Author: Vytla, V.K.
Paper Title Page
TUPAB296 LLRF Upgrade at the Argonne Wakefield Accelerator Test Facility 2176
 
  • W. Liu, D.S. Doran, G. Ha, P. Piot, J.G. Power, J.H. Shao, C. Whiteford, E.E. Wisniewski
    ANL, Lemont, Illinois, USA
  • L.R. Doolittle, D. Filippetto, D. Li, S. Paiagua, C. Serrano, V.K. Vytla
    LBNL, Berkeley, California, USA
 
  Funding: US Department of Energy, Office of Science
The Argonne Wakefiled Accelerator (AWA) Test Facility designed and operated a homemade LLRF system for the last 20 years. It is based on NI-PXI products that has now become obsolete. The AWA’s LLRF cannot keep up with the increasing stability demands of AWA’s upgraded facility. An overhaul of the system is strongly desired. With the support from DOE-HEP, the AWA is collaborating with Lawrence Berkeley National Laboratory (LBNL)to upgrade its LLRF system with modern instrumentation to meet the growing stability demands. An overview of AWA’s current LLRF system performance is presented together with the upgrade plan and expectations.
 
poster icon Poster TUPAB296 [1.943 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2021-TUPAB296  
About • paper received ※ 19 May 2021       paper accepted ※ 05 July 2021       issue date ※ 26 August 2021  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPAB299 Spallation Neutron Source Proton Power Upgrade Low-Level RF Control System Development 3363
 
  • M.T. Crofford, J.A. Ball, J.E. Breeding, M.P. Martinez, J.S. Moss, M. Musrock
    ORNL, Oak Ridge, Tennessee, USA
  • L.R. Doolittle, C. Serrano, V.K. Vytla
    LBNL, Berkeley, California, USA
  • J. Graham, C.K. Roberts, J.W. Sinclair, Z. Sorrell, S. Whaley
    ORNL RAD, Oak Ridge, Tennessee, USA
 
  Funding: * This material is based upon work supported by the U.S. Department of Energy, Office of Science, Office of Basic Energy Sciences, under contract number DE-AC05-00OR22725.
The Proton Power Upgrade (PPU) Project is approved for the Spallation Neutron Source at Oak Ridge National Laboratory and will double the proton beam power capability from 1.4 MW to 2.8 MW with 2 MW beam power available to the first target station. A second target station is planned and will utilize the remaining beam power in the future. The proton power increase will be supported with the addition of twenty-eight new superconducting cavities powered by 700 kW peak power klystrons to increase beam energy while increases to the beam current will be done with a combination of existing RF margin, and DTL HPRF upgrades. The original low-level RF control system has proven to be reliable over the past 15 years of operations, but obsolescence issues mandate a replacement system be developed for the PPU project. The replacement system is realized in a µTCA.4 platform using a combination of commercial off-the-shelf boards and custom hardware to support the requirements of PPU. This paper presents the prototype hardware, firmware, and software development activities along with preliminary testing results of the new system.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2021-WEPAB299  
About • paper received ※ 18 May 2021       paper accepted ※ 21 June 2021       issue date ※ 11 August 2021  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)