Author: Di Pirro, G.
Paper Title Page
MOPMB017 Design Issues for the Optical Transition Radiation Screens for theELI-NP Compton Gamma Source 118
 
  • M. Marongiu, A. Giribono, A. Mostacci, V. Pettinacci
    INFN-Roma, Roma, Italy
  • D. Alesini, E. Chiadroni, F. Cioeta, G. Di Pirro, V.L. Lollo, L. Pellegrino, V. Shpakov, A. Stella, C. Vaccarezza, A. Variola
    INFN/LNF, Frascati (Roma), Italy
  • A. Cianchi
    INFN-Roma II, Roma, Italy
  • L. Palumbo
    University of Rome La Sapienza, Rome, Italy
 
  A high brightness electron LINAC is being built in the Compton Gamma Source at the ELI Nuclear Physics facility in Romania. To achieve the design luminosity, a train of 32, 16 ns spaced, bunches with a nominal charge of 250 pC will collide with the laser beam in the interaction point. Electron beam spot size is measured with optical transition radiation profile monitors. In order to measure the beam properties along the train, the screens must sustain the thermal stress due to the energy deposited by the bunches; moreover the optical radiation detecting system must have the necessary accuracy and resolution. This paper deals with the analytical studies as well as numerical simulations to investigate the thermal behaviour of the screens impinged by the nominal bunch; the design and the performance of the optical detection line is discussed as well.  
DOI • reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-MOPMB017  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPMY041 Delivery Status of the ELI-NP Gamma Beam System 1635
 
  • S. Tomassini, D. Alesini, A. Battisti, R. Boni, F. Cioeta, A. Delle Piane, E. Di Pasquale, G. Di Pirro, A. Falone, A. Gallo, S.I. Incremona, V.L. Lollo, A. Mostacci, S. Pioli, R. Ricci, U. Rotundo, A. Stella, C. Vaccarezza, A. Vannozzi, A. Variola
    INFN/LNF, Frascati (Roma), Italy
  • A. Bacci, D.T. Palmer, L. Serafini
    Istituto Nazionale di Fisica Nucleare, Milano, Italy
  • N. Bliss
    STFC/DL, Daresbury, Warrington, Cheshire, United Kingdom
  • F. Cardelli
    INFN-Roma1, Rome, Italy
  • K. Cassou, Z.F. Zomer
    LAL, Orsay, France
  • G. D'Auria
    Elettra-Sincrotrone Trieste S.C.p.A., Basovizza, Italy
  • A. Giribono, V. Pettinacci
    INFN-Roma, Roma, Italy
  • C. Hill
    STFC/DL/ASTeC, Daresbury, Warrington, Cheshire, United Kingdom
  • L. Palumbo
    Rome University La Sapienza, Roma, Italy
  • L. Piersanti
    University of Rome La Sapienza, Rome, Italy
 
  The ELI-NP GBS is a high intensity and monochromatic gamma source under construction in Magurele (Romania). The design and construction of the Gamma Beam System complex as well as the integration of the technical plants and the commissioning of the overall facility, was awarded to the Eurogammas Consortium in March 2014. The delivery of the facility has been planned in for 4 stages and the first one was fulfilled in October 31st 2015. The engineering aspects related to the delivery stage 1 are presented.  
DOI • reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-TUPMY041  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOW004 Status of the STAR Project 1747
 
  • A. Bacci, I. Drebot, L. Serafini, V. Torri
    Istituto Nazionale di Fisica Nucleare, Milano, Italy
  • R.G. Agostino, R. Barberis, M. Ghedini, F. Martire, C. Pace
    UNICAL, Arcavacata di Rende, Italy
  • D. Alesini, M. Bellaveglia, J.J. Beltrano, F.G. Bisesto, G. Borgese, B. Buonomo, G. Di Pirro, G. Di Raddo, A. Esposito, A. Gallo, A. Ghigo, F. Iungo, L. Pellegrino, A. Stella, C. Vaccarezza
    INFN/LNF, Frascati (Roma), Italy
  • A. Cianchi
    INFN-Roma II, Roma, Italy
  • G. D'Auria, A. Fabris, M. Marazzi
    Elettra-Sincrotrone Trieste S.C.p.A., Basovizza, Italy
  • V. Petrillo
    Universita' degli Studi di Milano, Milano, Italy
  • E. Puppin
    Politecnico/Milano, Milano, Italy
  • M. Rossetti Conti
    Universita' degli Studi di Milano & INFN, Milano, Italy
 
  This paper reports on the final design and the work in progress on the STAR project (IPAC2014:WEPRO115), which is under construction at the Univ. of Calabria (Italy). The project is devoted to the construction of an advanced Thomson source of monochromatic tunable, ps-long, polarized X-ray beams, ranging from 40 up to 140 KeV . At present the buildings and main plants have been completed as the acquisition of main components: the RF photo-injector, the accelerating section, laser systems for collision and photo-cathode, RF Power Source and magnets are ready to start installation and site acceptance tests. The design of laser lines is complete and simulated by ZEMAX, aiming to minimize energy losses, optical distortions and providing a tunable experimental setup as well. The RF power network is close to be tested, it's based on a 55MW (2.5us pulse) S-band Klystron driven by a 500kV Pulse Forming Network based modulator and a Low Level RF system, running at 100 Hz. The Control System is been designed using EPICS and allows to manage easily and fastly each machine parameter. We expect to start commissioning the machine by the end of 2016 and obtain the first collisions within the first part of 2017.  
DOI • reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-TUPOW004  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOW041 Optimization Studies for the Beam Dynamic in the RF Linac of the ELI-NP Gamma Beam System 1850
 
  • C. Vaccarezza, D. Alesini, M. Bellaveglia, M.E. Biagini, G. Di Pirro, A. Gallo, A. Ghigo, S. Guiducci, A. Vannozzi, A. Variola
    INFN/LNF, Frascati (Roma), Italy
  • A. Bacci, I. Drebot, D.T. Palmer, A.R. Rossi, L. Serafini
    Istituto Nazionale di Fisica Nucleare, Milano, Italy
  • G. Campogiani
    Rome University La Sapienza, Roma, Italy
  • A. Giribono, A. Mostacci, L. Palumbo
    University of Rome La Sapienza, Rome, Italy
  • V. Petrillo
    Universita' degli Studi di Milano & INFN, Milano, Italy
  • L. Sabbatini
    Consorzio Laboratorio Nicola Cabibbo, Frascati, Italy
 
  The ELI-NP GBS is an high spectral density and monochromatic gamma ray source based upon the inverse Compton scattering effect now under construction in Magurele.  Its relevant specifications are brilliance higher than 1021, 0.5% monochromaticity and a 0.2-19.5 MeV energy tunability. Strong requirements are set for the electron beam dynamic: the control of both the transverse normalized emittance and the energy spread to optimize the spectral density and guarantee the mono chromaticity of the emitted radiation. On this basis the RF Linac optimization has been performed for the designed energy range; a sensitivity analysis of the machine to possible jitters, errors and so on has been also performed, the simulations results hare here presented.  
DOI • reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-TUPOW041  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPOY003 The Turn-key Control System for the ELI-NP Gamma Beam System 4091
 
  • S. Pioli, G. Di Pirro
    INFN/LNF, Frascati (Roma), Italy
  • F. Amand, V.A. Isaev, A. Jesenko, A. Manojlovic, R. Modic, I. Mustac, G. Pajor
    Cosylab, Ljubljana, Slovenia
  • B.G. Martlew, A. Oates
    STFC/DL, Daresbury, Warrington, Cheshire, United Kingdom
 
  The new Gamma Beam System (GBS) under construction in Magurele (RO) by the consortium EuroGammas led by INFN, as part of the ELI-NP project, can provide gamma rays that open new possibilities for nuclear photonics and nuclear physics. In the ELI-GBS, gamma rays are produced by means of Compton back-scattering to get mono-chromaticity (0,1% bandwidth), a high flux (1013 photon/s the highest in the world), tunable directions and energies up to 19 MeV. Such gamma beam characteristic is obtained when a high-intensity laser collides a high-brightness electron-beam with energies up to 720 MeV. In order to increase the gamma beam flux, the electron beam operates at a repetition rate of 100 Hz in a multi-bunch mode: trains of 32 bunches, 16 ns apart, interact with the laser pulse recirculated 32 times through the interaction point. The EPICS Control System collects data from all sub-systems, constantly monitoring to ensure the safety of the ELI-GBS facility. This paper describes all the aspects of the ELI-GBS turn-key Control System, such as hardware integration, micro-bunches diagnostics, high level applications, the data network and the pico-second timing system.  
DOI • reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-THPOY003  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)