TUP78Status of the Cryomodules and Cavities Development for the SPIRAL2 Superconducting Linac339
 
  • G. Olry, S. Blivet, N. Hammoudi, D. Longuevergne, F. Lutton, G. Martinet, G. Michel, H. Saugnac, P. Szott
    IPN Orsay
  • P-E. Bernaudin, P. Bosland, G. Devanz, C. Madec, A. Perolat
    CEA-Saclay
 
 The French laboratories CEA/Saclay and IPN Orsay, involved in the SPIRAL2 project, are now preparing the final tests of the two qualifying cryomodules (called respectively A for the beta 0.07 cavities and B for the beta 0.12 cavities) in order to start the series production in 2008. Each cryomodule A and B will be tested at 4.2 K and nominal power (10 kW, CW). This paper presents an update of the cryomodules and cavities developments (first results at room temperature, first assembly...) which have been presented in [1].