MOP092 Overview of LCLS-II Project Status at Fermilab 302
 
  • R.P. Stanek, T.T. Arkan, J.N. Blowers, C.M. Ginsburg, A. Grassellino, C.J. Grimm, B.J. Hansen, E.R. Harms, B.D. Hartsell, J.P. Holzbauer, J.A. Kaluzny, A.L. Klebaner, A. Martinez, T.H. Nicol, Y.O. Orlov, K.S. Premo, N. Solyak, J. Theilacker, G. Wu
    Fermilab, Batavia, Illinois, USA
 
  The superconducting RF Continuous-Wave (CW) Linac for the LCLS-II consists of thirty-five 1.3 GHz and two 3.9 GHz cryomodules that Fermilab and Jefferson Lab are jointly producing in collaboration with SLAC. Fermilab¿s scope of work is to build, test, and deliver half the 1.3 GHz and all the 3.9 GHz cryomodules and to design and procure components for the cryogenic distribution system. Fermilab has primary responsibility for delivering a working design. The cryomodule design basis was the European XFEL but several elements evolved to meet CW operation requirements and specifics of the SLAC tunnel. There have been several challenges faced during the design, assembly, testing and transportation of the cryomodules which have required design updates. Success in overcoming these challenges is attributable to the strength of the LCLS-II SRF Collaboration (Fermilab, Jefferson Lab and SLAC with extensive help from DESY and CEA/Saclay). The cryogenic distribution system has progressed relatively well and there are valuable Lessons Learned. An overview of the status, accomplishments, problems encountered, solutions developed, and a summary of Lessons Learned will be presented.  
poster icon Poster MOP092 [0.393 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-MOP092  
About • paper received ※ 20 June 2019       paper accepted ※ 30 June 2019       issue date ※ 14 August 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THP060 Experience With LCLS-II Cryomodule Testing at Fermilab 1018
 
  • E.R. Harms, E. Cullerton, C.M. Ginsburg, B.J. Hansen, B.D. Hartsell, J.P. Holzbauer, J. Hurd, V.S. Kashikhin, M.J. Kucera, F.L. Lewis, A. Lunin, D.L. Newhart, D.J. Nicklaus, P.S. Prieto, O.V. Prokofiev, J. Reid, N. Solyak, R.P. Stanek, M.A. Tartaglia, G. Wu
    Fermilab, Batavia, Illinois, USA
  • C. Contreras-Martinez
    FRIB, East Lansing, Michigan, USA
  • J. Einstein-Curtis
    Private Address, Naperville, USA
 
  Funding: This manuscript has been authored by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the U.S. Department of Energy, Office of Science, Office of High Energy Physics.
The Cryomodule Test Stand (CMTS1) at Fermilab has been engaged with testing 8-cavity 1.3 GHz cryomodules designed and assembled for the LCLS-II project at SLAC National Accelerator Laboratory since 2016. Over these three years twenty cryomodules have been cooled to 2K and power tested in continuous wave mode on a roughly once per month cycle. Test stand layout and testing procedures are presented together with results from the cryomodules tested to date. Lessons learned and future plans will also be shared.
 
poster icon Poster THP060 [2.774 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-THP060  
About • paper received ※ 22 June 2019       paper accepted ※ 30 June 2019       issue date ※ 14 August 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)