MOOFAV10 Completion of FRIB Superconducting Linac and Phased Beam Commissioning 197
 
  • T. Xu, Y. Al-Mahmoud, H. Ao, J. Asciutto, B. Bird, J. Bonofiglio, B. Bullock, N.K. Bultman, F. Casagrande, W. Chang, Y. Choi, C. Compton, J.C. Curtin, K.D. Davidson, K. Elliott, A. Facco, V. Ganni, A. Ganshyn, J. Gao, P.E. Gibson, Y. Hao, W. Hartung, N.M. Hasan, L. Hodges, K. Holland, J.D. Hulbert, M. Ikegami, T. Kanemura, S.H. Kim, P. Knudsen, Z. Li, S.M. Lidia, G. Machicoane, C. Magsig, P.E. Manwiller, F. Marti, T. Maruta, K.E. McGee, E.S. Metzgar, S.J. Miller, D.G. Morris, H. Nguyen, P.N. Ostroumov, A.S. Plastun, J.T. Popielarski, L. Popielarski, X. Rao, M.A. Reaume, H.T. Ren, K. Saito, M. Shuptar, A. Stolz, A. Taylor, B.P. Tousignant, A.D.F. Victory, D.R. Victory, J. Wei, E.M. Wellman, J.D. Wenstrom, Y. Yamazaki, C. Zhang, Q. Zhao, S. Zhao
    FRIB, East Lansing, Michigan, USA
  • K. Hosoyama
    KEK, Ibaraki, Japan
  • M.P. Kelly
    ANL, Lemont, Illinois, USA
  • R.E. Laxdal
    TRIUMF, Vancouver, Canada
  • M. Wiseman
    JLab, Newport News, Virginia, USA
 
  Funding: This work is supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661.
The Facility for Rare Isotope Beams (FRIB) is an ac-celerator-based facility funded by the US Department of Energy for nuclear physics research. FRIB is nearing the end of technical construction, with first user beams ex-pected in Summer 2022. Key features are the delivery of a variety of rare isotopes with a beam energy of ’ 200 MeV/u and a beam power of up to 400 kW. The facility is upgradable to 400 MeV/u and multi-user capability. The FRIB driver linac consists of 324 superconducting resonators and 69 superconducting solenoids in 46 cry-omodules. FRIB is the first linac to deploy a large number of HWRs (220) and the first heavy ion linac to operate at 2 K. We report on the completion of production and in-stallation of the FRIB cryomodules and phased beam commissioning results.
 
DOI • reference for this paper ※ doi:10.18429/JACoW-SRF2021-MOOFAV10  
About • Received ※ 12 August 2021 — Revised ※ 16 August 2021 — Accepted ※ 21 August 2021 — Issue date ※ 04 May 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPTEV010 RF System Experience for FRIB Half Wave Resonators 226
 
  • S. Zhao, W. Chang, E. Daykin, E. Gutierrez, S.H. Kim, S.R. Kunjir, T.L. Larter, D.G. Morris, J.T. Popielarski
    FRIB, East Lansing, Michigan, USA
 
  Funding: Work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661.
The installation and commissioning of the FRIB superconducting linac adopts a phased strategy. In SRF’19 we reported the progress on the commissioning of the linear segment 1 (LS1) which contains mainly the quarter wave resonators (QWRs). In this paper, we will report the recent progress on the commissioning of the remainder of the linac, including linear segment 2 (LS2), folding segment 2 (FS2) and linear segment 3 (LS3), focusing on the RF system experience for the half wave resonators (HWRs). Compared to the QWRs, the HWRs have a different type of tuner, run at higher power levels and have additional components (for example, high voltage bias tee for multipacting suppression and spark detector). Topics such as nonlinear tuner control for the pneumatic tuners; auto turn on/off implementation; and early issues and failures will be discussed in more detail.
 
poster icon Poster MOPTEV010 [1.604 MB]  
DOI • reference for this paper ※ doi:10.18429/JACoW-SRF2021-MOPTEV010  
About • Received ※ 22 June 2021 — Revised ※ 22 August 2021 — Accepted ※ 16 November 2021 — Issue date ※ 22 November 2021
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)