Author: Tavian, L.J.
Paper Title Page
TUPFI002 Electron Cloud and Scrubbing Studies for the LHC 1331
 
  • G. Iadarola
    Naples University Federico II, Science and Technology Pole, Napoli, Italy
  • G. Arduini, V. Baglin, H. Bartosik, C.O. Domínguez, J.F. Esteban Müller, G. Iadarola, G. Rumolo, E.N. Shaposhnikova, L.J. Tavian, F. Zimmermann
    CERN, Geneva, Switzerland
  • C.O. Domínguez
    EPFL, Lausanne, Switzerland
  • G.H.I. Maury Cuna
    CINVESTAV, Mexico City, Mexico
 
  Electron cloud build-up resulting from beam-induced multipacting is one of the major limitations for the operation of the LHC with beams with close bunch spacing. Electron clouds induce unwanted pressure rise, heat loads on the beam screens of the superconducting magnets and beam instabilities. Operation with bunch spacing of 50 ns in 2011 and 2012 has required decreasing the Secondary Electron Yield of the beam screens below the multipacting threshold for beams with this bunch spacing. This was achieved by continuous electron bombardment induced by operating the machine with high intensity beams with 50 and 25 ns spacing during dedicated periods at injection energy (450 GeV) and at top energy (3.5 and 4 TeV). The evolution of the Secondary Electron Yield during these periods, at different sections of the machine, can be estimated by pressure, heat load and by bunch-by-bunch RF stable phase measurements. The experimental information on the scrubbing process will be discussed and a possible “scrubbing strategy” to allow the operation with 50ns and 25ns beams after the Long Shutdown in 2013-2014 will be presented.  
 
TUPME032 Update on Beam Induced RF Heating in the LHC 1646
 
  • B. Salvant, O. Aberle, G. Arduini, R.W. Aßmann, V. Baglin, M.J. Barnes, W. Bartmann, P. Baudrenghien, O.E. Berrig, A. Bertarelli, C. Bracco, E. Bravin, G. Bregliozzi, R. Bruce, F. Carra, F. Caspers, G. Cattenoz, S.D. Claudet, H.A. Day, M. Deile, J.F. Esteban Müller, P. Fassnacht, M. Garlaschè, L. Gentini, B. Goddard, A. Grudiev, B. Henrist, S. Jakobsen, O.R. Jones, O. Kononenko, G. Lanza, L. Lari, T. Mastoridis, V. Mertens, N. Mounet, E. Métral, A.A. Nosych, J.L. Nougaret, S. Persichelli, A.M. Piguiet, S. Redaelli, F. Roncarolo, G. Rumolo, B. Salvachua, M. Sapinski, R. Schmidt, E.N. Shaposhnikova, L.J. Tavian, M.A. Timmins, J.A. Uythoven, A. Vidal, J. Wenninger, D. Wollmann, M. Zerlauth
    CERN, Geneva, Switzerland
  • H.A. Day
    UMAN, Manchester, United Kingdom
  • L. Lari
    IFIC, Valencia, Spain
 
  Since June 2011, the rapid increase of the luminosity performance of the LHC has come at the expense of increased temperature and pressure readings on specific near-beam LHC equipment. In some cases, this beam induced heating has caused delays whilie equipment cools down, beam dumps and even degradation of these devices. This contribution gathers the observations of beam induced heating attributable to beam coupling impedance, their current level of understanding and possible actions that are planned to be implemented during the long shutdown in 2013-2014.  
 
THPME034 The LHC Cryogenic Operation Availability Results from the First Physics Run of Three Years 3585
 
  • D. Delikaris, K. Brodzinski, S.D. Claudet, G. Ferlin, L.J. Tavian, U. Wagner
    CERN, Geneva, Switzerland
 
  The LHC (Large Hadron Collider) accelerator consists in eight cryogenically independent sectors, each 3.3 km long with a cold mass of 4500 ton cooled at 1.9 K. Each helium cryogenic plant combines an 18 kW at 4.5 K refrigerator and a 2.4 kW at 1.8 K refrigeration unit. Since early operation for physics in November 2009, the availability has been above 90% for more than 260 days per year, ending at 94.8% in 2012 and corresponding to an equivalent availability of more than 99% per independent sector. The operation and support methodology as well as the achieved performance results are presented. Emphasis is given on implementing operational return for short, medium and long term consolidations. Perspective for restart after the first long shutdown of the LHC works will be described.