Xu, H.

Paper Title Page
WOAB002 Status of the Shanghai Synchrotron Radiation Facility 214
 
  • Z. Zhao, H. Ding, H. Xu
    SINAP, Shanghai
 
  The Shanghai Synchrotron Radiation Facility (SSRF) made its ground breaking at Zhang-Jiang High Tech Park on Dec.25, 2004 and moved into its construction phase with the plan of commencing user’s operation from April 2009. The SSRF complex is based on a 3.5GeV storage ring optimized to operate with top-up injection, mini-gap undulators and superconducting RF system, the 432m circumference storage ring provides 18 ID straight sections (4X12.0m and 16X6.5m), and four of them will be used for the first SSRF beam lines. The SSRF project was proposed in 1995, and since then it has experienced the conceptual design stage, the R&D program and the design optimization phase. This paper presents the updated design specifications and the construction status of the SSRF project.  
RPAE076 The Commission of Hefei Light Source After Reconstruction 3967
 
  • H. Xu, H. He, W. Li, G. Liu, L. Liu, S. Shang, B. Sun, L. Wang
    USTC/NSRL, Hefei, Anhui
 
  After the new four-kicker injection bump system was mounted, it was found that the magnetic field of four–kicker magnet through the same pulse current is different each other, the reason is which the width of pulse magnet fields is not same, so the four-kickers can not form completely local bump, and produce large global orbit distortion,and lead to beam loss. At last we found that the films of ceramic chambers were not plated evenly. The new rf system have two low level control circle circuits, which are the frequency and amplitude automatic adjustment systems. Because the energy of injection electron beam is 200MeV, and radiation damping is weak, so the gain of amplitude circuit was adjusted to the small value not to disturb beam.The beam load is large,and Robinson instability happen easily, so the small detune angle is preset. The Octupoles were inserted in ring for damping instability, and over compensated chromaticity was adjusted.Superconductor wiggler bring the variation of beta function, and the beam life time decreased from 8 hours to about 3 hours. By adjusting the beta functions close to situation ago, the beam lifetime was improved.  
RPPT049 Linear Optics Compensation of the Superconducting Wiggler in HLS 3037
 
  • L. Wang, G. Feng, W. Li, H. Xu, H. Zhang
    USTC/NSRL, Hefei, Anhui
 
  Hefei Light Source is a dedicated VUV light source. A superconducting wiggler magnet with 6 Tesla magnetic field was installed on the storage ring to generate hard X-ray radiation. With the compensation of tune shift due to insertion device, beam was successfully stored, but the beam lifetime was decreased much. In order to cure the lifetime, a simple hard-edge model of the wiggler was constructed in lattice simulation code and the compensation scheme was extensively studied again. Calculation showed that it is difficulty to localize the strong focusing effects from wiggler magnet. Then, a new scheme was brought forward and experimental result showed that it can restore the beam lifetime largely. As the application of LOCO method in HLS, a new compensation scheme was calculated by response matrix fitting, and the experimental result also presented in this paper.