THPTEV014 Managing Procurements in the Time of Covid-19: SNS-PPU as a Case Study 863
 
  • K.M. Wilson, G. Cheng, E. Daly, N.A. Huque, T. Huratiak, M. Laney, K. Macha, D.J. Maddox, M. Marchlik, P.D. Owen, T. Peshehonoff, M. Torres, M. Wiseman
    JLab, Newport News, Virginia, USA
 
  Funding: Supported by the Dept of Energy, Office of Nuclear Physics under contract DE-AC05-06OR23177 (JSA); and by UT-B which manages Oak Ridge National Laboratory under contract DE-AC05-00OR22725.
In early 2020, COVID-19 swept across the world. The accelerator industry, like many others, was impacted by disease, delays, shortages, and new working conditions. All Thomas Jefferson National Accelerator Facility (JLab) employees were sent home in mid-March 2020, with many still working remotely now. At the time, JLab was working on the Proton Power Upgrade (PPU) to the Spallation Neutron Source (SNS) at Oak Ridge National Laboratory (ORNL). Procurements had been placed and were being managed, parts were being received and inspected. This paper details the JLab procurement plan for the SNS PPU project, and the mitigations that were developed to continue to support this project smoothly under the limitations imposed by COVID-19.
 
poster icon Poster THPTEV014 [1.081 MB]  
DOI • reference for this paper ※ doi:10.18429/JACoW-SRF2021-THPTEV014  
About • Received ※ 15 June 2021 — Revised ※ 30 November 2021 — Accepted ※ 21 January 2022 — Issue date ※ 01 May 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPTEV017 Status of the LCLS-II-HE Project at Jefferson Lab 876
 
  • K.M. Wilson, J. Hogan, M. Laney, A.D. Palczewski, C.E. Reece
    JLab, Newport News, Virginia, USA
 
  Funding: This work was supported by the U.S. Department of Energy Office of Science, Office of Nuclear Physics under contract DE-AC05-06OR23177 (JSA); and for BES under contract DE’AC02’76SF00515 (SLAC).
The Linac Coherent Light Source II High Energy (LCLS-II-HE) upgrade at the SLAC National Accelerator Laboratory is being constructed in partnership with the Thomas Jefferson National Accelerator Facility (JLab) and the Fermi National Accelerator Laboratory (FNAL). The cryomodule production scope consists of the design, procurement, construction, and acceptance testing of 24 eight-cavity, 1.3 GHz cryomodules, as well as R&D activities necessary to develop the required technology. To achieve this, JLab and FNAL are also contributing to SLAC’s effort to develop the cavity recipe and production processes necessary to meet the LCLS-II-HE goal of 20.8 MV/m and average Q0 of 2.7·1010. This paper details the JLab scope, focusing on the project initiation phase, in particular technology development and prototyping, project development and planning, and implementation of lessons learned from LCLS-II.
 
poster icon Poster THPTEV017 [1.536 MB]  
DOI • reference for this paper ※ doi:10.18429/JACoW-SRF2021-THPTEV017  
About • Received ※ 21 June 2021 — Revised ※ 12 August 2021 — Accepted ※ 02 March 2022 — Issue date ※ 01 May 2022
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)