TUPAS038 The Concept Design of a New Transfer Line from Booster to Recycler for the Fermilab Proton Plan Phase 2 Campaign 1727
 
  • D. E. Johnson, M. Xiao
    Fermilab, Batavia, Illinois
 
  Funding: Work supported by URA under contract No. DEAC02-76CH03000 with the U. S.Dept. of Energy.

Upon the termination of the Fermilab Collider program, the current Recycler anti-proton storage ring will be converted to a proton pre-injector for the Main Injector synchrotron. This is scheduled to increase the beam power for the 120 GeV Neutrino program to upwards of 700KW. A transport line that can provide direct injection from the Booster to the Recycler while preserving direct injection from the Booster into the Main Injector and the 8 GeV Booster Neutrino program will be discussed,and its concept design will be presented.

 
TUPAS039 The Concept Design of a Transfer Line from the Recycler to the Main Injector for the Fermilab Nova Project 1730
 
  • M. Xiao, D. E. Johnson
    Fermilab, Batavia, Illinois
 
  Funding: Work supported by URA under contract No. DEAC02-76CH03000 with the U. S.Dept. of Energy.

Upon the termination of the Fermilab Collider program, the current Recycler anti-proton storage ring will be converted to a proton pre-injector for the Main Injector synchrotron. This is scheduled to increase the beam power for the 120 GeV Neutrino program to upwards of 700KW. Due to momentum aperture restriction, a new transport line that extracts the beam from the Recycler at a dispersion free region to the main injector will be discussed, and its concept design will be presented.