  Funding: Work supported by the U.S. DoE Office of Science under Cooperative Agreement DE-SC0000661 and the NSF under Cooperative Agreement PHY-1102511, the State of Michigan and Michigan State University.
The present RFQ of ReA3 reaccelerator at Michigan State University (MSU) has been commissioned in 2010. This 4-rod RFQ was designed to accelerate the prebunched 80.5 MHz beams with the lowest Q/A = 1/5. However, the lack of proper cooling limited the RFQ performance to the pulsed operation with the lowest Q/A = 1/4. The design voltage for Q/A = 1/5 has never been reached even in a pulsed mode due to the sparking. In 2016 we initiated the upgrade of ReA3 RFQ to support high duty cycle (up to CW) operation with Q/A = 1/5 beams. The upgrade included the new rods with trapezoidal modulation, and new stems with improved cooling. The redesigned 80.5 MHz RFQ will consume only 65% rf power of the present RFQ for Q/A = 1/5 beam. It will provide the transmission up to 78% for 16.1 MHz beams and 89% for 80.5 MHz beams. High reliability and efficiency of the RFQ are very important for the going-on reaccelerator upgrade to ReA6 and for future operation as a part of FRIB. The electrodes have been manufactured and are being installed. The RF and beam tests are scheduled to summer 2019.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2019-WEPLH03  
About • paper received ※ 27 August 2019       paper accepted ※ 01 September 2019       issue date ※ 08 October 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPLH07 Commissioning of the FRIB/NSCL New ReA3 4-Rod Radio Frequency Quadrupole Accelerator 817
 
  • S. Nash, J.F. Brandon, D.B. Crisp, T. Summers, A.C.C. Villari, Q. Zhao
    NSCL, East Lansing, Michigan, USA
  • P.N. Ostroumov, A.S. Plastun
    FRIB, East Lansing, Michigan, USA
 
  Funding: This work was supported by the National Science Foundation under Grant PHY-15-65546
The reaccelerator facility ReA3 at the National Superconducting Cyclotron Laboratory is a state-of-the-art accelerator for ions of rare and stable isotopes. The first stage of acceleration is provided by a 4-rod radio-frequency quadrupole (RFQ) at 80.5 MHz, which accelerates ions from 12 keV/u to 530 keV/u. The internal copper acceleration structure of the RFQ was re-designed. The goal was to improve transmission while allowing to operate the RFQ in CW and accelerating ions with A/Q from 2 to 5. In this paper, we summarize the steps involved in the disassembly of the existing structure, preparation work on the retrofitted vacuum vessel, installation of the new components, acceptance testing, and commissioning of the completed RFQ.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2019-WEPLH07  
About • paper received ※ 29 August 2019       paper accepted ※ 19 November 2019       issue date ※ 08 October 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)