Author: Barbier, C.N.
Paper Title Page
TUPAB199 Progress on the Proton Power Upgrade at the Spallation Neutron Source 1876
 
  • M.S. Champion, C.N. Barbier, M.S. Connell, J. Galambos, M.P. Howell, S.-H. Kim, J.S. Moss, B.W. Riemer, K.S. White
    ORNL, Oak Ridge, Tennessee, USA
  • E. Daly
    JLab, Newport News, Virginia, USA
  • N.J. Evans, G.D. Johns
    ORNL RAD, Oak Ridge, Tennessee, USA
 
  Funding: ORNL is managed by UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U.S. Department of Energy. This research was supported by the DOE Office of Science, Basic Energy Science.
The Proton Power Upgrade Project at the Spallation Neutron Source (SNS) at Oak Ridge National Laboratory will double the proton power capability from 1.4 to 2.8 MW. This will be accomplished through an energy increase from 1.0 to 1.3 GeV and a beam current increase from 26 to 38 mA. The energy increase will be accomplished through the addition of 7 cryomodules to the linear accelerator (Linac). The beam current increase will be supported by upgrading several radio-frequency systems in the normal-conducting section of the Linac. Upgrades to the accumulator ring injection and extraction regions will accommodate the increase in beam energy. A new 2-MW-capable target and supporting systems will be developed and installed. Conventional facility upgrades include build-out of the existing klystron gallery and construction of a tunnel stub to facilitate future beam transport to the second target station. The project received approval to proceed with construction in October 2020. Procurements are in progress, and some installation activities have already occurred. Most of the installation will take place during three outages in 2022-2023. The project early finish is planned for 2025.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2021-TUPAB199  
About • paper received ※ 10 May 2021       paper accepted ※ 28 May 2021       issue date ※ 21 August 2021  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPAB367 Bubble Generation in the SNS 2 MW Mercury Target 3567
 
  • C.N. Barbier, M.P. Costa, K.C. Johns, D. Ottinger, F. Rasheed, B.W. Riemer, R.L. Sangrey, J.R. Weinmeister, D.E. Winder
    ORNL, Oak Ridge, Tennessee, USA
 
  The accelerator at the Spallation Neutron Source is currently being upgraded to increase the proton beam power from 1.4 MW to 2.8 MW. About 2 MW will go to the first target station, while the rest will go to the future second target station. The first target station uses a mercury target. When the short proton beam pulse hits it, strong pressure waves are developed inside the mercury and the vessel itself, causing weld failures and cavitation erosion. The pressure wave can be significantly mitigated by injecting small helium bubbles into the mercury. SNS has been injecting helium since 2017 using small orifices but has met challenges in fabrication and operations with them. Thus, for the 2 MW target, swirl bubblers will be used to increase gas injection and improve reliability. A 2 MW prototypical target was built and tested in a mercury process loop available at Oak Ridge National Laboratory. Acrylic viewports on the top of the target were used to determine the bubble size distribution (BSD) generated by the swirl bubblers. It was found that the bubblers were not only capable of generating small bubbles but that the BSD was independent of gas injection rate.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2021-WEPAB367  
About • paper received ※ 10 May 2021       paper accepted ※ 22 June 2021       issue date ※ 20 August 2021  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)