Paper | Title | Page |
---|---|---|
MOP092 | Overview of LCLS-II Project Status at Fermilab | 302 |
|
||
The superconducting RF Continuous-Wave (CW) Linac for the LCLS-II consists of thirty-five 1.3 GHz and two 3.9 GHz cryomodules that Fermilab and Jefferson Lab are jointly producing in collaboration with SLAC. Fermilab¿s scope of work is to build, test, and deliver half the 1.3 GHz and all the 3.9 GHz cryomodules and to design and procure components for the cryogenic distribution system. Fermilab has primary responsibility for delivering a working design. The cryomodule design basis was the European XFEL but several elements evolved to meet CW operation requirements and specifics of the SLAC tunnel. There have been several challenges faced during the design, assembly, testing and transportation of the cryomodules which have required design updates. Success in overcoming these challenges is attributable to the strength of the LCLS-II SRF Collaboration (Fermilab, Jefferson Lab and SLAC with extensive help from DESY and CEA/Saclay). The cryogenic distribution system has progressed relatively well and there are valuable Lessons Learned. An overview of the status, accomplishments, problems encountered, solutions developed, and a summary of Lessons Learned will be presented. | ||
![]() |
Poster MOP092 [0.393 MB] | |
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-MOP092 | |
About • | paper received ※ 20 June 2019 paper accepted ※ 30 June 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
TUP096 | Optimization of Clean Room Infrastructure and Procedure During LCLS-II Cryomodule Production at Fermilab | 695 |
|
||
Funding: The work is supported by Fermilab which is operated by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the United States Department of Energy. Optimization of Fermilab string assembly procedure and infrastructure has yielded a significant improvement of cryomodule particulate counts. Late production of LCLS-II cryomodules were tested at CMTF at Fermilab and showed little to no x-ray up to administrative limit. The paper describes the field emission measurement instrumentation, field emission results of LCLS-II cyomodules, clean room infrastructure upgrade and procedure optimization. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-TUP096 | |
About • | paper received ※ 23 June 2019 paper accepted ※ 30 June 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
TUP101 | LCLS-II Cryomodules Production Experience and Lessons Learned at Fermilab | 709 |
|
||
LCLS-II is a planned upgrade project for the linear coherent light source (LCLS) at SLAC. The LCLS-II Linac will consist of thirty-five 1.3 GHz and two 3.9 GHz superconducting RF continuous wave (CW) cryomodules that Fermilab and Jefferson Lab are currently producing in collaboration with SLAC. The LCLS-II 1.3 GHz cryomodule design is based on the European XFEL pulsed-mode cryomodule design with modifications needed for CW operation. Two prototype cryomodules had been assembled and tested. After prototype cryomodule tests, both laboratories have increased their cryomodule production rate to meet the challenging LCLS-II project installation schedule requirements of approximately one cryomodule per month per laboratory. To date, Fermilab has completed the assembly and testing of sixteen 1.3 GHz cryomodules. Fermilab has successfully shipped five CMs to SLAC and will continue to ship with a two-week throughput. The first 3.9 GHz cryomodule assembly is scheduled to start in June 2019; production readiness verifications are in progress. This paper presents LCLS-II cryomodule assembly and production experience, emphasizing the challenges, the mitigations and lessons learned | ||
![]() |
Poster TUP101 [0.834 MB] | |
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-TUP101 | |
About • | paper received ※ 20 June 2019 paper accepted ※ 30 June 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |