Paper | Title | Page |
---|---|---|
MO204 | The Injector Systems of the FAIR Project | 31 |
|
||
Funding: EU-Research Infrastructure Activity under the FP6 "Structuring the European Research Area" program (CARE, contract number RII3-CT-2003-506395); EU-INTAS Project Ref. no. 06-1000012-8782 |
||
|
||
MOP019 | The HITRAP Decelerator Project at GSI - Status and Commissioning Report | 100 |
|
||
For injection into the ion trap facility HITRAP, the GSI accelerator complex has the unique possibility to provide beams of highly stripped ions and even bare nuclei up to Uranium at an energy of 4 MeV/u. The HITRAP facility consists of linear 108 MHz-structures of IH- and RFQ-type to decelerate the beams further down to 6 keV/u for capturing in a large penning trap for cooling purpose. The installation is completed except of the RFQ-tank. During commissioning periods in 2007 64Ni28+ and 20Ne10+ beam was used to investigate the beam optics from the experimental storage ring extraction to the HITRAP double-drift-buncher system. In 2008 the IH-structure decelerator and the downstream matching section was examined with 197Au79+ beam. Comprehensive beam diagnostics were installed: Faraday cups, tubular and short capacitive pick ups, SEM grids, YAG scintillation screens, a single shot pepperpot emittance meter, and a diamond detector for bunch shape measurements. Results of the extensive measurements are presented. |
||
MOP032 | Upgrade of the Unilac High Current Injector RFQ | 136 |
|
||
Funding: Work supported by the European Community INTAS Project Ref. no. 06-1000012-8782. |
||
MOP046 | Commissioning of the New GSI-Charge State Separator System for High Current Heavy Ion Beams | 175 |
|
||
A dedicated charge separator system is now installed in the transfer line to the GSI-synchrotron SIS18. In former times charge separation was performed with a single 11 degree dipole magnet after a 25 m beam transport section. This was not adequate to meet the requirements during high current operation for FAIR: it only allows for charge state separation of low intensity and low emittance beams. With the new compact charge separator system emittance blow up and unwanted beam losses for high intensity beam operation will be avoided. Additionally a new beam diagnostics test bench is integrated. With this the beam parameters (ion current, beam profile, beam position, transversal emittance, bunch structure and beam energy) for the injection into the SIS18 can be measured in parallel to the routine operation in the transfer line. Results of the commissioning with high intensity argon beams as well as with an uranium beam will be reported. |
||
MOP057 | Linac Front-End Upgrade at the Cancer Therapy Facility HIT | 208 |
|
||
A clinical facility for cancer therapy using energetic proton and ion beams (C, He and O) has been installed at the Radiologische Universitätsklinik in Heidelberg, Germany. It consists of two ECR ion sources, a 7 MeV/u linac injector, and a 6.5 Tm synchrotron to accelerate the ions to energies of 430 MeV/u. The linac comprises a 400 keV/u RFQ and a 7 MeV/u IH-DTL operating at 216.8 MHz and has been commissioned successfully in 2006. Yet the overall achieved transmission through the injector linac did not exceed 30% due to a mismatch of the beam at the RFQ entrance. Thus a detailed upgrade programme has been started to exchange the RFQ with a new radial matcher design, to correct the alignment and to optimize beam transport to the IH-DTL. The aim is to achieve a sufficient linac transmission above 60%. The new design of the RFQ has been finished in 2007 and the RFQ is currently in production. A test bench comprising a full ion source and LEBT setup to commission the RFQ in 2008 is under construction at Danfysik in Danemark. The current status of this upgrade programme will be reported in this contribution. |
||
MOP075 | Benchmarking of Measurement and Simulation of Transverse RMS-Emittance Growth Along an Alvarez DTL | 251 |
|
||
Funding: CARE, contract number RII3-CT-2003-506395) European Community INTAS Project Ref. no. 06-1000012-8782 |
||
TUP074 | Commissioning of the HITRAP Decelerator Using a Single-Shot Pepper Pot Emittance Meter | 564 |
|
||
Funding: Work supported by BMBF under contract 06FY160I. *HITRAP webpage of AP division at GSI, http://www.gsi.de/forschung/ap/projects/hitrap/index_e.html |
||
THP078 | High Power RF Supplies for the FAIR Injector Linacs | 975 |
|
||
During the LINAC conference in Knoxville 2006 the operating frequency of the FAIR proton linac was fixed at 325.224 MHz. Even though the six CH-Structures need slightly different rf levels, the proton linac will be equipped with identical rf power sources. That applies although for the RFQ structure. To supply the FAIR accelerators with a good beam quality by the UNILAC as the high current heavy ion injector for FAIR, as well as an high duty factor accelerator for nuclear physics experiments, different upgrades and modifications have to be made at the rf components. In addition there has to be an upgrade for a planned 50% duty cycle mode, higher beam load within the post-stripper section as well as the provision of an excellent rf operation for the next 30 years. Discussions on possible collaborations with CERN in terms of LLRF and the combining of the procurement for tube amplifiers for bunching cavities are on the way. This paper describes the actual status of the proton linac rf system and the future requirements for the existing UNILAC rf systems. |