Paper |
Title |
Page |
WEPAF075 |
Availability Allocation to Particle Accelerators Subsystems by Complexity Criteria |
2009 |
|
- O. Rey Orozko, A. Apollonio, M. Jonker, J.A. Uythoven
CERN, Geneva, Switzerland
|
|
|
In the early design stages of an accelerator, an effective allocation method is needed to translate an overall accelerator availability goal into availability requirements for its subsystems. During the allocation process, many factors are considered to obtain so-called ‘complexity weights', which are at the basis of the system availability allocation. Some of these factors can be measured quantitatively while other have to be assessed qualitatively. Based on our analysis of factors affecting availability, we list six criteria for complexity resulting in an availability allocation of accelerator subsystems. System experts determine the scales of factors and relationships between subsystems. In this paper, we consider four availability apportionment techniques to allocate complexity weights to subsystems. Finally, we apply this method to the Compact Linear Collider (CLIC) and we propose another application of the complexity weights to the Large Hadron Collider (LHC).
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-IPAC2018-WEPAF075
|
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
WEPAF076 |
Availability Studies Comparing Drive Beam and Klystron Options for the Compact Linear Collider |
2013 |
|
- O. Rey Orozko, S. Döbert, M. Jonker
CERN, Geneva, Switzerland
|
|
|
The initial proposal for the Compact Linear Collider (CLIC) is based on a two beam-scheme to accelerate the main colliding beams. For low collision energies, the main beam could also be accelerated by powering the accelerating structures with klystrons instead of the two-beam scheme. This paper studies the feasibility of this new alternative in terms of machine availability. An implemented bottom-up availability model considers the components failure modes to estimate the overall availability of the system. The model is defined within a Common Input Format scheme and the AvailSim3 software package is used for availability simulations. This paper gives an overview of the systems affecting the beam powering availability and makes recommendations for availability improvements.
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-IPAC2018-WEPAF076
|
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
WEPAF077 |
Performance Evaluation of Linac4 During the Reliability Run |
2016 |
|
- O. Rey Orozko, A. Apollonio, S.S. Erhard, G. Guidoboni, B. Mikulec, J.A. Uythoven
CERN, Geneva, Switzerland
|
|
|
Linac4 will replace Linac2 as the first element in the CERN proton injector chain from 2020 onwards, following the second LHC long shutdown (LS2). With more than three times higher energy and number of compo-nents than Linac2, beam availability is one of the main challenges of Linac4. Intended as a smooth transition from commissioning to operation, a Linac4 Reliability Run was started in July 2017 and is foreseen to last until mid-May 2018. The goal is to achieve the target availability of 95 %. This implies consolidated routine operation and identification of recurring problems. This paper introduces the schedule and operational aspects of the Linac4 Reliability Run, including the developed tools and methods for availability tracking. The paper also summarizes the lessons learned during the first period of the Linac4 Reliability Run with respect to fault tracking and provides an in-depth analysis of the failure modes and observed availability.
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-IPAC2018-WEPAF077
|
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
FRXGBD1 |
Reliability and Availability of Particle Accelerators: Concepts, Lessons, Strategy |
5014 |
|
- A. Apollonio, L. Ponce, O. Rey Orozko, R. Schmidt, A.P. Siemko, B. Todd, J.A. Uythoven, A.P. Verweij, D. Wollmann, M. Zerlauth
CERN, Geneva, Switzerland
|
|
|
This paper will present the results and latest status of an extensive effort to analyse and improve the reliability and availability of the LHC. After the introduction of basic concepts and definitions, the paper reviews the performance of the LHC in 2015-2017. A direct comparison of the luminosity production years 2016 and 2017 is presented, with a focus on the main differences in the observed failure modes. Based on the lessons learnt in this time window, expectations for the performance during future LHC runs are discussed. In particular, the thought process for the evaluation of the possible full energy exploitation of the LHC is described, considering relevant factors such as the expected availability loss and the risk associated to magnet training.
|
|
|
Slides FRXGBD1 [7.090 MB]
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-IPAC2018-FRXGBD1
|
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,