Author: Vassioutchenko, A.V.
Paper Title Page
TUP012 Computer Simulations of Waveguide Window and Coupler Iris for Precision Matching 832
 
  • S.W. Lee
    ORNL RAD, Oak Ridge, Tennessee, USA
  • Y.W. Kang, K.R. Shin, A.V. Vassioutchenko
    ORNL, Oak Ridge, Tennessee, USA
 
  Funding: This work was supported by SNS through UT-Battelle, LLC, under contract DE-AC05-00OR22725 for the U.S. DOE.
A tapered ridge waveguide iris input coupler and a waveguide ceramic disk windows are used on each of six drift tube linac (DTL) cavities in the Spallation Neutron Source (SNS). The coupler design employs rapidly tapered double ridge waveguide to reduce the cross section down to a smaller low impedance transmission line section that can couple to the DTL tank easily. The impedance matching is done by adjusting the dimensions of the thin slit aperture between the ridges that is the coupling element responsible for the power delivery to the cavity. Since the coupling is sensitive to the dimensional changes of the aperture, it requires careful tuning for precise matching. Accurate RF simulation using latest 3-D EM code is desirable to help the tuning for maintenance and spare manufacturing. Simulations are done for the complete system with the ceramic window and the coupling iris on the cavity to see mutual interaction between the components as a whole.
 
 
THOAS3 Status of the Oak Ridge Spallation Neutron Source (SNS) RF Systems 2050
 
  • T.W. Hardek, M.T. Crofford, Y.W. Kang, M.F. Piller, A.V. Vassioutchenko
    ORNL, Oak Ridge, Tennessee, USA
  • S.W. Lee, M.E. Middendorf
    ORNL RAD, Oak Ridge, Tennessee, USA
 
  The SNS has been delivering production neutrons for five years with first beam delivered to the neutron target at the end of April 2006. On September 18, 2009 SNS officially reached 1 megawatt of beam on target marking the achievement of a decades-old dream of providing a U.S. megawatt class pulsed spallation source. The SNS is now routinely delivering 1 megawatt of beam power to the neutron target at over 85 percent of the scheduled beam time. The present effort is aimed at increasing availability eventually to 95 percent and gradually increasing the intensity to the 1.4 megawatt design level. While the RF systems have performed well since initial installation some improvements have been implemented. This paper provides a review of the SNS RF Systems, an overview of the performance of the various components and a detailed review of RF related issues addressed over the past several years.  
slides icon Slides THOAS3 [2.759 MB]