Author: Adolphsen, C.
Paper Title Page
TUPO042 SLAC/FNAL TTF3 Coupler Assembly and Processing Experience 476
 
  • C. Adolphsen, A.A. Haase, C.D. Nantista, J. Tice, F. Wang
    SLAC, Menlo Park, California, USA
  • T.T. Arkan, M.S. Champion, S. Kazakov, A. Lunin, K.S. Premo
    Fermilab, Batavia, USA
 
  Funding: Work supported by the U.S. Department of Energy under contract number DE-AC02-76SF00515
The TTF3-style coupler is typically used to power 1.3 GHz TESLA-type superconducting cavities. For the US ILC program, parts purchased in industry for such couplers are received at SLAC where they are inspected, cleaned, assembled as pairs in a Class 10 cleanroom, pumped down, baked at 150 degC and rf processed. The pairs are then shipped to FNAL and installed in cavities that are then tested at input power levels up to 300 kW. This paper describes the coupler results to date including improvements to the procedures and efforts to mitigate problems that have been encountered. Also progress on building a cold coupler section without e-beam wielding is presented.
 
poster icon Poster TUPO042 [0.712 MB]  
 
THIOA01 Test Results of the International S1-Global Cryomodule 615
 
  • Y. Yamamoto, M. Akemoto, S. Fukuda, K. Hara, H. Hayano, N. Higashi, E. Kako, H. Katagiri, Y. Kojima, Y. Kondo, T. Matsumoto, H. Matsushita, S. Michizono, T. Miura, H. Nakai, H. Nakajima, K. Nakanishi, S. Noguchi, N. Ohuchi, T. Saeki, M. Satoh, T. Shidara, T. Shishido, T. Takenaka, A. Terashima, N. Toge, K. Tsuchiya, K. Watanabe, S. Yamaguchi, A. Yamamoto, K. Yokoya, M. Yoshida
    KEK, Ibaraki, Japan
  • C. Adolphsen, C.D. Nantista
    SLAC, Menlo Park, California, USA
  • T.T. Arkan, S. Barbanotti, M.A. Battistoni, H. Carter, M.S. Champion, A. Hocker, R.D. Kephart, J.S. Kerby, D.V. Mitchell, T.J. Peterson, Y.M. Pischalnikov, M.C. Ross, W. Schappert, B.E. Smith
    Fermilab, Batavia, USA
  • A. Bosotti, C. Pagani, R. Paparella, P. Pierini
    INFN/LASA, Segrate (MI), Italy
  • K. Jensch, D. Kostin, L. Lilje, A. Matheisen, W.-D. Möller, P. Schilling, M. Schmökel, N.J. Walker, H. Weise
    DESY, Hamburg, Germany
 
  S1-Global collaborative project by joint efforts of INFN, DESY, FNAL, SLAC and KEK, finished successfully at KEK- STF on February in 2011, is a crucial project for ILC. For this project, 8 SRF cavities, 2 from DESY, 2 from FNAL and 4 from KEK, were installed into one cryomodule with the thermal shields and the cooling pipes of liquid helium and nitrogen, cooled down to 2K totally three times, and cold-tested by using the three different frequency tuning systems (Blade tuner from INFN/FNAL, Saclay tuner from DESY and Slide-Jack tuner from KEK) and two types of input couplers (TTF III from DESY and STF#2 from KEK). During the cold test with high power, cavity performance, LFD (Lorentz Force Detuning) compensation by Piezo actuator, simultaneous 7 SRF cavities operation, dynamic heating loss measurement including static loss and DRFS (Distributed RF Scheme) operation with LLRF (Low Level RF) feedback system, were established successfully. In this talk, the results of the S1-Global cryomodule test are reported, discussed and summarized.  
slides icon Slides THIOA01 [11.254 MB]