Author: Cole, J.R.T.
Paper Title Page
MOPFI054 Upgrades for the CERN PSB-TO-PS Transfer at 2 GeV 404
 
  • W. Bartmann, J. Borburgh, J.R.T. Cole, S.S. Gilardoni, B. Goddard, O. Hans, M. Hourican, L. Sermeus, R. Steerenberg
    CERN, Geneva, Switzerland
  • C.H. Yu
    IHEP, Beijing, People's Republic of China
 
  The CERN PS Booster extraction energy will be upgraded from 1.4 to 2.0 GeV to alleviate the direct space charge tune shift in the PS. The focussing structure of the transfer line will be modified in order to better match the optics between the PSB and the PS. The optics of the PS at injection and, with it, of the transfer line can be adapted to reduce the continuous losses from the already injected and circulating beam bumped towards the septum. Experimental results of the optics optimisation and probing the injection kicker gap will be shown.  
 
THPWO078 Status of the Upgrade of the CERN PS Booster 3939
 
  • K. Hanke, O. Aberle, M. E. Angoletta, W. Bartmann, S. Bartolome, E. Benedetto, C. Bertone, A. Blas, P. Bonnal, J. Borburgh, D. Bozzini, A.C. Butterworth, C. Carli, E. Carlier, J.R.T. Cole, P. Dahlen, M. Delonca, T. Dobers, A. Findlay, R. Froeschl, J. Hansen, D. Hay, S. Jensen, J.-M. Lacroix, P. Le Roux, L.A. Lopez Hernandez, C. Maglioni, A. Masi, G.W. Mason, S.J. Mathot, B. Mikulec, Y. Muttoni, A. Newborough, D. Nisbet, S. Olek, M.M. Paoluzzi, A. Perillo-Marcone, S. Pittet, B. Puccio, V. Raginel, B. Riffaud, I. Ruehl, A. Sarrió Martínez, J. Tan, B. Todd, V. Venturi, W.J.M. Weterings
    CERN, Geneva, Switzerland
 
  The CERN PS Booster (PSB) is presently undergoing an ambitious consolidation and upgrade program within the frame of the LHC Injectors Upgrade (LIU) project. This program comprises a new injection scheme for H ions from CERN’s new Linac4, the replacement of the main RF systems and an energy upgrade of the PSB rings from 1.4 to 2.0 GeV which includes the replacement of the main magnet power supply as well as the upgrade of the extraction equipment. This paper describes the status and plans of this work program.  
 
THPWO079 A Possible Scheme to Deliver 2 GeV Beams from the CERN PS Booster to the ISOLDE Facility 3942
 
  • K. Hanke, W. Bartmann, J.R.T. Cole, R. Fernandes Luis, A. Newborough, S. Pittet, T. Stora, D. Voulot
    CERN, Geneva, Switzerland
 
  The CERN PS Booster (PSB) is presently undergoing an upgrade program to increase its beam energy from 1.4 GeV to 2.0 GeV. While this energy upgrade is targeted at LHC-type beams, the option of delivering 2 GeV beams to the ISOLDE facility has also been investigated. In this paper we present a preliminary study for delivering 2 GeV beams to ISOLDE including the physics motivation and the implications on the accelerator hardware.