Paper | Title | Page |
---|---|---|
THP063 | Inivestigation of the Possibility of High Efficiency L-Band SRF Cavity for Medium-Beta Heavy Ion Multi-Charge-State Beams | 1035 |
|
||
Funding: This work was supported in part by the U.S. National Science Foundation, under Grant PHY-1102511 and by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661. The possibility of L-band SRF elliptical cavity in order to accelerate heavy ion multi-charge-state beams is being investigated for accelerating energy higher than 200 MeV/u. A first simple analytic study was performed and the result showed that the longitudinal acceptance of 1288 MHz is sufficient for heavy-ion multi-charge-state (5 charge states) medium-beta linac. Encouraged this result, detail beam dynamic simulation took place. The cryogenic heat load is also calculated for this linac with taken into consideration cavity doping technology. In this paper, a summary of the beam dynamics and cryogen-ic heat load calculations for 1288 MHz linac for heavy-ion multi-charge-state (5 charge states) medium-beta beams. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-THP063 | |
About • | paper received ※ 24 June 2019 paper accepted ※ 14 August 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
THP106 | An SRF Test Stand in High Intensity and High Energy Proton Beams | 1187 |
|
||
In the framework of HL-LHC, a new infrastructure was installed in 2018, to test SRF structures in the proton beams of the SPS. Scope of the test stand is to study the operational performance of crab cavities for HL-LHC – more generally, SRF cavities – through a wide range of proton beam parameters up to high energy and current, under safe conditions for equipment and personnel. The SPS beam instrumentation is used to monitor orbit centering, RF phase scans, bunch rotation. To minimize impact on beam time, infrastructure and services allow for full remote control. Critical aperture restrictions is overcome by placing the test structure and its ancillaries on a motorized table for lateral translation in- and out of beam. Two articulated Y-shaped vacuum chambers connect the test cryomodule on a beam by-pass. A new cryogenic refrigerator is installed in a split scheme, with an underground cold box fed from a surface compressor. The two Inductive Output Tubes (IOT) power amplifiers deliver up to 60 kW cw via coaxial transmission lines to the two cavities and charges and circulators, the latter installed on the translation table. Interlocks and safety equipment complete the test stand. | ||
![]() |
Poster THP106 [3.982 MB] | |
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-THP106 | |
About • | paper received ※ 23 June 2019 paper accepted ※ 01 July 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |