TUPAB039 Installation Management for the European XFEL Main Accelerator 1409
 
  • M. Bousonville, S. Choroba, F. Eints
    DESY, Hamburg, Germany
 
  By end of 2016, the main accelerator of the European XFEL was completed. To build this complex machine in a minimum of time, certain management methods were introduced in mid 2015, which accelerated the installation process substantially. In the following 64 weeks additional 84 % of the main accelerator were set up. This was possible due to an improved planning, the reinforcement of two teams as well as a permanent controlling and optimizing of the installation process. In this paper, the installation process from July 2015 to end 2016 and the measures which speeded up the workflow are described.  