomes important to reduce as much as possible any kind of perturbation seen by the users during injection. For this purpose, a novel technique to improve injection efficiency by shaping the horizontal beam phase space to better match the storage ring acceptance and hence reduce the duration of injections was developed. Theoretical concept, simulations and first experimental results are presented. | |||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-THPMR016 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
THPMR043 | Performance of Transverse Beam Splitting and Extraction at the CERN Proton Synchrotron in the Framework of Multi-turn Extraction | extraction, proton, resonance, sextupole | 3492 |
|
|||
Considerable progress has been made in 2015 in the setting up of the multi-turn extraction (MTE) in the CERN Proton Synchrotron (PS). A key ingredient in this novel extraction technique is the beam splitting in transverse phase space. This manipulation is based on adiabatic trapping in stable islands of transverse phase space and requires mastering a number of devices in the PS ring. In addition, an in-depth review of all fast extractions schemes in the PS had been required due to the development and installation of a dummy septum to shield the actual magnetic septum. In this paper, the current performance of the beam splitting and of the extraction including the shadowing effect is presented. Future lines of development will also be discussed. | |||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-THPMR043 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
THPOR048 | Beam Losses at CERNs PS and SPS Measured with Diamond Particle Detectors | extraction, detector, injection, kicker | 3898 |
|
|||
Diamond particle detectors have been used in the LHC to measure fast particle losses with a nanosecond time resolution. In addition, these detectors were installed in the PS and the SPS. The detectors are mounted close to the extraction septum of the PS (transfer line to SPS) and the SPS (transfer lines TI2 and TI8 to LHC). Mainly, they monitor the losses occurring during the extraction process but the detectors are also able to measure turn-by-turn losses in the accelerators. In addition, detailed studies concerning losses due to ghost bunches were performed. This paper will describe the installed diamond detector setup, discuss the measurement results and possible loss mitigations. | |||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-THPOR048 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
THPOW032 | Experimental Test on the TPS Booster Injection Scheme Exploration and the Associated Bunch Train Analysis | injection, booster, kicker, operation | 4008 |
|
|||
In order to explore the tuning range of injection septum and kicker for TPS booster operation, an experimental test on the designed injection scheme has been performed. Tuning of these injection units is based on the top-up operation process for storage ring vacuum cleaning purpose. It is set for a fast beam accumulation in the storage ring where the stored beam variation range is selected for efficient operation consideration. The measurement results of booster beam current variation while tuning of injection septum and kicker are presented. A preliminary analysis concerning the observation of deteriorated phase space acceptance in the TPS booster is given in this report. This study also includes an effort to extend the present available operation bunch train for TPS booster. It shows that the increase of the booster beam current by bunch train tuning indicates an upper bound of about 400 ns. | |||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-THPOW032 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
THPOW034 | TLS Booster Injection Scheme Exploration | booster, injection, kicker, electron | 4016 |
|
|||
In this paper, the booster injection efficiency and the parameter working range related to key components in-cluding septum magnet and kicker magnet for Taiwan Light Source (TLS) injector operation are introduced. Booster injection scheme for different lattice is explored by machine study plan using injector property. The study result may be used by the operator as booster injection parameter fine tuning reference. It is also helpful for the advanced injection scheme exploration. | |||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-THPOW034 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
THPOW050 | Upgrade of Septum Magnets of the Transfer Line in TPS | injection, power-supply, simulation, booster | 4057 |
|
|||
Taiwan Photon Source (TPS) is a 3-GeV light source. The full current of the storage beam and commissioning of insertion devices are still in progress. An improved injection between the booster ring (BR) and the storage ring (SR) was implemented to increase the efficiency of injection and the reliability of the electrical parts. A DC septum (length 0.8 m) was replaced with an AC septum (length 1 m, type C) to decrease the leakage field and to relax the loading of the power supply. Mapping the field with mu-metal shielding was also implemented to diminish the leakage field from the AC septum. The lattice of the transfer line between the booster ring and the storage ring, BTS, was also rearranged to meet the new injection requirements. The performance of the AC septum with mu-metal shielding and the upgrade of the BTS lattice are discussed in this paper. | |||
DOI • | reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-THPOW050 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
THPOY033 | SIS100 Availability and Machine Protection | ion, dipole, proton, extraction | 4171 |
|
|||
For the future FAIR driver accelerator, SIS100, a detailed System-FMEA (Failure Modes and Effects Analysis) according to IEC 61508 has been done. One the one hand, this has been done to identify possible shortcomings for machine protection and on the other hand to predict the machine's availabilty for beam on target. The methodology for the analysis and the main failure modes currently known for the machine and its environment are described in detail. An estimate of the total machine's availability is given. | |||