MO201 | Progress in the Beam Commissioning of J-PARC Linac and its Upgrade Path | 16 |
|
||
The beam commissioning of J-PARC linac has been started since November 2006, and the initial commissioning has been completed in September 2007. Since then, the linac beam has been supplied to the succeeding RCS (Rapid Cycling Synchrotron) for its commissioning with occasional linac beam studies for finer tuning. The emphasis of the linac tuning has been shifted to the characterization and stabilization of the beam parameters, and better beam availability has gradually been required for the linac operation. In this paper, we present the current linac performance and operational experience obtained so far after a brief review of the commissioning history. Remaining commissioning tasks and the future upgrade plan to increase the beam power are also discussed. |
||
|
||
MO202 | Status of a High Current Linear Accelerator at CSNS | 21 |
|
||
China Spallation Neutron Source (CSNS) consist of an H- linac as an injector of a rapid cycling synchrotron of 1.6 GeV. The 324 MHz rf linac is designed with beam energy of 81 MeV and a peak current of 30 mA. The linac design and R&D are in progress. A test stand of a Penning ion source is under construction. RFQ technology has been developed in ADS study, with beam energy of 3.5 MeV, a peak current of 47 mA at 7% duty factor and a beam transmission rate more than 94%. The first segment of the DTL tank has been fabricated. This paper will introduce the design and R&D status of the linac. |
||
|
||
MO203 | The SARAF CW 40 MeV Proton/Deuteron Accelerator | 26 |
|
||
The Soreq Applied Research Accelerator Facility, SARAF, is currently under construction at Soreq NRC. SARAF is based on a continuous wave (cw), proton/deuteron rf superconducting linear accelerator with variable energy (5-40 MeV) and current (0.04-2 mA). SARAF is designed to enable hands-on maintenance, which implies beam loss below 10-5 for the entire accelerator. Phase I of SARAF consists of an ECR ion source, a LEBT section, a 4-rod RFQ, a MEBT section, a superconducting module housing 6 half-wave resonators and 3 superconducting solenoids, a diagnostic plate and a beam dump. Phase II will include 5 additional superconducting modules. The ECR source has been in routine operation since 2006, the RFQ has been operated with ions and is currently under characterization. The superconducting module rf performance is being characterized off the beam line. Phase I commissioning results, their comparison to beam dynamics simulations and Phase II plans will be presented. |
||
|
||
MO204 | The Injector Systems of the FAIR Project | 31 |
|
||
Funding: EU-Research Infrastructure Activity under the FP6 "Structuring the European Research Area" program (CARE, contract number RII3-CT-2003-506395); EU-INTAS Project Ref. no. 06-1000012-8782 |
||
|