Paper | Title | Page |
---|---|---|
MOPLO12 | The RF BPM Pickup Electrodes Development for the APS-MBA Upgrade | 256 |
|
||
Beam stability is critical for the Advanced Photon Source (APS) multi-bend achromat (MBA) lattice up-grade and will employ 560 radio frequency (RF) beam position monitors (BPMs). The RF BPMs will provide the primary measurement of the electron beam. Design goals for the BPM assembly include high sensitivity, low wakefield impedance, and ultra-mechanically stability. The design, electromagnetic simulation, manufacturing tolerance and prototype testing will be presented in this paper.
*Work supported by the U.S. Department of Energy, Office of Science, under Contract No. DE-AC02-06CH11357. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-NAPAC2019-MOPLO12 | |
About • | paper received ※ 27 August 2019 paper accepted ※ 31 August 2019 issue date ※ 08 October 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |