Author: Lefort, B.
Paper Title Page
MOPAB177 ELENA Commissioning and Status 598
 
  • C. Carli, M.E. Angoletta, W. Bartmann, L. Bojtár, F. Butin, B. Dupuy, Y. Dutheil, M.A. Fraser, P. Freyermuth, D. Gamba, L.V. Jørgensen, B. Lefort, O. Marqversen, M. McLean, S. Ogur, S. Pasinelli, L. Ponce, G. Tranquille
    CERN, Geneva, Switzerland
 
  The Extra Low ENergy Antiproton ring ELENA is a small synchrotron recently constructed and commissioned to decelerate antiprotons injected from the Antiproton Decelerator AD with a kinetic energy of 5.3 MeV down to 100 keV. Controlled deceleration in the synchrotron, equipped with an electron cooler to reduce losses and generate dense bunches, allows the experiments, typically capturing the antiprotons in traps and manipulating them further, to improve the trapping efficiency by one to two orders of magnitude. During 2018, bunches with an energy of 100 keV with parameters close to nominal have been demonstrated, and first beams have been provided to an experiment in a new experimental zone. The magnetic transfer lines from the AD to the experiments have been replaced by electrostatic lines from ELENA. Commissioning of the new transfer lines and, in parallel, studies to better understand the ring with H beams from a dedicated source, have started in autumn 2020. The first 100 keV antiproton physics run using ELENA will start in late summer 2021.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2021-MOPAB177  
About • paper received ※ 18 May 2021       paper accepted ※ 14 June 2021       issue date ※ 23 August 2021  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPAB366 Towards the Last Stages of the CERN’s AD-Target Area Consolidation Project and Recommissioning Plans to Resume Operation 3563
 
  • C. Torregrosa, C. Ahdida, A. Bouvard, A. Broche, S. Burger, M.E.J. Butcher, M. Calviani, V. Clerc, A. De Macedo, S. De Man, F.A. Deslande, M. Di Castro, T. Dobers, T. Feniet, R. Ferriere, E. Fornasiere, R. Franqueira Ximenes, T.J. Giles, J.L. Grenard, E. Grenier-Boley, G. Gräwer, M. Guinchard, M.D. Jedrychowski, K. Kershaw, B. Lefort, E. Lopez Sola, J.M. Martin Ruiz, A. Martínez Sellés, G. Matulenaite, C.Y. Mucher, A. Newborough, M. Perez Ornedo, E. Perez-Duenas, A. Perillo-Marcone, L. Ponce, N. Solieri, M.B. Szewczyk, P.A. Thonet, M.A. Timmins, A. Tursun, W. Van den Broucke, F.M. Velotti, C. Vendeuvre, V. Vlachoudis
    CERN, Meyrin, Switzerland
  • J.C. Espadanal
    LIP, Lisboa, Portugal
 
  Antiprotons are produced at CERN at the Antiproton Decelerator (AD) Target Area by impacting 26 GeV/c proton beams onto a fixed target. Further collection, momentum selection, and transport of the secondary particles - including antiprotons - towards the AD ring is realised by a 400 kA pulsed magnetic horn and a set of magnetic dipoles and quadrupoles. A major consolidation of the area - in operation since the 80s - has taken place during the CERN Long Shutdown 2 (2019-2021). Among other activities, such upgrade included: (i) Installation of a new air-cooled target design and manufacturing of a new batch of magnetic horns, including a surface pulsing test-bench for their validation and fine-tuning (ii) Installation of a new positioning and maintenance system for the target and horn (iii) Refurbishment and decontamination of the Target Area and its equipment, (iv) Construction of a new surface service building to house new nuclear ventilation systems. This contribution presents an overview of such activities and lesson learnt. In addition, it provides the latest results from refractory metals R&D for the antiproton target and a summary of the recommissioning and optimization plans.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2021-WEPAB366  
About • paper received ※ 18 May 2021       paper accepted ※ 21 June 2021       issue date ※ 01 September 2021  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)