Author: Honda, T.
Paper Title Page
WEPAB044 Construction and Commissioning of Direct Beam Transport Line for PF-AR 2678
 
  • N. Higashi, S. Asaoka, K. Furukawa, K. Haga, K. Harada, T. Higo, T. Honda, H. Honma, N. Iida, H. Iwase, K. Kakihara, T. Kamitani, M. Kikuchi, Y. Kishimoto, Y. Kobayashi, K. Kodama, K. Kudo, T. Kume, K. Mikawa, T. Mimashi, F. Miyahara, H. Miyauchi, S. Nagahashi, H. Nakamura, N. Nakamura, T. Natsui, K.N. Nigorikawa, Y. Niwa, T. Nogami, T. Obina, Y. Ogawa, M. Ono, T. Ozaki, H. Sagehashi, T. Sanami, M. Sato, M. Satoh, T. Suwada, M. Tadano, T. Tahara, R. Takai, H. Takaki, S. Takasaki, M. Tanaka, Y. Tanimoto, M. Tawada, N. Toge, T. Uchiyama, A. Ueda, Y. Yamada, M. Yamamoto, M. Yoshida
    KEK, Ibaraki, Japan
 
  PF-AR was constructed as an accumulator ring for TRISTAN, and in the KEKB era it has been revitalized as a 6.5 GeV synchrotron radiation source. The injection energy was 3 GeV and the beam was accelerated to 6.5 GeV prior to the user run. The original beam transport line (BT) from the LINAC to the PF-AR shared its upstream part with the the BT line of KEKB High Energy Ring (HER). The injection-mode change from PF-AR to HER or vice versa needs about 10 minutes for the magnet cycling procedure of the shared part. In SuperKEKB, the upgrade of KEKB, the lifetime of HER is about 10 minutes. The mode-switch operation of the BT is, therefore, not allowed for maintaining the highest luminosity of the SuperKEKB. In order to avoid this problem, a new 6.5 GeV BT line dedicated to PF-AR has been constructed. This also enables the top-up injection for the user run. The commissioning of the new BT line has been completed in this March, and now the first user run has been operated successfully.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-WEPAB044  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPAB047 Concept of a New Generation Synchrotron Radiation Facility KEK Light Source 2687
 
  • T. Honda
    KEK, Ibaraki, Japan
 
  KEK has proposed a new SR facility: KEK Light Source (KEK-LS) towards the completion of the first half of the 2020s. The energy and the natural horizontal emittance are 3 GeV and 0.13 nm rad, respectively. To mitigate the intra-beam scattering effect, we are planning to install third harmonic RF cavities. The extremely low emittance ring has been designed based on the Hybrid Multi-Bend Achromatic (HMBA) lattice, which was originally developed at the ESRF upgrade project. We have modified it to insert a short straight section at the center of the unit cell. The number of unit cells is 20, and the circumference is about 570 m. Except for an RF section and an injection section, the ring can accommodate 18 undulators in the long straight sections of 5.6 m, and the additional 20 short straight section of 1.2 m will be used for short-period narrow-gap undulators. If we assume an undulator of the magnetic period 20 mm, total length 5.0 m, and the smallest gap 4 mm, the SR brightness approaches 1022 Photons/mrad2/mm2/s/0.1%B.W. at the X-ray range. It has a high coherent fraction of about 20% at the diffraction limit wavelength 0.32 keV.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-WEPAB047  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPVA059 Construction of the New Septum Magnet Systems for PF-Advanced Ring 3398
 
  • A. Ueda, S. Asaoka, T. Honda, S. Nagahashi, N. Nakamura, T. Nogami, H. Takaki, T. Uchiyama
    KEK, Ibaraki, Japan
 
  From July 2016 we are constructing a new beam transport (BT) line for the Photon Factory Advanced Ring (PF-AR). The new BT line was designed to transport the full energy 6.5-GeV beam directly from the LINAC, and the top up injection will be possible for the PF-AR. We designed and produced new pulsed septum magnet systems for this project. Two pulsed septum magnets are used for the injection of the 6.5-GeV beam. The septum magnets were constructed with a passive type magnet, a copper eddy current shield and a silicon steel magnetic shield. The magnetic fields of these magnets have been measured by the search coil method. We paid attention to evaluating eddy current losses of the SUS beam duct in the magnetic field measurement.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-WEPVA059  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPVA060 Construction of the New Kicker Magnet Systems for PF-Advanced Ring 3401
 
  • A. Ueda, S. Asaoka, T. Honda, S. Nagahashi, N. Nakamura, T. Nogami, H. Takaki, T. Uchiyama
    KEK, Ibaraki, Japan
 
  From July 2016 we are constructing a new beam transport (BT) line for the Photon Factory Advanced Ring (PF-AR). The new BT line was designed to transport the full energy 6.5-GeV beam directly from the LINAC, and the top up injection will be possible for the PF-AR. We designed and produced new kicker systems for this project. Three kicker magnets are used for the injection of the 6.5-GeV beam. The kicker magnets were designed as a window frame type ferrite core magnet. The magnetic fields of these magnets have been measured by the search coil method. We paid attention to evaluating eddy current losses of the metal coated ceramic duct in the magnetic field measurement.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-WEPVA060  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)