MOPP05 The Frascati Beam Test Facility New Line: From Design to Beam Commissioning. 35
 
  • C. Di Giulio, B. Buonomo, F. Cardelli, D. Di Giovenale, L.G. Foggetta
    INFN/LNF, Frascati, Italy
 
  The request of beam time for a long-time experiment and the contemporary request to provide beam time to the detector developers community, drive the INFN to invest in the commissioning of new beam line test facility. In this work we describe the necessary step followed from the design to the commissioning of the new beam line in the Frascati Beam Test Facility.  
poster icon Poster MOPP05 [3.481 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IBIC2021-MOPP05  
About • paper received ※ 03 September 2021       paper accepted ※ 15 September 2021       issue date ※ 17 October 2021  