MOPEA063 The First Results of the NESTOR Commissioning 225
 
  • A.Y. Zelinsky, V.P. Androsov, O. Bezditko, V.N. Boriskin, P. Gladkikh, A.N. Gordienko, V.A. Grevtsev, A. Gvozd, V.E. Ivashchenko, A.A. Kalamayko, I.I. Karnaukhov, I.M. Karnaukhov, D. Korzhov, V.P. Kozin, V.A. Kushnir, V.P. Lyashchenko, M.P. Maksim, V.S. Margin, N.I. Mocheshnikov, V.V. Mytrochenko, A. Mytsykov, F.A. Peev, O.V. Ryezayev, V.P. Sergienko, A.A. Shcherbakov, S. Sheyko, V.L. Skirda, Y.N. Telegin, V.I. Trotsenko, O.P. Zolochevskij, O.D. Zvonarjova
    NSC/KIPT, Kharkov, Ukraine
 
  In the paper the first results of the NESTOR facility are presented. 60 MeV electron linac injector has been tested and the first electron beam with project parameters was registered at the screen monitors. Electron beam was passed through the transportation channel and injection system. As a result, the first turn of the storage ring was closed.  
 
WEPWA060 The Kharkov X-ray Generator Facility NESTOR 2253
 
  • A.A. Shcherbakov, V.P. Androsov, N. Ayzatsky, V.N. Boriskin, E.V. Bulyak, A.N. Dovbnya, P. Gladkikh, A.N. Gordienko, V.A. Grevtsev, A. Gvozd, V.E. Ivashchenko, A.A. Kalamayko, I.I. Karnaukhov, I.M. Karnaukhov, V.P. Kozin, V.A. Kushnir, V.P. Lyashchenko, V.S. Margin, N.I. Mocheshnikov, V.V. Mytrochenko, A. Mytsykov, I.M. Neklyudov, T.F. Nikitina, F.A. Peev, O.V. Ryezayev, V.L. Skirda, V.A. Skomorokhov, Y.N. Telegin, V.I. Trotsenko, A.Y. Zelinsky, O.D. Zvonarjova
    NSC/KIPT, Kharkov, Ukraine
  • J.I.M. Botman
    TUE, Eindhoven, The Netherlands
  • I.V. Drebot
    LAL, Orsay, France
 
  The last few years the sources of the X-rays NESTOR based on a storage ring with low beam energy and Compton scattering of intense laser beam are under design and development in NSC KIPT. The main task of the project is to develop compact intense X-ray generator on the base of relatively cheap accelerator equipment and up-to-date laser technologies. The paper is devoted to description of the last results on construction and commissioning of the facility.  
 
THPFI079 Start-up of the NESTOR Facility Vacuum System 3478
 
  • A.Y. Zelinsky, A.N. Gordienko, V.A. Grevtsev, I.I. Karnaukhov, I.M. Karnaukhov, N.I. Mocheshnikov, A. Mytsykov, V.L. Skirda
    NSC/KIPT, Kharkov, Ukraine
 
  The Kharkov X-ray generator NESTOR based on Compton backscattering is under commissioning. The vacuum system of the complex integrates a linear accelerator-injector, the beam transport channel and the electron storage ring with energy range from 40 to 225 MeV. Elements of vacuum chambers, pumping facilities, cleaning surfaces procedures are described. Chambers are made of stainless steel (SS). After vacuum pretesting pressure 5 × 10-9 Torr in the storage chambers ring achieved.