Author: Forehand, D.
Paper Title Page
MOPB049 Upgraded Cavities for the CEBAF Cryomodule Rework Program 168
 
  • R.A. Rimmer, G. Cheng, G. Ciovati, W.A. Clemens, E. Daly, G.K. Davis, J. Follkie, D. Forehand, F. Fors, J. Guo, J. Henry, K. Macha, F. Marhauser, G.R. Myneni, L. Turlington
    JLab, Newport News, Virginia, USA
 
  Funding: Authored by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE-AC05-06OR23177.
The CEBAF cryomodule rework program has been a successful tool to recover and maintain the energy reach of the original baseline 6 GeV accelerator. The weakest original modules with eight five-cell cavities assembled in four 'pairs', with a specification when new of 20 MV per cryomodule (5 MV/m), are disassembled, re-cleaned with modern techniques and re-qualified to at least 50 MV (12.5 MV/m), (leading to the acronym 'C50'). The cost per recovered MV is much less than building new modules. However over time the stock of weak modules is being used up and the voltage gain per rework cycle is diminishing. In an attempt to increase the gain per cycle it is proposed to rework the cavities by replacing the original accelerating cells with new ones of an improved shape and better material. The original CEBAF HOM and FPC end groups are retained. The goal is to achieve up to 75 MV (18.75 MV/m) for the reworked module ('C75'). We report on the fabrication experience and test results of the first trial pair, containing two such reworked cavities.
 
poster icon Poster MOPB049 [1.503 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2017-MOPB049  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPB050 Cavity Processing and Testing Activities at Jefferson Lab for LCLS-II Production 173
 
  • L. Zhao, G.K. Davis, J. Follkie, D. Forehand, K. Macha, A.D. Palczewski, A.V. Reilly
    JLab, Newport News, Virginia, USA
 
  Funding: Work supported by Jefferson Science Associates, LLC under U.S. DOE Contracts DE-AC05-06OR23177 and DE-AC02-76SF00515 for the LCLS-II Project.
Cryomodule production for LCLS-II is well underway at Jefferson Lab. This paper explains the process flow for production cavities, from being received at the Test Lab to being assembled onto cavity strings. Taking our facility and infrastructure into consideration, process optimization and process control are implemented to ensure high quality products.
 
poster icon Poster MOPB050 [2.338 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2017-MOPB050  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)