Paper | Title | Page |
---|---|---|
TUP034 | Microphonics Testing of LCLS II Cryomodules at Jefferson Lab | 493 |
|
||
Funding: Authored by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE-AC05-06OR23177 Jefferson Lab is partnering with Fermilab to build the 36 cryomodules for the LCLS II accelerator that will be installed at SLAC. The cavities have design loaded-Q of 4×107, which means that it has a control bandwidth of 16 Hz. The JLab prototype cryomodule was instrumented with a series of seven accelerometers, and impulse hammer response measurements were made while the cryomodule was being built and after it was installed in the JLab cryomodule test facility. This was done so that we could understand the shapes of the modes of the structure. These results were compared to impulse hammer testing from the outside of the cryomodule and to individual cavity frequency shifts when the cryomodule was cold. The prototype cryomodule had excessive microphonics of 150 Hz peak due to a thermos-acoustic oscillation. Design modifications were implemented and subsequently the cryomodules had microphonics on the order of 10 to 20 Hz. Results of the modal analysis as well as the background microphonics observed when operated under various cryogenic conditions and with different modifications will be presented. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-TUP034 | |
About • | paper received ※ 21 June 2019 paper accepted ※ 01 July 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
FRCAA3 | Industrial Cavity Production: Lessons Learned to Push the Boundaries of Nitrogen-Doping | 1199 |
|
||
Funding: Work supported by US DOE Contract DE-AC02-76SF00515. Nitrogen doping has been proven now in several labs to enhance Q0 values of 1.3 GHz cavities in the gradient domain favored by CW operation. The choice of doping for the LCLS-II project has given the community a wealth of statistics and experience on the challenge of transferring the doping technology to industry. Overall, industry-produced nitrogen-doped cavities have shown excellent performance, however some technical issues have arisen. This talk focuses on lessons learned from the production of over 300 nitrogen-doped cavities for LCLS-II and how issues were mitigated to further improve performance. Finally, I will discuss pushing the boundaries of nitrogen-doping further by exploring different doping regimes in order to maintain excellent Q0 performance, while reaching higher quench fields. |
||
![]() |
Slides FRCAA3 [16.880 MB] | |
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-SRF2019-FRCAA3 | |
About • | paper received ※ 02 July 2019 paper accepted ※ 03 July 2019 issue date ※ 14 August 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |