Author: Jones, S.
Paper Title Page
MOFAA3 The FRIB SC-Linac - Installation and Phased Commissioning 12
 
  • J. Wei, H. Ao, S. Beher, B. Bird, N.K. Bultman, F. Casagrande, D. Chabot, W. Chang, S. Cogan, C. Compton, J. Curtin, K.D. Davidson, E. Daykin, K. Elliott, A. Facco, A. Fila, V. Ganni, A. Ganshyn, P.E. Gibson, T. Glasmacher, I. Grender, W. Hartung, L. Hodges, K. Holland, H.-C. Hseuh, A. Hussain, M. Ikegami, S. Jones, T. Kanemura, S.H. Kim, P. Knudsen, M.G. Konrad, J. LeTourneau, Z. Li, S.M. Lidia, G. Machicoane, P. Manwiller, F. Marti, T. Maruta, E.S. Metzgar, S.J. Miller, D.G. Morris, C. Nguyen, K. Openlander, P.N. Ostroumov, A.S. Plastun, J.T. Popielarski, L. Popielarski, J. Priller, M.A. Reaume, H.T. Ren, T. Russo, K. Saito, M. Shuptar, J.W. Stetson, D.R. Victory, R. Walker, X. Wang, J.D. Wenstrom, M. Wright, M. Xu, T. Xu, Y. Yamazaki, Q. Zhao, S. Zhao
    FRIB, East Lansing, Michigan, USA
  • K. Dixon, M. Wiseman
    JLab, Newport News, Virginia, USA
  • A. Facco
    INFN/LNL, Legnaro (PD), Italy
  • K. Hosoyama
    KEK, Ibaraki, Japan
  • M.P. Kelly
    ANL, Lemont, Illinois, USA
  • R.E. Laxdal
    TRIUMF, Vancouver, Canada
 
  Funding: Work supported by the U.S. Department of Energy Office of Science under Cooperative Agreement DE-SC0000661.
The Facility for Rare Isotope Beams (FRIB) superconducting (SC) driver linac is designed to accelerate all stable ions including uranium to energies above 200 MeV/u primarily with 46 cryomodules containing 324 quarter-wave resonators (QWR) and half-wave (HWR) resonators. With the newly commissioned helium refrigeration system supplying liquid helium to the QWR and solenoids, heavy ion beams including Ne, Ar, Kr and Xe were accelerated to the charge stripper location above 20 MeV/u with the first linac segment consisting of 15 cryomodules containing 104 QWRs of β=0.041 and 0.085 and 39 solenoids. Installation of cryomodules with β=0.29 and 0.53 HWRs is proceeding in parallel. Development of β=0.65 elliptical resonators is on-going supporting the FRIB energy upgrade to 400 MeV/u. This paper summarizes the SC-linac installation and phased commissioning status that is on schedule and on budget to the FRIB project.
 
slides icon Slides MOFAA3 [46.571 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-MOFAA3  
About • paper received ※ 23 June 2019       paper accepted ※ 30 June 2019       issue date ※ 14 August 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)