Paper | Title | Page |
---|---|---|
MOP018 | ISAC-II Superconducting Linac Upgrade - Design and Status | 97 |
|
||
The ISAC-II superconducting linac, operational since April 2006, adds 20 MV accelerating potential to the ISAC Radioactive Ion Beam (RIB) facility. An upgrade to the linac, in progress, calls for the addition of a further 20 MV of accelerating structure by the end of 2009. The new installation consists of twenty 141 MHz quarter wave cavities at a design beta of 11%. The cavities will be housed in three cryomodules with six cavities in the first two cryomodules and eight cavities in the last. A second Linde TC50 refrigerator has been installed and commissioned to provide cooling for the new installation. The design incorporates several new features as improvements to the existing cryomodules. They include a four point support frame for the cavity strongback, a modified LN2 circuit internal to the cryomodule and a new design for the mechanical motion of the rf coupling loop. A summary of the design and the current status of the cryomodule production and supporting infrastructure will be presented. |
||
TUP002 | ARIEL and the TRIUMF E-Linac Initiative, a 0.5 MW Electron Linac for Rare Isotope Beam Production | 383 |
|
||
TRIUMF, in collaboration with university partners, proposes to construct a megawatt-class electron linear accelerator (e-linac) as a driver for U(γ,f) of actinide targets for nuclear astrophysics studies, and 9Be(γ,p)8Li for beta-NMR materials science. The e-linac is part of a broader proposal for an expansion of the TRIUMF rare isotope beams capability through a new facility to be named ARIEL. The e-linac design and prospects for funding are elaborated. |
||
THP002 | The 1.3 GHz Superconducting RF Program at TRIUMF | 774 |
|
||
TRIUMF is proposing to build a 50 MeV electron linac as a driver to produce radioactive ion beams through photofission. The present design calls for the use of nine-cell 1.3 GHz Tesla type cavities. A 1.3 GHz Superconducting RF (SRF) program has been initiated with the goal to produce and test one nine cell cavity by the end of 2009. The program will utilize the existing clean room and SRF test facilities that support the ISAC-II heavy ion superconducting linac. A vertical cryostat has been modified with a new insert to allow single cell testing. Pumps for 2 K sub-atmospheric operation have been tested. A single cell fabrication program is being initiated with a local company. A RRR measurement program is on-going to test cavity welds. The goal of the 1.3 GHz upgrade is to not only produce cavities for the in house project but to broaden TRIUMF's technical base for future potential collaborations. The paper will report the progress and plans of the 1.3 GHz SRF program. |
||
|