The Commissioning of a 230 MeV Superconducting Cyclotron CYCIAE-230 |
15 |
|
- C. Wang, H.R. Cai, W.F. Fu, A.L. He, M.Z. Hu, B. Ji, L.Y. Ji, X.L. Jia, Y. Jia, T.Y. Jiang, J. Liu, J.Y. Liu, P. Liu, Z.W. Liu, X. Mu, S. Pei, G.F. Song, Q.Q. Song, F. Wang, J.Y. Wei, L.P. Wen, J.S. Xing, Z.G. Yin, D.Z. Zhang, S.P. Zhang, T.J. Zhang, X. Zheng, H. Zhou, P.F. Zhu, X.F. Zhu
CIAE, Beijing, People’s Republic of China
|
|
|
There are very strong demands for proton accelera-tors in medium energy range in recent years due to the fast growth of proton therapy and the space science in China. For the applications of proton therapy and pro-ton irradiation, the energy range of proton beam is usually from 200MeV to 250MeV, or even higher for astronavigation [1]. An R&D project for constructing a 230MeV superconducting cyclotron (CYCIAE-230) has been initiated at China Institute of Atomic Energy (CIAE) since Jan 2015. In July of 2016, after the fund-ing was approved by China National Nuclear Corpora-tion (CNNC), the construction project was fully launched. In Dec 2019, the superconducting main magnet and the RF system were transferred to the new-ly built commissioning site. Then, the RF commission-ing, ion source and central region test were performed even during the pandemic in early 2020. In September 2020, after finishing the commissioning tests of all subsystems, the beam was reached the extraction channel but with very low efficiency. Since then, with more efforts on beam diagnostics, the fine tuning of the beam phase and the adjusting of the superconduct-ing coil have been proven to be useful to get higher beam extraction efficiency ~55%. In this paper, the commissioning of the key components, including the main magnet, SC coils, internal ion source and central region, extraction system, etc, as well as the commis-sioning progress of the machine CYCIAE-230 will be presented.
|
|
|
Slides MOAO02 [10.305 MB]
|
|
DOI • |
reference for this paper
※ doi:10.18429/JACoW-CYCLOTRONS2022-MOAO02
|
|
About • |
Received ※ 24 January 2023 — Revised ※ 25 January 2023 — Accepted ※ 09 February 2023 — Issue date ※ 10 June 2023 |
Cite • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
TUBO03 |
Application Progress of CYCIAE-100 High Current Proton Cyclotron |
130 |
|
- L.C. Cao, X.L. Jia, Z.W. Liu, G.F. Song, T.J. Zhang
CIAE, Beijing, People’s Republic of China
|
|
|
A new RIB facility, Beijing radioactive ion-beam facility (BRIF) had been constructed at CIAE. A 100 MeV H− cyclotron (CYCIAE-100) is selected as the driving accelerator which can provide a 70 - 100 MeV, 10 pA - 520 µA proton beam for basic and applied research in the field of nuclear science and technology. The application of this facility has promoted the development of frontier scientific research in China, such as radioactive nuclear beam physics, nuclear data, neutron physics and space radiation effects. Recently, quasi-monoenergetic neutron source above 20 MeV and the white light neutron source with the best time resolution were completed, which had filled the gap in the measurement of neutron data in the range of energy of 100 MeV in China. In this paper, the main milestones in the use and development of CYCIAE-100 high current proton cyclotron are reviewed, the scientific applications based on platform are described, and the important topics in proton applications based on intermediate energy are discussed, including space radiation hardening, neutron standard radiation field and biological radiation damage mechanism.
|
|
|
Slides TUBO03 [7.851 MB]
|
|
DOI • |
reference for this paper
※ doi:10.18429/JACoW-CYCLOTRONS2022-TUBO03
|
|
About • |