Paper | Title | Page |
---|---|---|
MOZGBD3 | Performance of the First LCLS-II Cryomodules: Issues and Solutions | 34 |
|
||
LCLS-II 4 GeV linac is on the middle production stage. Linac contains 40 cryomodules of 1.3 GHz and 3 cryomodules of 3.9 GHz, including spares. Fermilab and JLAB share responsibility for cryomodule design, assembly and test. Paper will overview the performance of the cryomodules it the tests, lessons learned and modifications in design to improve performance. | ||
![]() |
Slides MOZGBD3 [8.630 MB] | |
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2018-MOZGBD3 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
WEPMK010 | LCLS-II Cryomodules Production at Fermilab | 2652 |
|
||
Funding: DOE LCLS-II is a planned upgrade project for the linear coherent light source (LCLS) at SLAC. The LCLS-II linac will consist of thirty-five 1.3 GHz and two 3.9 GHz superconducting RF continuous wave (CW) cryomodules that Fermilab and Jefferson Lab are currently producing in collaboration with SLAC. The LCLS-II 1.3 GHz cryomodule design is based on the European XFEL pulsed-mode cryomodule design with modifications needed for CW operation. Two prototype cryomodules had been assembled and tested. After prototype cryomodule tests, both laboratories have increased cryomodule production rate to meet the challenging LCLS-II project installation schedule requirements of approximately one cryomodule per month per laboratory. Fermilab is at half point for the production, meaning that 6 cryomodules are fully assembled and tested. This paper presents Fermilab Cryomodule Assembly Facility (CAF) infrastructure for the LCLS-II cryomodules assembly, production experience at the half point emphasizing the challenges and mitigations. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2018-WEPMK010 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
WEPML001 | Passive Microphonics Mitigation during LCLS-II Cryomodule Testing at Fermilab | 2668 |
|
||
Funding: This manuscript has been authored by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the U.S. Department of Energy, Office of Science, Office of High Energy Physics. The LCLS-II project calls for cryomodule production and testing at both Fermilab and JLab. Due to low beam loading and high cavity quality factor, the designed peak detuning specification is 10 Hz. Initial testing showed peak detuning up to 150 Hz with a complex and varying time-structure, showing both fast (1-2 second) and slow (1-2 hour) drifts in amplitude and spectrum. Extensive warm and cold testing showed Thermoacoustic Oscillations in the cryogenic valves were the primary source of the microphonics. This was mitigated by valve wipers and valve re-plumbing, resulting in a greatly improved cavity detuning environment. Additional modifications were made to the cavity mechanical supports and Fermilab test stand to improve detuning performance. These modifications and testing results will be presented. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2018-WEPML001 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |