Preparation of the Cryomodule Assembly for the Linear IFMIF Prototype Accelerator (LIPAc) in Rokkasho |
726 |
|
- T. Ebisawa, A. Kasugai, K. Kondo, S. Maebara, K. Sakamoto
QST, Aomori, Japan
- N. Bazin, S. Berry
CEA-DRF-IRFU, France
- P. Cara
IFMIF/EVEDA, Rokkasho, Japan
- H. Dzitko, G. Phillips
F4E, Germany
- E. Kako, H. Sakai, K. Umemori
KEK, Ibaraki, Japan
|
|
|
The staged installation and commissioning of LIPAc is ongoing at Rokkasho Fusion Institute of QST, Japan for validating the low energy section of the IFMIF deuteron accelerator up to 9 MeV. The LIPAc Superconducting Radio Frequency accelerator (SRF) cryomodule is assembled under the responsibility of the EU Home Team, and the assembly work recently started at Rokkasho in March 2019. To fulfil the cleanliness requirements for the assembly process, QST took the responsibility to prepare the infrastructure of a cleanroom and associated devices. In this present paper, the details of the preparation work for the cryomodule assembly made by QST will be presented.
|
|
|
Poster TUP105 [2.116 MB]
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-SRF2019-TUP105
|
|
About • |
paper received ※ 17 June 2019 paper accepted ※ 01 July 2019 issue date ※ 14 August 2019 |
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
WETEA3 |
Status of the IFMIF/EVEDA Superconducting Linac |
735 |
|
- N. Bazin, G. Devanz, H. Jenhani, O. Piquet
CEA-DRF-IRFU, France
- S. Chel
CEA-IRFU, Gif-sur-Yvette, France
- T. Ebisawa
QST, Aomori, Japan
- G. Phillips
F4E, Germany
- D. Regidor, F. Toral
CIEMAT, Madrid, Spain
|
|
|
The IFMIF accelerator aims to provide an accelerator-based D-Li neutron source to produce high intensity high energy neutron flux to test samples as possible candidate materials to a full lifetime of fusion energy reactors. A prototype of the low energy part of the accelerator (LIPAc) is under construction at Rokkasho Fusion Institute in Japan. It includes one cryomodule containing 8 half-wave resonators (HWR) operating at 175 MHz and eight focusing solenoids. The talk will cover the progress of developments in the IFMIF/EVEDA cryomodule: the qualification of 8 cavities, the RF conditioning results of 8 high-power couplers, the manufacturing and test of the 8 superconducting solenoids and the equivalent operational equivalent tests performed at Saclay. The assembling status of the cryomodule at Rokkasho site will also be presented.
|
|
|
Slides WETEA3 [11.091 MB]
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-SRF2019-WETEA3
|
|
About • |
paper received ※ 20 June 2019 paper accepted ※ 29 June 2019 issue date ※ 14 August 2019 |
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|