Paper | Title | Other Keywords | Page |
---|---|---|---|
MOPEA046 | Solaris Project Progress | storage-ring, linac, vacuum, injection | 181 |
|
|||
Funding: Work supported by the European Regional Development Fund within the frame of the Innovative Economy Operational Program:POIG.02.01.00-12-213/09 Solaris is a 3rd generation light source facility being built in Kraków, Poland at the Jagiellonian University Campus. The project is being accomplished in a tight collaboration with the MAX IV Laboratory in Lund, Sweden. The Solaris 1.5 GeV storage ring is a replica of the MAX IV 1.5 GeV machine, whereas the injector and the transfer line although based on the same components, are unique for Solaris. One of the main differences is the 600 MeV injection energy requiring an energy ramp in the storage ring to the final operating energy of 1.5 GeV. The construction of the facility started in early 2010 and is planned to be finished in the autumn 2014. Up to now, 70% of the components have been procured and construction of the buildings in progress with expected handover in autumn 2013. This paper will give an update on infrastructure progress and design choices for shielding, service area placement of racks and routing of piping and cables. An update is also presented of machine layout that includes the injector, transfer line and storage ring. |
|||
MOPEA048 | Operation Status of RF System for the PLS-II Storage Ring | cryomodule, SRF, status, LLRF | 187 |
|
|||
Funding: Supported by the Korea Ministry of Science and Technology The RF system of the Pohang Light Source-II (PLS-II) storage ring is operating at the 3.0GeV/200mA with two superconducting RF (SRF) cavities. Each RF station is composed with a 300kW klystron with power supply unit, transmission components, a digital LLRF and a SRF cavity. And a cryogenic system of 700W capacities is supplied the LHe and LN2 to three cryomodules of SRF cavities. The second SRF cavity is installed during at the beginning in 2013 and the third one will be installed during summer shutdown in 2014 for stable 400mA operation with all 20 insertion devices. Also the third high power RF station with a 300kW klystron, power supply unit and WR1800 waveguide components will be prepared in 2013. The third LLRF system is already installed, but improved stabilities of amplitude, phase and tuner control. This paper describes the present operation status and improve plan of the RF system for the PLS-II storage ring. |
|||
MOPME024 | Status of Beam Loss Spatial Distribution Measurements at J-PARC Linac | proton, linac, controls, status | 524 |
|
|||
Funding: This work was supported by JSPS KAKENHI Grant Number 24510134. We have developed 8-plane (4 horizontal and 4 vertical) scintillating fiber hodoscope system to measure proton tracks due to beam loss in the ACS section at the J-PARC linac. The detector consists of upstream 4 planes (two horizontal and two vertical) and downstream 4 planes (two horizontal and 4 vertical). The time of flight measuremments between the upstream and downstream subsystems allow proton identification and energy mesurements. In summer of 2012, we have installed remote position movement system, which enables measurements of spatial distributions of proton tracks. In this presentation we show status of mesurements and data analysis. |
|||
MOPWA067 | Robust High-average-power Modulator | controls, neutron, power-supply, pick-up | 834 |
|
|||
Funding: US DOE. Grant No. DE-SC0004254 Diversified Technologies Inc. (DTI) designed a modulator which meets the requirements of the Spallation Neutron Source (SNS) modulators at Oak Ridge National Laboratory and will be less expensive than copies of the current modulators. The SNS modulators, under development for a decade, still do not meet the specifications for voltage, droop, or pulsewidth. The modulators must provide pulses of 85 kV, 165 A, with pulsewidths of 1.5 ms and voltage flatness of 1%. The current modulator switches the full power at high frequency during each pulse, and has a complex output transformer. DTI designed a modulator that meets all specifications and is less expensive. The proposed design is cheaper because there is an HV switch that operates at full current only once per pulse, a corrector that switches only 5% of the power at high frequency, a low-cost transformer-rectifier power supply, and no output transformer. DTI’s patented switch uses IGBTs, allowing the switch to operate at full capacity even if 20% of the devices fail. The modulator will be installed in 2013 at SNS to test klystrons. DTI will present the system components of the design as well as the performance results to date. |
|||
MOPWA087 | Predictive Diagnostics for High-availability Accelerators | diagnostics, monitoring, controls, extraction | 873 |
|
|||
In Accelerator Driven Systems, high availability of the accelerator is one of its key requirements. Fortunately, not every beam trip is necessarily a failure. For example, in the proposed MYRRHA transmuter, absence of the beam for less than 3 seconds is still deemed acceptable. Predictive diagnostics strives to predict where a failure is likely to occur, so that a mitigating action can be taken in a more controlled manner, thus preventing failure of other components while exactly pinpointing the component that is about to fail. One approach to predictive diagnostics is to analyze process variables that quantify inputs and outputs of components as archived by the accelerator's distributed control system. By observing trends in their values an impending fault can be predicted. In addition, sensors measuring e.g., vibration, temperature or noise can be attached to critical components. By analyzing the signatures of signals acquired by these sensors, non-nominal behavior can be detected which possibly indicates a looming failure. | |||
TUPEA088 | Argonne Flexible Linear Collider | collider, linac, linear-collider, wakefield | 1322 |
|
|||
We propose a linear collider based on a short rf pulse (~22ns flat top), high gradient (~120MV/m loaded gradient), high frequency (26GHz) two beam accelerator design. This is a modular design and its unique locally repetitive drive beam structure allows a flexible configuration to meet different needs. Major parameters of a conceptual 250GeV linear collider are presented. This preliminary study shows that an efficient (~5% overall), 4MW beam power collider may be achievable. The concept is extendable to the TeV scale. | |||
TUPFI068 | High Power Tests of Alumina in High Pressure RF Cavities for Muon Ionization Cooling Channel | cavity, pick-up, collider, resonance | 1508 |
|
|||
It is important to make a compact muon ionization cooling channel to increase the cooling efficiency (muon survival rate, cooling decrement, etc). A proposed scheme to reduce the radial size of RF cavities at a given resonance frequency is to insert a dielectric material into the RF cavity. In vacuum cavities, however, dielectric materials are extremely susceptible to breakdown in high power conditions. High-pressure hydrogen gas has been shown to inhibit breakdown events in RF cavities in strong magnetic fields. An experiment has been designed to test surface breakdown of alumina in RF cavities. A structure has been designed to maximize the parallel field parallel to the surface while bringing the cavity into a desired frequency range (800-810MHz). Alumina is tested in this configuration under high power conditions. The experimental result will be shown in this presentation. | |||
TUPME039 | The Drive Beam Phase Stability in CTF3 and its Relation to the Bunch Compression Factor | linac, acceleration, pick-up, linear-collider | 1655 |
|
|||
The proposed Compact Linear Collider (CLIC) is based on a two-beam acceleration scheme. The energy needed to accelerate a low intensity "main" beam is provided by a high intensity, low energy "drive" beam. The precision and stability of the phase relation between two beams is crucial for the performance of the scheme. The tolerable phase jitter is 0.2 deg rms at 12GHz. For this reason it is fundamental to understand the main possible causes of the drive beam timing jitter. Experimental work aimed at such understanding was done in the CLIC Test Facility (CTF3) where a drive beam with characteristics similar to the CLIC one is produced. Several phase measurements allowed us to conclude that the main source of phase jitter is energy jitter of the beam transformed and amplified into phase jitter when passing through a magnetic chicane. This conclusion is supported by measurements done with different momentum compaction values in the chicane. In this paper the results of these several phase measurements will be presented and compared with expectations. | |||
TUPME047 | Sub-Harmonic Bunching System of CLIC Drive Beam Injector | space-charge, bunching, collider, acceleration | 1670 |
|
|||
In the Compact Linear Collider (CLIC) the RF power for the acceleration of the Main Beam is extracted from a high-current Drive Beam that runs parallel with the main linac. The sub-harmonic bunching system of the drive beam injector has been studied in detail and optimized. The model consists of a thermionic gun, three travelling wave sub-harmonic bunchers followed by a tapered travelling wave buncher. The simulation of the beam dynamics has been carried out with PARMELA with the goal of optimizing the overall bunching process and in particular capturing particles as much as possible in the buncher acceptance and decreasing the satellite population. | |||
TUPME049 | Status of the Exploration of an Alternative CLIC First Energy Stage Based on Klystrons | linac, luminosity, linear-collider, collider | 1676 |
|
|||
The Compact Linear Collider is based on a two-beam scheme to accelerate the main, colliding beams. This scheme allows to reach very high centre-of-mass energies. At low collision energies the main beams could be accelerated by powering the accelerating structures with X-band instead of a second beam. We explore this option and indicate the parameters and conceptual design. | |||
TUPWA069 | Longitudinal Phase Space Dynamics with Novel Diagnostic Techniques at FACET | linac, wakefield, damping, radiation | 1865 |
|
|||
Funding: Work supported [optional: in part] by the U.S. Department of Energy under contract number DE-AC02-76SF00515. FACET produces high energy density electron beams for Plasma Wakefield Acceleration (PWFA) experiments. The high energy density beams are created by chirping the electron beam with accelerating sections and compressing the beam in magnetic chicanes. Precise control of the longitudinal beam profile is needed for the drive-witness bunch PWFA experiments currently underway at FACET. We discuss the simulations, controls, and diagnostics used to achieve FACET's unique longitudinal phase space. |
|||
TUPWO007 | Investigation of the Magnetic Chicane of the New Short-Pulse Facility at the DELTA Storage Ring | undulator, laser, simulation, electron | 1889 |
|
|||
Funding: Supported by DFG, BMBF, and the Federal State NRW. The new short-pulse facility at DELTA (a 1.5-GeV synchrotron light source) based on coherent harmonic generation (CHG) utilizes an electromagnetic undulator which can be configured as optical klystron (undulator – chicane – undulator). To optimize the CHG signal, the energy modulation of the electrons in the first undulator and the dispersion of the magnetic chicane (i.e. the R56 matrix element) have to be optimized. Since the R56 value of the present chicane is not sufficient, it is planned to rewire the magnetic coils to create a more efficient chicane. Simulations of the present chicane will be compared to measurements of the R56 matrix element and a new chicane configuration will be presented which increases the R56 value by a factor of ten. |
|||
TUPWO065 | Anomalously Long Bunches from the SLAC North Damping Ring | electron, linac, simulation, damping | 2015 |
|
|||
The SLC damping ring provides emittance reduced beam to the beginning of the FACET accelerator. In measurements conducted during the 2012 FACET run, we find the bunch-length to be ~20% longer than canonical. A study is performed with longitudinal simulation code to determine the impact on the various stages of compression for FACET experimental running. | |||
TUPWO067 | Start-to-end Particle Tracking of the FACET Accelerator | emittance, linac, wakefield, simulation | 2018 |
|
|||
Funding: Work supported by Department of Energy contract DE-AC02-76SF00515. The Facility for Advanced aCcelerator Experimental Tests (FACET) consists of the first two-thirds of the SLAC two-mile linac followed by a final focus and experimental end station. To date, wakefield-dominated emittance growth and dispersion in the linac, as well as dispersive and chromatic effects in the final focus have precluded regular reliable operation that meets the design parameters for final spot size. In this work, a 6-D particle tracking code (Lucretia) is used to simulate the complete machine, with input parameters taken directly from saved machine configurations. Sensitivities of various tuning parameters to the final spot sizes are compared with measurements taken from the real machine, and a set of tuning protocols is determined to improve regular machine operation. |
|||
TUPWO068 | Performance Improvements of the SLAC Linac for the FACET Beam | linac, emittance, quadrupole, injection | 2021 |
|
|||
Funding: Work supported by U.S.Department of Energy, Contract DE-AC02-76SF00515. Two thirds of the SLAC Linac is used to generate a short, intense electron beam for the FACET experiments. The emittance growth along the Linac is a major concern to finally get small spot sizes for these experiments. There are two different approaches to get the required small emittances: a) lengthy iterative global tuning technique, and b) trying to identify locations of the main sources of the emittance growth and reducing their effect locally. How these approaches help to get good beam performances is discussed. |
|||
WEOBB101 | The KOMAC Accelerator Facility | linac, DTL, proton, rfq | 2052 |
|
|||
Funding: This work was supported by the Ministry of Education, Science and Technology of the Korean Government. The development of the Korea Multi-purpose Accelerator Complex (KOMAC) accelerator facility was finished and went into the operation period from 2013. The facility consists of an 100-MeV proton linac including a 50-keV ion source, a 3-MeV RFQ, and a 100-MeV DTL, and 20-MeV and 100-MeV beam lines. The linac and beam lines were developed by the Proton Engineering Frontier Project (PEFP), the first phase of KOMAC from 2002 to 2012. The goal of the beam commissioning is delivering 100-MeV 1-kW proton beams to a beam bump in a 100-MeV target room. After finishing the commissioning, the user beam service will start from spring 2013. The KOMAC user facility consists of 2 beam lines in the initial operation stage and it will be increased to 10 beam lines in future. The one beam line is for 20-MeV proton beams which are extracted after 20-MeV part of the DTL tanks. A medium energy beam transport (MEBT) is installed there for the 20-MeV beam extraction and the beam matching to the next DTL tank. The other beam line is for 100-MeV proton beams. This work summarized the status of the KOMAC accelerator and beam lines. |
|||
![]() |
Slides WEOBB101 [6.038 MB] | ||
WEODB103 | Current Status of PAL-XFEL Project | FEL, undulator, emittance, gun | 2074 |
|
|||
The PAL-XFEL is a 0.1-nm hard X-ray FEL construction project which started from 2011 with a total budget of 400 M$. The PAL-XFEL is designed to have three hard X-ray undulator lines at the end of 10-GeV linac and a dog-leg branch line at 3 GeV point for two soft X-ray undulator lines. The three-bunch compressor lattice (3-BC) is chosen to have large flexibility of operation, making it possible to operate soft X-ray FEL undulator line simultaneously and independently from hard X-ray FEL line. Self seeding to achieve the FEL radiation bandwidth of below 5x10-5 is baseline for the hard X-ray FEL line. Polarization control will be available by using the PU + EPU layout for the soft X-ray FEL line. The overview of the project with current status is presented. | |||
![]() |
Slides WEODB103 [8.332 MB] | ||
WEOBB201 | Commissioning of the X-band Transverse Deflector for Femtosecond Electron/X-Ray pulse Length Measurements at LCLS | FEL, undulator, electron, diagnostics | 2091 |
|
|||
X-ray free-electron lasers provide ultrashort x-ray pulses from several to a few hundred femtoseconds for multidisciplinary users. However, tremendous challenges remain in the measurement and control of these ultrashort pulses with femtosecond precision, for both the electron beam and the x-ray pulses. A new diagnostic scheme adding a transverse radio-frequency deflector at the end of the linac coherent light source (LCLS) undulator beamline has been proposed*. Two 1-m long deflecting structures have been installed at LCLS during the summer of 2012. Installation of the high power RF components including the klystron, waveguide, RF controls etc. is proceeding and commissioning is scheduled for March 2013. We report the latest progress of the commissioning of the deflector at LCLS.
* Y. Ding et al., Phys. Rev. ST Accel. Beams 14, 120701 (2011) |
|||
![]() |
Slides WEOBB201 [4.199 MB] | ||
WEIB204 | Industry and Science, POSCO and POSTECH Case | linac, site, FEL, storage-ring | 2115 |
|
|||
Funding: * Supported by MEST and POSTECH POSCO is a world-leading iron and steel company established in 1968 in Pohang, in the South East coast of Korea. Starting with 1.0 million ton size in 1973, the company made profits even in the first year. While its capacity has been increased to 40 million tons with another works in Gwangyang, POSCO paid attention on education to attract intellectuals to Pohang and Korea. It results in establishing a small-sized university, Pohang University of Science and Technology (POSTECH) in 1987. POSTECH immediately decided to construct a third generation synchrotron light source of 2.0 GeV, Pohang Light Source (PLS) on its campus in 1988, with support from POSCO and also Government. POSTECH achieved a high rank in the world, and PLS is upgraded to 3.0 GeV in 2011. A new PAL-XFEL of 10.0 GeV is now under construction. POSCO's consistent policy is the key of the success of POSTECH and Pohang Light Source. This is an unprecedented example of the relationship between industry and science. |
|||
![]() |
Slides WEIB204 [4.759 MB] | ||
WEPWA043 | Construction of Injector Test Facility (ITF) for the PAL XFEL | gun, emittance, laser, controls | 2220 |
|
|||
Funding: Work supported by the Ministry of Education, Science and Technology (MEST) in Korea. An injector test facility (ITF) for the PAL-XFEL has been successfully constructed and its commissioning is under way. The facility is to demonstrate beam performances required by the PAL XFEL (beam energy of 139 MeV, projected rms emittance of < 0.5 mm mrad @ 200 pC, and beam repetition rate of 60 Hz) with good enough stabilities. We have constructed a dedicated building for the facility in which a radiation-shielding tunnel (19.2-m long, 3.5-m wide, and 2.4-m high inner space), a klystron-modulator gallery, a laser room, and a control room are installed. The injector consists of an in-house-developed photo-cathode rf gun, a 30-mJ Ti:Sa laser system, two accelerating structures (as well as two sets of klystron-modulator systems), and various diagnostics as well as magnets & instrumentations. The installation of a transverse deflecting cavity (S-band, 10-fs resolution) and a laser heater is scheduled in 2013. In this article we report on the facility construction and some of the early commisisoning results. |
|||
WEPEA069 | Review of the Drive Beam Stabilization in the CLIC Test Facility CTF3 | feedback, linac, controls, low-level-rf | 2666 |
|
|||
CTF3 is a Test Facility focusing on beam-based studies of the key concepts of the Compact Linear Collider CLIC. Over the past several years many aspects the CLIC two-beam acceleration scheme were studied in CTF3, including the crucial issue of drive beam stability. The main sources of drifts and instabilities have been identified and mitigated, helping to improve the machine performance and showing significant progress towards the experimental demonstration of the very stringent requirements on current, energy and phase stability needed in CLIC. In this paper, the more effective techniques and feed-backs are summarized. The latest measurements on beam stability are reported and their relevance to CLIC is discussed. | |||
WEPFI019 | High Power Test of Kanthal-coated L-band Lossy Cavity | cavity, vacuum, positron, solenoid | 2744 |
|
|||
We have been developing a Kanthal (Al-Cr-Fe)-coated collinear load as a possible candidate of the L-band acc. structure of SuperKEKB positron capture system. In order to achieve the higher capture efficiency comparing to that of KEKB, the upgrade of the e+ production and capture section is required. The system consists of a W target with a flux concentrator followed by acc. structures surrounded by solenoids. The increase of the e+ bunch charge and the reduction of satellite bunches are the main issues for this system. The frequency choice of L-band is based on the larger transverse and longitudinal acceptances than those of the S-band one. The load is preferable to compose the system with compact magnets and to minimize the dip in the solenoid field. The design of the load was reported in previous work*. We understand that the Kanthal-coated cell should be confirmed in high power to confirm the feasibility at our design field of 10 MV/m level. We are making a test cavity which consists of 3 cells and one of them is composed of Kanthal-coated disks to lower the intrinsic Q value from 20000 to the order of 1000. The cavity production and the experimental result will be reported.
*Development of L-band accelerating structure with Kanthal-coated collinear load for SuperKEKB, IPAC12, THLR04. |
|||
WEPFI024 | Anisotropic Ferrite Magnet Focusing System for Klystrons | focusing, cathode, permanent-magnet, simulation | 2756 |
|
|||
The permanent magnet beam focusing for klystrons can eliminate the solenoid coil with the water cooling system and the power supply that consumes electricity. Hence the failure rate and the operating cost of RF systems should decrease. This feature is suitable for a large facility that requires a lot of klystrons such as ILC. Since the required magnetic field for klystron beam is moderate, inexpensive anisotropic ferrite magnets can be applied. The test model is fabricated for a 1.3 GHz klystron whose output power is 800 kW. Each magnet block in the model is movable for magnetic field adjustment and the iron yoke in the oil tank improves magnetic field distribution around cathode area. The result of a klystron power test will be presented. | |||
WEPFI040 | R&D of C-band Pulse Compression for Soft X-ray FEL at SINAP | cavity, coupling, simulation, FEL | 2791 |
|
|||
A compact Soft X-ray Free Electron Lasers facility is presently being constructed at SINAP, and 8 C-band accelerating structure unit are required for third-stage including 4 pulse compressors. The field mode of C-band SLED is TE0.1.15 with high quality factor Q, and the coupling coefficient is 8.5. Based on the design, the power pulse of klystron is compressed from 2.5μs to 0.5μs, and finally the power gain is about 3.1. In this paper, the details and simulation of 3-dB coupler, mode convertors and the resonant cavities are presented, meanwhile some cold test results of cavity are also analyzed at the end of this paper. | |||
WEPFI042 | Installation and Operation of the RF System for the 100 MeV Proton Linac | linac, controls, LLRF, proton | 2797 |
|
|||
Funding: This work was supported by the Ministry of Education, Science and Technology of the Korean Government. The RF system of the 100MeV proton linac for 1st phase of KOMAC has been installed at the Gyeong-ju site. Nine sets of LLRF control system and the HPRF system including 1MW klystrons, circulators and waveguide components have been installed at the klystron gallery, and four high voltage converter modulators has been installed at the modulator room. A RF reference system distributing 300MHz LO signal to each RF control system has also been installed with a temperature control system. The requirement of RF field control is within ± 1% in RF amplitude and ± 1 degree in RF phase, and the operation of RF system will start at the end of this year after installation. The installation and operation of the RF system for the 100MeV proton linac are presented in this paper. |
|||
WEPFI043 | S-band High Stability Solid State Amplifier for 10 GeV PAL-XFEL | LLRF, controls, FEL, monitoring | 2800 |
|
|||
In PAL, We are constructing a 10GeV PxFEL project. The output power of the klystron is 80 MW at the pulse width of 4 ㎲ and the repetition rate of 60 Hz. And the specifications of the rf phase and amplitude stability are 0.05 degrees(rms) and 0.05%(rms) respectively. The SSA(Solid State Amplifier) is used for driver of 80MW Klystron. The output power of SSA is 800W. Also, the measured rf stability of SSA output is 0.03 degrees rms and 0.025 % rms. This paper describes the microwave system and the SSA for the PxFEL. | |||
WEPFI044 | High Power Test of New SLED System with Biplanar 3-dB Power Divider and Dual Side-wall Coupling Irises for PAL XFEL | coupling, simulation, cavity, free-electron-laser | 2803 |
|
|||
The new type of the Stanford Linear Accelerator Energy Doubler (SLED) system for the PAL (Pohang Accelerator Laboratory) XFEL (X-ray Free Electron Laser) is developed to be operated with an RF input power of 80 MW and a pulse width of 4 μs. To prevent the RF breakdown such a high power operation, a biplanar 3-dB power divider and dual side-wall coupling irises structure are used in the new SELD system. It is shown that the field gradient and surface current is reduced from that of the original SLED system using the the finite-difference time-domain (FDTD) simulation. The high power test result of the new SLED system in the PAL XFEL test facility will be presented. | |||
WEPFI045 | PAL-XFEL Accelerating Structures | linac, electron, emittance, impedance | 2806 |
|
|||
We need 172 accelerating structures for the PAL-XFEL 10 GeV main linac. It takes long time for these structures to be delivered. So we are trying to find suppliers of the accelerating structures. First, we made an order of 40 accelerating structures to Mitsubishi Heavy Industry (MHI), which have Quasi-type couplers to reduce the quadruple and sextuple components of the electric field in the coupling cavity. And Research Instruments (RI) has fabricated a 3m long race type accelerating structure for PAL-XFEL. Also, Vitzrotech which is a domestic company and IHEP in China are under developing accelerating structures for PAL-XFEL respectively. We will describe the current status of accelerating structures and high power test results of the newly developed structures in this paper. | |||
WEPFI059 | C-band RF Pulse Compressor for SwissFEL | coupling, resonance, HOM, cavity | 2827 |
|
|||
The SwissFEL C-band (5.712 GHz) linac consists of 28 RF modules. Each module is composed of a single 50 MW klystron feeding a pulse compressor and four two meter long accelerating structures. The pulse compressor is based on a single Barrel Open Cavity (BOC). The BOC makes use of a “whispering gallery” mode which has an intrinsically high quality factor and operates in resonant rotating wave regime; moreover, and contrary to the conventional SLED scheme, a single cavity is sufficient to define the pulse compressor, without the need for two cavities and a 3-dB hybrid. A prototype has been manufactured and successfully tested. A short description of the BOC is presented, together with the prototype design, production, low level RF measurements, and high power test. | |||
WEPFI060 | Planar Balun Design with Advanced Heat Dissipation Structure for kW Level Solid-state Amplifier Module Development | coupling, controls, impedance, storage-ring | 2830 |
|
|||
The power level of solid-state amplifier is continuously growing for advanced accelerator application as the RF power source. Huge amount of solid-state power amplifier (SSPA) modules can contribute several hundreds of kW RF power with high redundancy and reliability. However, with the increasing desire of RF power of single RF station, too much power modules would adversely cause larger area occupation and higher maintenance cost and complexity. Therefore, with the advancement of the RF power on single SSPA, the overall system design and configuration would become much simple and compact. However, the increasing RF of single SSPA would also bring the thermal problem at its chip as well as the output power combining balun. In this paper, kW range SSPA is developed with the novel planar balun structure with good thermal expansion property. With such new planar balun design, the SSPA can operate stably with above 1kW output RF power. | |||
WEPFI065 | The Commissioning of the EBTF S-band Photoinjector Gun at Daresbury Laboratory | cavity, electron, vacuum, laser | 2845 |
|
|||
The first stage of the installation of the Electron Beam Test Facility (EBTF) at Daresbury Laboratory has been completed and a commissioning phase is presently underway. At the heart of the machine is a photoinjector based on a two and a half cell S-band RF gun incorporating a metallic photocathode, which is capable of delivering 4-6 MeV, low emittance, short electron pulses (10 - 250 pC). The photoinjector is driven by a UV light at 266 nm wavelength delivered by a laser system and is powered by a RF system incorporating a Low Level RF system, a high power RF modulator and a klystron. This paper describes the commissioning and conditioning of the photoinjector. | |||
WEPFI067 | FETS RF System Design and Circulator Testing | rfq, shielding, ion, insertion | 2851 |
|
|||
The Front End Test Stand (FETS) is an experiment based at the Rutherford Appleton Laboratory (RAL) in the UK. In this experiment, the first stages necessary to produce a very high quality, chopped H− ion beam as required for the next generation of high power proton accelerators (HPPAs) are designed, built and tested. HPPAs with beam powers in the megawatt range have many possible applications including drivers for spallation neutron sources, neutrino factories, accelerator driven sub-critical systems, waste transmuters and tritium production facilities. RF system outline and design options of the waveguide and coaxial parts and shielding are presented and discussed in this paper. Experimental measurements of the system’s circulator will be presented as part of the system testing results. | |||
WEPFI078 | LLNL X-band RF System | high-voltage, vacuum, gun, cathode | 2875 |
|
|||
Funding: This work performed under the auspices of the U.S. Department of Energy by Lawrence Livermore National Laboratory under Contract DE-AC52-07NA27344 An X-band test station is being developed at LLNL to investigate accelerator optimization for future upgrades to mono-energetic gamma-ray technology at LLNL. The test station will consist of a 5.5 cell X-band rf photoinjector, single accelerator section, and beam diagnostics. The high power RF for the test station will be provided by a SLAC XL4 11.424 GHz klystron driven by a ScandiNova solid state modulator. The high power system has been installed and results of initial testing into high power loads will be presented. Performance of the system with respect to processing and stability will be discussed as well as future plans for the low level RF system. |
|||
WEPFI080 | Waveguide Component R&D for the ILC | linac, cavity, coupling, linear-collider | 2881 |
|
|||
Funding: Work supported by the U.S. Department of Energy under contract DE-AC02-76SF00515. Several years of effort have gone into refining the design of the International Linear Collider. The direction the design has evolved in response to driving considerations has resulted in a more sophisticated waveguide system for delivering RF power to the cavities. In particular, the desire to eliminate parallel service tunnels along the main linacs led to the proposal of the Klystron Cluster Scheme (KCS)*, involving plumbing the combined power from groups of klystrons down from the surface at several locations in overmoded waveguide. Additionally, to increase superconducting cavity yield, the acceptance criteria were relaxed to encompass a ±20% range in sustainable operating gradient, which must be accommodated by tailoring of the RF power distribution. Designs and prototype testing of some of the novel waveguide components developed to allow these changes are described here. * Christopher Nantista and Chris Adolphsen, “Klystron Cluster Scheme for ILC High Power RF Distribution,” presented at the 2009 Particle Accel. Conf., Vancouver, B.C., Canada, May 2009. |
|||
WEPFI081 | High Power Tests of Overmoded Waveguide for the ILC Klystron Cluster Scheme | resonance, linac, simulation, coupling | 2884 |
|
|||
A Klystron Cluster Scheme has been proposed for the ILC Main Linacs in which the output power of up to thirty, 10 MW, 1.3 GHz klystrons are combined in a single, 0.5 m diameter circular waveguide in a surface building and transported down to and along the accelerator tunnel where it is periodically tapped-off to power strings of cavities. This schemes eliminates the need for a separate linac service tunnel and simplifies the linac electric and cooling distribution systems. Recently, a 40 meter long circular waveguide with a coaxial input coupler and a 90 degree rf bend were assembled and run in a resonant configuration to test the concept. With the pipe pressurized with up to 30 psig of N2 to raise the rf breakdown threshold, it was demonstrated that field levels equal to those for the 300 MW transmission required for ILC could be sustained reliably. We report on these and other test results from this program. | |||
WEPFI084 | High Power S-band RF Window Optimized to Minimize Electric and Magnetic Field on the Surface | linac, vacuum, simulation, positron | 2893 |
|
|||
Funding: * Work Supported by Doe Contract No. DE-AC02-76SF00515 RF windows are used to separate vacuum from atmosphere in high power microwave systems, such as klystrons. RF breakdowns in these megawatt power environments are frequent and problematic. And S-band RF window was designed to have reduced electric and magnetic field in the ceramic and waveguide joints. Specifically the normal component of the electric field on the ceramic is minimized and a traveling wave is created inside the ceramic by optimizing the shape of the window and the geometry of the joint between the circular waveguide to the rectangular waveguide. A prototype of this window in the process of being made at SLAC for high power tests. |
|||
WEPFI088 | High-power Tests of an Ultra-high Gradient Compact S-band (HGS) Accelerating Structure | vacuum, coupling, monitoring, linac | 2902 |
|
|||
RadiaBeam Technologies reports on the RF design, fabrication and high-power tests of a ultra-high gradient S-Band accelerating structure (HGS) operating in the pi-mode at 2.856 GHz. The compact HGS structure offers a drop-in replacement for conventional S-Band linacs in research and industrial applications such as drivers for compact light sources, medical and security systems. The electromagnetic design (optimization of the cell shape in order to maximize RF efficiency and minimize surface fields at very high accelerating gradients) has been carried out with the codes HFSS and SuperFish while the thermal analysis has been performed by using the code ANSYS. The high-power conditioning was carried out at Lawrence Livermore National Laboratory (LLNL). | |||
WEPME007 | Commissioning of the Upgraded Superconducting CW Linac ELBE | cavity, vacuum, linac, SRF | 2935 |
|
|||
With the expansion of the radiation source ELBE a center for high power radiation sources is being built at the Helmholtz Zentrum Dresden-Rossendorf (HZDR). In a first step (January 2012) the available CW RF-power (1.3 GHz) per superconducting 9-cell TESLA cavity at ELBE had been increased from 8.5 kW to 20 kW (CW) using solid state amplifiers. In a second step the performance of several machine components of ELBE must be redesigned to enable full power operation without risks. The poster gives an overview how these problems have been solved at ELBE and reports on the commissioning. | |||
WEPME013 | Development and Test of a Fully Automated PkQl Control Procedure at KEK STF | cavity, controls, LLRF, feedback | 2950 |
|
|||
In order to operate the cavities near their maximum gradients, cavity input (Pk) and cavity loaded Q (QL) should be controlled individually (PkQL control) at the International Linear Collider (ILC). A manual PkQL operation procedure was developed and performed at the linear electron accelerator at the Superconducting RF Test Facility (STF), in which the beam is accelerated up to 40 MeV by two superconducting 9-cell TESLA type L band cavities. The cavity gradients were set to 16 MV/m and 24 MV/m with QL values of 1106 and 3·106. A 6.2 mA beam with a pulse length of 154 us was used. The field stabilities in amplitude were 0.160% and 0.097% for the cavities and 0.016% for the vector sum. The stabilities without beam are 0.057% and 0.054% for the cavities and 0.009% for the vector sum. For stability improvement during beam transient an adaptive beam feedforward for beam loading compensation is under development. So far an amplitude field stability of 0.013% for the vector sum was achieved at cavity gradients of 15 MV/m and 25 MV/m (no PkQL control) during a 6.8 mA beam with a pulse length of 123 us. Furthermore a fully automated PkQL control procedure is currently developed and tested. | |||
![]() |
Poster WEPME013 [0.647 MB] | ||
WEPME014 | Progress in Development of New LLRF Control System for SuperKEKB | cavity, controls, LLRF, pick-up | 2953 |
|
|||
For the SuperKEKB project, a new LLRF control system was developed to realize high accuracy and flexibility. It is an FPGA-based digital RF feedback control system using 16-bit ADC's, which works on the μTCA platform. The FPGA boards control accelerating cavity fields and cavity tuning, and the EPICS-IOC is embedded in each of them. The CSS-BOY was adopted for a user interface of our system. High power test of the new LLRF control system was performed with the ARES Cavity of KEKB. The obtained feedback control stability with a klystron drive was sufficient as well as the low-level evaluation result. And auto tuner control also worded successfully. The start-up sequencer program for the cavity operation and auto-aging program also worked very well. The temperature characteristics of the system depend largely on band-pass filters (BPF). We tried to tune the BPF to reduce the temperature coefficient. Consequently the temperature dependence was improved to satisfy the required stability. | |||
WEPME017 | Development and Application of the Trigger Timing Watchdog System in KEK Electron/Positron Linac | linac, controls, EPICS, electron | 2962 |
|
|||
The KEK injector linac provides electrons and positrons to several accelerator facilities. A 50 Hz beam-mode switching system has been constructed to realize simultaneous top-up injections for Photon Factory and the KEKB high- and low-energy rings, which require different beam characteristics. An event-based timing and control system was built to change the parameters of various accelerator components within 20 ms. The components are spread over a 600-m-long linac and require changes to a total of 100 timing and control parameters. The system has been operated successfully since the autumn of 2008 and has been improved upon as beam operation experience has been accumulated. The timing watchdog and alert system are indispensable for the stable and high quality beam operation. For this purpose, we developed and utilized several timing watchdog system. We will present the detail of timing signal watchdog system for the KEK injector linac. | |||
WEPME040 | Investigation to Reduce Power Overhead Required in Superconducting RF Cavity Field Control | cavity, controls, feedback, cathode | 3013 |
|
|||
A power overhead of more than 25% is usually required in RF field control of klystron drived superconducting cavity, since it is much easier to implement feild control in a linear region of klystron where it is far below saturation. It however results in a reduced efficiency and more power consumption. Within ESS project it places very high demands on energy efficiency, which leads to stringent requirements on power overhead required in RF field control. Investigation on power overhead reduction in RF field control has been carried out at ESS and related simulation has been done. In this paper we will look at how close we can implement field control to the klystron saturation and discuss if it is possible to make RF field control the RF field with 10% overhead. | |||
THPEA052 | TLS Operation Information Management: Automatic Logging Tools | kicker, booster, injection, linac | 3261 |
|
|||
The Taiwan Light Source (TLS) has been operated in the Top-up mode since October 2005 and has maintained a beam current of 360mA since 2010. Several essential parameters and waveforms are constantly recorded as routine accelerator operation reference. Therefore, five LabVIEW-based data and waveform logging software programs have been developed for the purpose of preliminary diagnose at the TLS. In this report, certain actual cases in regular operation are presented. | |||
THPEA060 | LLRF System for LCLS-II at SLAC | LLRF, controls, feedback, linac | 3276 |
|
|||
Funding: Work supported by US Department of Energy Contract DE AC03 76SF00515 After LCLS-I successfully delivering the full operation for users, SLAC has been approved to build the second Linac Coherent Light Source, LCLS-II, which makes use of another third of the 2-mile long Linac from Sector 10 to Sector20. The LLRF System will use mTCA (Micro Telecommunication Computing Architecture) to replace the VME system for LCLS-II injector and some key stations along the LINAC. The faster data acquisition and more powerful FPGA and CPU in the mTCA system enable the LLRF system to extend its control ability to a 2.5 μsec beam pulse rate of 360Hz. The new LLRF system is more compact and has the capability of low latency intra-pulse feedback to reduce fast phase and amplitude jitter during a single pulse. The prototype of the mTCA based LLRF control system has been operating at RF station 28-2 in LCLS-I. Detailed design structure and the prototype experimental results will be presented that demonstrate the system meets the exacting phase and amplitude stability requirements for LCLS-II. |
|||
THPFI013 | Development of Cylindrical-type 1.2 MW High Power Water-load for Super KEKB | positron, collider, cavity, factory | 3318 |
|
|||
We have developed and manufactured CW 1.2 MW high power water-load for the use of the Super KEKB, an electron – positron double-ring collider at KEK. The tank and rf window of the water-load is the circular and cylindrical-type. The material to absorb the rf power is a tap water. This load is equipped on the 3rd port of the circulators to safe the 1.2 MW CW klystrons to drive the ARES cavities in main ring. The operational frequency is 508.9 MHz. A proto-type model of this water-load was fabricated at Sep 2012, and tested using by high power klystron (1 MW) at Oct 2012 at KEK D2-ET station. The result of high power test will be reported in this paper. | |||
THPFI080 | NSC KIPT Neutron Source on the Base of Subcritical Assembly Driven with Electron Linear Accelerator | neutron, target, electron, radiation | 3481 |
|
|||
National Science Center “Kharkov Institute of Physics and Technology” (NSC KIPT, Kharkov, Ukraine) together with Argonne National Laboratory (ANL, USA) develops the conceptual project of a neutron source based on the sub-critical assembly driven by electron linear accelerator. The main functions of the subcritical assembly are support of the nuclear industry and medical researches. Reactor physics and material researchs will be carried out at the facility. For subcritical assembly design proven techniques and practices are used to enhance its utilization. The goal of the development is to create in Ukraine the experimental basis for neutron research based on safe intensive sources of neutrons. The main facility components are an electron linear accelerator, a system for electron beam transportation from linear accelerator to the target, neutron production target, subcritical assembly, biological shield, neutron channels and auxiliary supporting systems. | |||
THPWA008 | Design of a Fast-cycling High-gradient Rotating Linac for Protontherapy | linac, cyclotron, proton, simulation | 3642 |
|
|||
General interest has been shown over the last years for the development of single room facilities serving a population of about 2 million people for proton cancer therapy. Compact machines are needed to accelerate proton beams of few nanoamperes up to 230 MeV. In this framework the project TULIP (Turning LInac for Protontherapy), patented by TERA Foundation, foresees a linac mounted on a rotating gantry used as a booster for protons previously accelerated by a cyclotron. The linac is composed of modular units powered by independently controlled klystrons. The RF power transmission is made possible by high power rotating joints developed in collaboration with CLIC group. The final beam energy can be varied in steps of few MeV from pulse to pulse by amplitude and/or phase modulation of the klystron signals, making possible the implementation of active spot scanning technique with tumor multi-painting. The present paper provides the main characteristics of TULIP, describing the different choices for the linac design parameters together with the structural design of the supporting gantry and of the final beam line. | |||
THPWO050 | High Power Test and Beam Commissioning of he CPHS RFQ Accelerator | rfq, vacuum, proton, ECR | 3884 |
|
|||
Funding: Work supported by the “985 Project” of the Ministry of Education of China, National Natural Science Foundation of China (Major Research Plan Grant No. 91126003 and 11175096). We present, in this paper, the high power test result and the beam commissioning status of a Radio Frequency Quadrupole (RFQ) accelerator for the Compact Pulsed Hadron Source (CPHS) at Tsinghua University. The 3-meter-long RFQ is designed to deliver 3 MeV protons to the downstream High Energy Beam Transport (HEBT) with the peak current of 50 mA, pulse length of 0.5 ms and beam duty factor of 2.5%. The RFQ has been designed, manufactured, and installed at Tsinghua University. High-vacuum test of the RFQ has been carried out carefully and the cooling system has been mounted. At the beginning of 2013, the high power RF test has been performed and the first 3 MeV proton beam is obtained. |
|||