The European Spallation Source, ESS, is under construction in Lund since 2014. While the installation of the source and the normal conducting part will start in this autumn, the production and testing of cryomodules and cavities for the superconducting accelerator is in full swing at the partner laboratories. The spoke cavities and cryomodules will be provided by IPN Orsay and the testing of those modules will take place at Uppsala University. Prototyping and assembly of the elliptical cryomodules series is occurring at CEA Saclay, and the modules will be tested at a new test stand at ESS. The fabrication and test of the medium beta cavities is provided by INFN Milan and STFC Daresbury for the high beta cavities respectively. An overview of the current activities and test results will be presented in this talk.
|
|
|
Slides MOYA01 [26.361 MB]
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-SRF2017-MOYA01
|
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
MOPB018 |
Testing of SRF Cavities and Cryomodules for the European Spallation Source |
95 |
|
- N. Elias, E. Asensi Conejero, C. Darve, N.F. Hakansson, W. Hees, C.G. Maiano, F. Schlander
ESS, Lund, Sweden
|
|
|
The European Spallation Source (ESS) is currently under construction in Lund, Sweden. The ESS linear accelerator aims to deliver a 62.5 mA , 2.86 ms long proton beam onto a rotating tungsten target, at 14 Hz repetition rate, thus achieving an energy of 2 GeV and 5 MW power. Most of the beam acceleration happens in the superconducting fraction of the linac, which is composed of three sectors of cryomodules named after the cavities housed within. The first sector of the SRF linac is composed of 13 Spoke cryomodules containing 2 double-spoke cavities with a geometric beta of 0.5, the second is composed of 9 medium beta cryomodules each housing four elliptical cavities (β=0.67) and finally 21 high beta cryomodules enclosing four elliptical cavities (β=0.86). ESS has strategically built up a SRF collaboration with other European institutions, these partners will deliver through In-Kind agreements cavities and cryomodules performing within the ESS specification. This article describes the process leading to the acceptance of cavities and cryomodules received from the different partners and the necessary testing required prior to the final installation in the ESS tunnel.
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-SRF2017-MOPB018
|
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
MOPB019 |
Interface Challenges for the SRF Cryomodules for the European Spallation Source |
100 |
|
- F. Schlander, C. Darve, N. Elias, C.G. Maiano
ESS, Lund, Sweden
- P. Bosland
CEA/DSM/IRFU, France
- G. Olry
IPN, Orsay, France
|
|
|
The European Spallation Source is currently under construction in Lund in southern Sweden. The main part of the accelerator will consist of two different types of cryomodules housing three different types of cavities ' double spoke cavities and two different elliptical cavities. The spoke cavities as well as the cryomodules will be provided by IPN Orsay, thus the external interfaces to the other accelerator systems have to be verified. While the procurement and assembly of the elliptical cryomodules will be performed by CEA Saclay, the cavities will be provided by INFN Milano and STFC Daresbury. Thus in addition to the external cryomodule interfaces, also the internal interfaces between cavities and cryomodules have to be taken care of. This contribution presents the challenges related to this work.
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-SRF2017-MOPB019
|
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
THYA05 |
Developments and Progress with ESS Elliptical Cryomodules at CEA-Saclay and IPN-orsay |
729 |
|
- F. Peauger, C. Arcambal, F. Ardellier, S. Berry, P. Bosland, A. Bouygues, E. Cenni, J.-P. Charrier, G. Devanz, F. Éozénou, A. Gaget, D. Gevaert, A. Gomes, T. Hamelin, X. Hanus, P. Hardy, V.M. Hennion, T.J. Joannem, C. Marchand, O. Piquet, J.P. Poupeau, B. Renard, P. Sahuquet, T. Trublet
CEA/DRF/IRFU, Gif-sur-Yvette, France
- C. Darve
ESS, Lund, Sweden
- G. Olivier
IPN, Orsay, France
|
|
|
CEA Saclay in collaboration with IPN Orsay is in charge of the ESS elliptical cavities cryomodule design, prototyping and series production. Two cryomodule prototypes are being developed and will be tested at CEA Saclay before starting the series production. The main cryomodule design features are first reminded. We present the cavities and couplers test results and the achieved assembly sequences of the first medium beta cavities cryomodule demonstrator M-ECCTD. The progress on the preparation of the CEA cryomodule test station is given. The procurement status and development plan of the second high beta demonstrator H-ECCTD are also reported. Finally we give the components procurement progress and the assembly strategy of the 30 series cry-omodules to be integrated at CEA before delivery to ESS at Lund.
|
|
|
Slides THYA05 [11.226 MB]
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-SRF2017-THYA05
|
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|