THO1C05 | Status and Beam Commissioning Plan of PEFP 100 MeV Proton Linac | 570 |
|
||
Funding: This work was supported by Ministry of Education, Science and Technology of the Korean government. The proton engineering frontier project (PEFP) is developing a 100 MeV proton linac which consists of a 50 keV injector, a 3 MeV RFQ (radio frequency quadrupole), and a 100 MeV DTL (drift tube linac). The installation of the linac was finished on March this year. The other elements including the high power RF components will be installed after completing the other part of the accelerator building. The beam commissioning is scheduled at the end of this year. This work summarized the status of the PEFP linac development and the beam commissioning plan. |
||
![]() |