Author: Emery, J.
Paper Title Page
MOPAB316 Commissioning the New CERN Beam Instrumentation Following the Upgrade of the LHC Injector Chain 976
 
  • F. Roncarolo, S. Bart Pedersen, J.M. Belleman, D. Belohrad, M. Bozzolan, C. Bracco, S. Di Carlo, J. Emery, A. Goldblatt, A. Guerrero, S. Levasseur, A. Navarro Fernandez, E. Renner, H.S. Sandberg, J.W. Storey, J. Tan, J. Tassan-Viol
    CERN, Geneva, Switzerland
  • A. Navarro Fernandez
    UPC, Barcelona, Spain
  • E. Renner
    TU Vienna, Wien, Austria
 
  The LHC injectors Upgrade (LIU) program has been fully implemented during the second long shutdown (LS2), which took place in 2019-20. In this context, new or upgraded beam instrumentation was developed to cope with H beam in LINAC4 and the new Proton Synchrotron Booster (PSB) injection systems which would provide high brightness proton beams in the rest of the injector complex. After a short overview of the newly installed diagnostics, the main focus of this paper will move to the instruments already commissioned with the beam. This will include LINAC4 diagnostics, the PSB H0/H monitor, the PSB Trajectory Measurement System, and the PS beam gas ionization monitor. In addition, particular emphasis will be given to the first operational experience with the new generation of fast wire scanners installed in all injector synchronous.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2021-MOPAB316  
About • paper received ※ 19 May 2021       paper accepted ※ 17 June 2021       issue date ※ 14 August 2021  