Paper | Title | Page |
---|---|---|
MOP051 | 3.9 GHz SRF Production Cavities for LCLS-II | 173 |
|
||
Funding: This work was supported by the US DOE and the LCLS-II Project. The main part of the SRF linac for the Linac Coherent Light Source II (LCLS-II) at SLAC will consist of 35 cryomodules with superconducting RF cavities operating at 1.3 GHz. In addition, two cryomodules with 3.9 GHz cavities will be installed and help to linearize the longitudinal phase space of the beam. During the design verification phase, four prototype 9-cell 3.9 GHz cavities had been built by industry and then processed, including chemical surface removal and heat treatment, and tested at Fermi National Accelerator Laboratory. Based on the resulting cavity treatment recipe, 24 cavities (for two cryomodules to be installed in the linac and one spare cryomodule) have been built by industry and tested at Fermilab prior to cryomodule string assembly. We present an overview of the cavity production and the results of the vertical acceptance tests for the LCLS-II 3.9 GHz cavities. |
||
![]() |
Poster MOP051 [1.015 MB] | |
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-MOP051 | |
About • | paper received ※ 02 July 2019 paper accepted ※ 03 July 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
MOP092 | Overview of LCLS-II Project Status at Fermilab | 302 |
|
||
The superconducting RF Continuous-Wave (CW) Linac for the LCLS-II consists of thirty-five 1.3 GHz and two 3.9 GHz cryomodules that Fermilab and Jefferson Lab are jointly producing in collaboration with SLAC. Fermilab¿s scope of work is to build, test, and deliver half the 1.3 GHz and all the 3.9 GHz cryomodules and to design and procure components for the cryogenic distribution system. Fermilab has primary responsibility for delivering a working design. The cryomodule design basis was the European XFEL but several elements evolved to meet CW operation requirements and specifics of the SLAC tunnel. There have been several challenges faced during the design, assembly, testing and transportation of the cryomodules which have required design updates. Success in overcoming these challenges is attributable to the strength of the LCLS-II SRF Collaboration (Fermilab, Jefferson Lab and SLAC with extensive help from DESY and CEA/Saclay). The cryogenic distribution system has progressed relatively well and there are valuable Lessons Learned. An overview of the status, accomplishments, problems encountered, solutions developed, and a summary of Lessons Learned will be presented. | ||
![]() |
Poster MOP092 [0.393 MB] | |
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-MOP092 | |
About • | paper received ※ 20 June 2019 paper accepted ※ 30 June 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
TUP095 | Lessons Learned Assembling the SSR1 Cavities String for PIP-II | 690 |
|
||
The string assembly of the prototype Single Spoke Resonator type 1 (SSR1) cryomodule for PIP-II at Fermilab was successfully completed. Lessons learned from the preparation, assembly and the quality control activities of the final fully integrated assembly will be presented. | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-TUP095 | |
About • | paper received ※ 28 June 2019 paper accepted ※ 29 June 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
TUP096 | Optimization of Clean Room Infrastructure and Procedure During LCLS-II Cryomodule Production at Fermilab | 695 |
|
||
Funding: The work is supported by Fermilab which is operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy. Optimization of Fermilab string assembly procedure and infrastructure has yielded a significant improvement of cryomodule particulate counts. Late production of LCLS-II cryomodules were tested at CMTF at Fermilab and showed little to no x-ray up to administrative limit. The paper describes the field emission measurement instrumentation, field emission results of LCLS-II cyomodules, clean room infrastructure upgrade and procedure optimization. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-TUP096 | |
About • | paper received ※ 23 June 2019 paper accepted ※ 30 June 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
TUP101 | LCLS-II Cryomodules Production Experience and Lessons Learned at Fermilab | 709 |
|
||
LCLS-II is a planned upgrade project for the linear coherent light source (LCLS) at SLAC. The LCLS-II Linac will consist of thirty-five 1.3 GHz and two 3.9 GHz superconducting RF continuous wave (CW) cryomodules that Fermilab and Jefferson Lab are currently producing in collaboration with SLAC. The LCLS-II 1.3 GHz cryomodule design is based on the European XFEL pulsed-mode cryomodule design with modifications needed for CW operation. Two prototype cryomodules had been assembled and tested. After prototype cryomodule tests, both laboratories have increased their cryomodule production rate to meet the challenging LCLS-II project installation schedule requirements of approximately one cryomodule per month per laboratory. To date, Fermilab has completed the assembly and testing of sixteen 1.3 GHz cryomodules. Fermilab has successfully shipped five CMs to SLAC and will continue to ship with a two-week throughput. The first 3.9 GHz cryomodule assembly is scheduled to start in June 2019; production readiness verifications are in progress. This paper presents LCLS-II cryomodule assembly and production experience, emphasizing the challenges, the mitigations and lessons learned | ||
![]() |
Poster TUP101 [0.834 MB] | |
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-TUP101 | |
About • | paper received ※ 20 June 2019 paper accepted ※ 30 June 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
WETEA2 |
SRF Cryomodules for PIP-2 at Fermilab | |
|
||
Funding: The work is supported by Fermilab which is operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy. The Proton Improvement Plan-II (PIP-II) is an essential upgrade to the Fermilab accelerator complex to provide powerful, high-intensity proton beams to the laboratory¿s experiments. Design challenges include the areas of high Q cavities, high power couplers, resonance control, and oversea transportation. The recent developments of cavities and cryomodules for the PIP-2 project will be described. |
||
![]() |
Slides WETEA2 [12.357 MB] | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
THP055 | Magnetic Field Induced by Thermo Electric Current in LCLS-II Cryomodules | 1003 |
|
||
Funding: The work is supported by Fermilab which is operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy. Seebeck effect of metals play an important role in cryomodule design. As cryomodule cools down from room temperature down to nominal cavity operating temperature, components in a cryomodule experiences different temperatures. Some components such as power couplers cross from room temperature to 2 K. Thermo electric current forms loops circulating through and around cavities. Such current loops will generate additional magnetic field that could be trapped into cavity wall during superconducting transition as well as during cavity quench. These trapped field can degrade cavity quality factor and increase heat load. Simple circuit model is proposed and compared to calculated trapped field during cryomodule tests. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-THP055 | |
About • | paper received ※ 26 June 2019 paper accepted ※ 30 June 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
THP060 | Experience With LCLS-II Cryomodule Testing at Fermilab | 1018 |
|
||
Funding: This manuscript has been authored by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the U.S. Department of Energy, Office of Science, Office of High Energy Physics. The Cryomodule Test Stand (CMTS1) at Fermilab has been engaged with testing 8-cavity 1.3 GHz cryomodules designed and assembled for the LCLS-II project at SLAC National Accelerator Laboratory since 2016. Over these three years twenty cryomodules have been cooled to 2K and power tested in continuous wave mode on a roughly once per month cycle. Test stand layout and testing procedures are presented together with results from the cryomodules tested to date. Lessons learned and future plans will also be shared. |
||
![]() |
Poster THP060 [2.774 MB] | |
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-THP060 | |
About • | paper received ※ 22 June 2019 paper accepted ※ 30 June 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |