TUPAN055 Present Status of J-PARC Ring RF Ring RF Systems 1511
 
  • M. Yoshii, S. Anami, E. Ezura, K. Hara, Y. Hashimoto, C. Ohmori, A. Takagi, M. Toda
    KEK, Ibaraki
  • K. Haga, K. Hasegawa, M. Nomura, A. Schnase, F. Tamura, M. Yamamoto
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken
 
  The RCS high frequency accelerating systems are prepared for beam commissioning in September 2007. Installations of cavities, power supplies and amplifiers have been carried out. The systems have been checked for operation and interoperability. For the MR high frequency accelerating system, the examination of the whole system and its final adjustment are done aiming at installation in October 2007. Here, we report on various issues which had been found and solved during the examination and installation period.