MOOP01 The SARAF-LINAC Project Status 38
MOPLR075   use link to see paper's listing under its alternate paper code  
 
  • N. Pichoff, B. Gastineau, P. Girardot
    CEA/DSM/IRFU, France
  • N. Bazin, D. Chirpaz-Cerbat, B. Dalena, G. Ferrand, P. Gastinel, F. Gougnaud, M. Jacquemet, C. Madec, P.A.P. Nghiem, D. Uriot
    CEA/IRFU, Gif-sur-Yvette, France
  • P. Bertrand, M. Di Giacomo, R. Ferdinand, J.-M. Lagniel
    GANIL, Caen, France
 
  SNRC and CEA collaborate to the upgrade of the SARAF accelerator to 5 mA CW 40 MeV deuteron and proton beams (Phase 2). CEA is in charge of the design, construction and commissioning of the superconducting linac (SARAF-LINAC Project). This paper presents to the accelerator community the status at August 2016 of the SARAF-LINAC Project.  
slides icon Slides MOOP01 [4.978 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-LINAC2016-MOOP01  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPLR062 European Spallation Source (ESS) Normal Conducting Front End Status Report 274
 
  • W. Wittmer, P.O. Gustavsson, F. Hellström, G. Hulla
    ESS, Lund, Sweden
  • I. Bustinduy, P.J. González, G. Harper, S. Varnasseri, C. de la Cruz
    ESS Bilbao, Zamudio, Spain
  • L. Celona, S. Gammino, L. Neri
    INFN/LNS, Catania, Italy
  • A.C. Chauveau, D. Chirpaz-Cerbat
    CEA/IRFU, Gif-sur-Yvette, France
  • F. Grespan, A. Pisent
    INFN/LNL, Legnaro (PD), Italy
  • P. Mereu
    INFN-Torino, Torino, Italy
  • O. Midttun
    University of Bergen, Bergen, Norway
  • O. Piquet, B. Pottin
    CEA/DSM/IRFU, France
 
  The European Spallation Source (ESS) will deliver first protons on target by mid 2019. Civil construction of the accelerator tunnel has made good progress and will allow starting installation of the normal conducting frond end (NCFE) by end of 2017. To achieve these milestones the design of all major beam line components have been completed and the construction of the subsystems begun. We report on the advancement of the subsystems and the commissioning progress of the microwave discharge Proton Source (PS-ESS).  
poster icon Poster MOPLR062 [1.396 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-LINAC2016-MOPLR062  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPLR054 Recent RF and Mechanical Developments for the ESS RFQ 978
 
  • N. Misiara, A. Albéri, G. Bourdelle, A.C. Chauveau, D. Chirpaz-Cerbat, M. Desmons, A.C. France, M. Lacroix, P.-A. Leroy, J. Neyret, G. Perreu, O. Piquet, B. Pottin, H. Przybilski, N. Sellami
    CEA/IRFU, Gif-sur-Yvette, France
 
  The ESS Radio-Frequency Quadrupole (RFQ) is a 4-vane resonant cavity designed at the frequency of 352.21 MHz frequency. It must accelerate and bunch a 70 mA proton beams from 75 keV to 3.62 Mev of energy with a 4% duty cycle. The current 3D design evolved and is currently divided in 5 segments for a total length of 4.54 m. This paper presents a complete radiofrequency (RF) analysis using the ANSYS Multiphysics 3D RF simulating code HFSS and a RFQ 4-wire transmission line model (TLM). It describes the integrated cooling strategy based on a coupling between the RF power losses and the thermo-mechanical physics in order to allow a proper RFQ tuning once under operation.  