Keyword: booster
Paper Title Other Keywords Page
MOPTEV007 RF Conditioning of 120 kW CW 1.3 GHz High Power Couplers for the bERLinPro Energy Recovery Linac cavity, vacuum, SRF, operation 216
 
  • A. Neumann, W. Anders, A. Frahm, F. Göbel, A. Heugel, S. Klauke, J. Knobloch, M. Schuster, Y. Tamashevich
    HZB, Berlin, Germany
 
  Funding: The work is funded by the Helmholtz-Association, BMBF, the state of Berlin and HZB.
This year, the commissioning of the 50 MeV, 100 mA bERLinPro Energy Recovery Linac test facility [1] will resume. For the Booster cryo-module of the injector line, operated with three modified 1.3 GHz Cornell style 2-cell SRF cavities, a new type of power coupler was developed, based on KEK’s C-ERL injector coupler. Modifications were made for a stronger coupling and lower emittance diluting coupler tip variant, a so-called "Golf Tee" shape and the cooling concept was redesigned based on KEK’s first experiences. For the final stage, the injector needs to deliver a low emittance beam of 100 mA average beam current at 6.5 MeV. That results in a traveling and continuous wave forward power requirement of up to 120 kW each of the twin setup feeding one Booster cavity. In this contribution we will give a short overview of the RF design and its impact on the beam’s emittance, give an overview of the conditioning teststand and the results achieved with the first pairs of couplers.
[1] M. Abo-Bakr et al., in Proc. 9th Int. Particle Accelerator Conf. (IPAC’18), Vancouver, BC, Canada, Apr. 4,, pp. 4127-4130, doi:10.18429/JACoW-IPAC2018-THPMF034
 
poster icon Poster MOPTEV007 [2.466 MB]  
DOI • reference for this paper ※ doi:10.18429/JACoW-SRF2021-MOPTEV007  
About • Received ※ 19 June 2021 — Accepted ※ 19 August 2021 — Issue date ※ 17 January 2022  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPCAV015 Development of QWRS for the Future Upgrade of JAEA Tandem Superconducting Booster cavity, acceleration, tandem-accelerator, linac 299
 
  • Y. Kondo, H. Kabumoto, M. Matsuda
    JAEA, Ibaraki-ken, Japan
  • T. Dohmae, E. Kako, H. Sakai, K. Umemori
    KEK, Ibaraki, Japan
  • H. Harada, J. Kamiya, K. Moriya, J. Tamura
    JAEA/J-PARC, Tokai-mura, Japan
 
  The Japan Atomic Energy Agency (JAEA) tandem booster is one of the pioneering superconducting heavy ion linac in the world. It consists of 40 QWRs with an operation frequency of 130 MHz and βopt=0.1, and has potential to accelerate various ions up to Au to 10 MeV/u. The user operation was started in 1994, however, it has been suspended since the Great East Japan Earthquake in 2011. Recently, we started activities to investigate and improve the performance of the QWR cavities towards the restart of the tandem booster. In addition, design work of new lower beta cavities to improve the acceleration efficiency of heavier ions such as Uranium has been launched. Now we are surveying some operation frequencies and types of cavities including multi-gap QWR with use of electro-magnetic simulation of the cavities. In this work, the current status of the R&D program for the JAEA tandem facility is presented.  
DOI • reference for this paper ※ doi:10.18429/JACoW-SRF2021-MOPCAV015  
About • Received ※ 20 June 2021 — Accepted ※ 21 August 2021 — Issue date ※ 01 October 2021  
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)