Paper | Title | Other Keywords | Page |
---|---|---|---|
MOPLO18 | Thermal Analysis of the LANSCE H+ RFQ Test Stand Faraday Cup | LEBT, MEBT, linac, interface | 274 |
|
|||
The Los Alamos Neutron Science Center (LANSCE) op-erates one of the nation’s most powerful linear accelera-tors (LINAC). Currently the facility utilizes two 750 keV Cockcroft-Walton (CW) based injectors for transporting H+ and H− beams into the 800 MeV accelerator. A Radio Frequency Quadrupole (RFQ) design is being proposed to replace the aged CW injectors. An important component of the RFQ Test Stand is the Faraday cup that is assem-bled at the end of the Low Energy Beam Transport (Phase 1 LEBT) and Medium Energy Beam Transport (Phase 3 MEBT). The Faraday cup functions simultaneously as both a beam diagnostic and as a beam stop for each of the three project phases. This paper describes various aspects of the design and analysis of the Faraday cup. The first analysis examined the press fit assembly of the graphite cone and the copper cup components. A finite element analysis (FEA) evaluated the thermal expansion proper-ties of the copper component, and the resulting material stress from the assembly. Second, the beam deposition and heat transfer capability were analyzed for LEBT and MEBT beam power levels. Details of the calculations and analysis will be presented. | |||
![]() |
Poster MOPLO18 [3.399 MB] | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2019-MOPLO18 | ||
About • | paper received ※ 27 August 2019 paper accepted ※ 25 November 2019 issue date ※ 08 October 2019 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
TUPLO02 | Spin Dynamics in the JLEIC Ion Injector Linac | linac, solenoid, proton, focusing | 533 |
|
|||
Funding: This work was supported by the U.S. DOE, Office of Nuclear Physics, under Contract No. DE-AC02-06CH11357 for ANL and by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE-AC05-06OR23177. One of the requirements for the future Electron Ion Col-lider (EIC) is to collide polarized electrons and light ions with at least 70% polarization for each beam. For light ions, polarized ion sources are used for injection to a linac, which is usually the first accelerator in the collider chain. The Jefferson Lab EIC (JLEIC) ion injector linac consists of a low-energy room-temperature section with quadrupole focusing followed by a superconducting linac with solenoid focusing inside long cryomodules. These two sections have different effects on the spin. Spin dy-namics simulation studies are carried out for the JLEIC injector linac in order to preserve and maintain a high degree of polarization for light ion beams for delivery to the booster. The different options to maintain and restore the spin in the different sections of the linac for hydrogen, deuterium and helium ions are presented and discussed. Results from both the Zgoubi and COSY-Infinity codes are presented and compared for every section of the ion linac but the radio-frequency quadrupole (RFQ). Current-ly, a method to simulate the RFQ using Zgoubi is being investigated. |
|||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2019-TUPLO02 | ||
About • | paper received ※ 28 August 2019 paper accepted ※ 19 November 2019 issue date ※ 08 October 2019 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
WEPLH01 | Longitudinal Beam Profile Measurement by Silicon Detector in Facility for Rare Isotope Beams at Michigan State University | detector, timing, emittance, linac | 799 |
|
|||
Funding: Work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661, the State of Michigan and Michigan State University The Facility for Rare Isotope Beams (FRIB) includes a continuous wave superconducting linear accelerator designed to deliver 400 kW ion beams with energies above 200 MeV/u. The beam commissioning of the first three cryomodules took place in the summer of 2018. A temporary diagnostic station installed after the first three cryomodules included a Silicon Detector (SiD) to measure absolute energy and bunch shape of 40Ar and 86Kr beams accelerated up to 2.3 MeV/u. The beam longitudinal emittance was evaluated by measuring bunch shapes while the bunching field amplitude of the upstream resonator was varied. In this paper, we will present the SiD setup and measurement results. |
|||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2019-WEPLH01 | ||
About • | paper received ※ 28 August 2019 paper accepted ※ 31 August 2019 issue date ※ 08 October 2019 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
WEPLH02 | Experience with Long-Pulse Operation of the PIP2IT Warm Front End | operation, MEBT, kicker, LEBT | 803 |
|
|||
Funding: This manuscript has been authored by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the U.S. Department of Energy, Office of Science, Office of High Energy Physics The warm front end of the PIP2IT accelerator, assembled and commissioned at Fermilab, consists of a 15 mA DC, 30 keV H− ion source, a 2-m long Low Energy Beam Transport (LEBT) line, a 2.1-MeV, 162.5 MHz CW RFQ, followed by a 10-m long Medium Energy Beam Transport (MEBT) line. A part of the commissioning efforts involves operation in regimes where the average beam power in this front end emulates the operation of the proposed PIP-II accelerator, which will have a duty factor of 1.1% or above. The maximum achieved power is 5 kW (2.1 MeV x 5 mA x 25 ms x 20 Hz). This paper describes the difficulties encountered and some of the solutions that were implemented. |
|||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2019-WEPLH02 | ||
About • | paper received ※ 20 August 2019 paper accepted ※ 01 September 2019 issue date ※ 08 October 2019 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
WEPLH03 | Redesign of ReA3 4-Rod RFQ | MMI, operation, simulation, linac | 807 |
|
|||
Funding: Work supported by the U.S. DoE Office of Science under Cooperative Agreement DE-SC0000661 and the NSF under Cooperative Agreement PHY-1102511, the State of Michigan and Michigan State University. The present RFQ of ReA3 reaccelerator at Michigan State University (MSU) has been commissioned in 2010. This 4-rod RFQ was designed to accelerate the prebunched 80.5 MHz beams with the lowest Q/A = 1/5. However, the lack of proper cooling limited the RFQ performance to the pulsed operation with the lowest Q/A = 1/4. The design voltage for Q/A = 1/5 has never been reached even in a pulsed mode due to the sparking. In 2016 we initiated the upgrade of ReA3 RFQ to support high duty cycle (up to CW) operation with Q/A = 1/5 beams. The upgrade included the new rods with trapezoidal modulation, and new stems with improved cooling. The redesigned 80.5 MHz RFQ will consume only 65% rf power of the present RFQ for Q/A = 1/5 beam. It will provide the transmission up to 78% for 16.1 MHz beams and 89% for 80.5 MHz beams. High reliability and efficiency of the RFQ are very important for the going-on reaccelerator upgrade to ReA6 and for future operation as a part of FRIB. The electrodes have been manufactured and are being installed. The RF and beam tests are scheduled to summer 2019. |
|||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2019-WEPLH03 | ||
About • | paper received ※ 27 August 2019 paper accepted ※ 01 September 2019 issue date ※ 08 October 2019 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
WEPLH06 | Commissioning Status of the FRIB Front End | MMI, linac, cavity, ECR | 813 |
|
|||
Funding: This work is supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661. The FRIB Front End was successfully commissioned in 2017 with commissioning goals achieved and Key Per-formance Parameters (KPP) demonstrated for both 40Ar9+ and 86Kr17+ beams. Two more ion species, 20Ne6+ and 129Xe26+, have been commissioned on the Front End and delivered to the superconducting linac during the beam commissioning of Linac Segment 1 (LS1) in March 2019. In August 2019, Radio Frequency Quadrupole (RFQ) conditioning reached the full design power of 100 kW continuous wave (CW) that is required to accelerate Ura-nium beams. Start-up/shutdown procedures and opera-tional screens were developed for the Front End subsys-tems for trained operators, and auto-start and RF fast re-covery functions have been implemented for the Front End RFQ and bunchers. In this paper, we will present the current commissioning status of the Front End, and per-formance of the main technical systems, such as the ECR ion source and RFQ. |
|||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2019-WEPLH06 | ||
About • | paper received ※ 01 September 2019 paper accepted ※ 05 September 2019 issue date ※ 08 October 2019 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
WEPLH07 | Commissioning of the FRIB/NSCL New ReA3 4-Rod Radio Frequency Quadrupole Accelerator | vacuum, operation, MMI, cavity | 817 |
|
|||
Funding: This work was supported by the National Science Foundation under Grant PHY-15-65546 The reaccelerator facility ReA3 at the National Superconducting Cyclotron Laboratory is a state-of-the-art accelerator for ions of rare and stable isotopes. The first stage of acceleration is provided by a 4-rod radio-frequency quadrupole (RFQ) at 80.5 MHz, which accelerates ions from 12 keV/u to 530 keV/u. The internal copper acceleration structure of the RFQ was re-designed. The goal was to improve transmission while allowing to operate the RFQ in CW and accelerating ions with A/Q from 2 to 5. In this paper, we summarize the steps involved in the disassembly of the existing structure, preparation work on the retrofitted vacuum vessel, installation of the new components, acceptance testing, and commissioning of the completed RFQ. |
|||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2019-WEPLH07 | ||
About • | paper received ※ 29 August 2019 paper accepted ※ 19 November 2019 issue date ※ 08 October 2019 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
WEPLH15 | Light Ion Injector for NICA | cavity, linac, DTL, proton | 834 |
|
|||
The Nuclotron ring of the NICA project will get a new light ion injector linac (LILac) for protons and ions with a mass to charge ratio up to 3. The LILac will consist of 2 sections: A 600 A keV RFQ followed by an IH-type DTL up to 7 AMeV, and a postaccelerator IH-cavity for protons only - up to 13 MeV. A switching magnet will additionally allow 13 MeV proton beam injection into a future superconducting testing section. The pulsed Linac up to 7 AMeV and including the postaccelerator for protons up to 13 MeV will be developed in collaboration between JINR and Bevatech GmbH. The technical design of that Linac is discussed in this paper. | |||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2019-WEPLH15 | ||
About • | paper received ※ 29 August 2019 paper accepted ※ 03 September 2019 issue date ※ 08 October 2019 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||
THZBA2 | The MYRRHA Project | cavity, linac, proton, operation | 945 |
|
|||
The main objective of the MYRRHA project at SCK•CEN, the Belgian Nuclear Research Centre, is to demonstrate the feasibility of nuclear waste transmutation using an Accelerator Driven System (ADS). It is based on a High Power CW operated 600 MeV proton Linac with an average beam power of 2.4 MW. Due to the coupling of the accelerator with a subcritical reactor, a major concern is reliability and availability of the accelerator. The MYRRHA Linac consists of a room temperature 17 MeV Injector based on CH-cavities and the superconducting main Linac using different RF structures as Single Spokes, Double-Spokes and elliptical cavities. In 2017, it has been decided to stage the project and to start with the construction of a 100 MeV Linac (Injector and Single Spoke section) including a 400 kW proton target station. This facility (MINERVA) will be operational in 2026 aiming to evaluate the reliability potential of the 600 MeV Linac. The Front-End consisting of an ECR source, LEBT and 1.5 MeV RFQ is already operational while the first 7 CH-cavities are under construction. The presentation gives an overview about the MYRRHA Project, its challenges and the status of construction and testing. | |||
![]() |
Slides THZBA2 [27.209 MB] | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2019-THZBA2 | ||
About • | paper received ※ 27 August 2019 paper accepted ※ 15 September 2019 issue date ※ 08 October 2019 | ||
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | ||