Paper |
Title |
Page |
TUBB2 |
The Accelerator Facility of the Facility for Antiproton and Ion Research |
1343 |
|
- P.J. Spiller, F. Becker, A. Dolinskyy, L. Groening, O.K. Kester, K. Knie, H. Reich-Sprenger, W. Vinzenz, M. Winkler
GSI, Darmstadt, Germany
- D. Prasuhn
FZJ, Jülich, Germany
|
|
|
The accelerators of the Facility for Antiproton and Ion Research – FAIR are under construction. The sophisticated system of accelerators is designed to produce stable and secondary beams with a significant variety of intensities and beam energies. FAIR will explore the intensity frontier of heavy ion accelerators and the beams for the experiments will have highest beam quality for cutting edge physics to be conducted. The main driver accelerator of FAIR will be the SIS100 synchrotron. In order to produce the intense rare isotope beams (RIB) at FAIR, a unique superconducting fragment separator is under construction. A system of storage rings will collect and cool secondary particles from the FAIR. Intense work on test infrastructure for the huge number of superconducting magnets of the FAIR machines is ongoing at GSI and several partner labs. In addition, the GSI accelerator facility is being prepared to serve as injector for the FAIR accelerators. As the construction of the FAIR accelerators and the procurement has started, an overview of the designs, procurements plans and infrastructure preparation can be provided.
|
|
|
Slides TUBB2 [4.653 MB]
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-IPAC2015-TUBB2
|
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
WEPMA019 |
Status of the Super-FRS Magnet Devlopment for Fair |
2792 |
|
- H. Müller, E.S. Fischer, H. Leibrock, P. Schnizer, M. Winkler
GSI, Darmstadt, Germany
- J.-E. Munoz-Garcia, L. Quettier
CEA/IRFU, Gif-sur-Yvette, France
- L. Serio
CERN, Geneva, Switzerland
|
|
|
The Super FRS is a two-stage in flight separator to be built next to the site of GSI, Darmstadt, Germany as part of FAIR (Facility for Anti-proton and Ion Research). Its purpose is to create and separate rare isotope beams and to enable the mass measurement also for very short lived nuclei. Due to its three branches a wide variety of experiments can be carried out in frame of the NUSTAR collaboration. Due to the large acceptance needed, the magnets of the Super-FRS have to have a large aperture and therefore only a superconducting solution is feasible. A superferric design with superconducting coils was chosen in which the magnetic field is shaped by an iron yoke. We will present the actual design status of the dipole- and multipole magnets as well as the status of the development of the dedicated test facility at CERN.
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-IPAC2015-WEPMA019
|
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|