Mertens, V.

Paper Title Page
WEPP065 Beam Commissioning of the SPS-to-LHC Transfer Line TI 2 2668
 
  • J. A. Uythoven, G. Arduini, R. W. Assmann, N. Gilbert, B. Goddard, V. Kain, A. Koschik, T. Kramer, M. Lamont, V. Mertens, S. Redaelli, J. Wenninger
    CERN, Geneva
 
  The transfer line for the LHC Ring 1 was successfully commissioned with beam in the autumn of 2007. After extraction from the SPS accelerator and about 2.7 km of new transfer line, the beam arrived at the temporarily installed beam dump, about 50 m before the start of the LHC tunnel, without the need of any beam threading. This paper gives an overview of the hardware commissioning period and the actual beam tests carried out. It summarises the results of the beam test optics measurements and the performance of the installed hardware.