Author: Reymond, H.
Paper Title Page
MOPKN007 Lhc Dipole Magnet Splice Resistance From Sm18 Data Mining 98
 
  • H. Reymond, O.O. Andreassen, C. Charrondière, G. Lehmann Miotto, A. Rijllart, D. Scannicchio
    CERN, Geneva, Switzerland
 
  The splice incident which happened during commissioning of the LHC on the 19th of September 2008 caused damage to several magnets and adjacent equipment. This raised not only the question of how it happened, but also about the state of all other splices. The inter magnet splices were studied very soon after with new measurements, but the internal magnet splices were also a concern. At the Chamonix meeting in January 2009, the CERN management decided to create a working group to analyse the provoked quench data of the magnet acceptance tests and try to find indications for bad splices in the main dipoles. This resulted in a data mining project that took about one year to complete. This presentation describes how the data was stored, extracted and analysed reusing existing LabVIEW™ based tools. We also present the encountered difficulties and the importance of combining measured data with operator notes in the logbook.  
poster icon Poster MOPKN007 [5.013 MB]  
 
WEPMU010 Automatic Analysis at the Commissioning of the LHC Superconducting Electrical Circuits 1073
 
  • H. Reymond, O.O. Andreassen, C. Charrondière, A. Rijllart, M. Zerlauth
    CERN, Geneva, Switzerland
 
  Since the beginning of 2010 the LHC has been operating in a routinely manner, starting with a commissioning phase and then an operation for physics phase. The commissioning of the superconducting electrical circuits requires rigorous test procedures before entering into operation. To maximize the beam operation time of the LHC these tests should be done as fast as procedures allow. A full commissioning needs 12000 tests and is required after circuits have been warmed above liquid nitrogen temperature. Below this temperature, after an end of year break of two months, commissioning needs about 6000 tests. Because the manual analysis of the tests takes a major part of the commissioning time, we proceeded to the automation of the existing analysis tools. We present the way in which these LabVIEW™ applications were automated. We evaluate the gain in commissioning time and reduction of experts on night shift observed during the LHC hardware commissioning campaign of 2011 compared to 2010. We end with an outlook at what can be further optimized.  
poster icon Poster WEPMU010 [3.124 MB]