A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z    

Allison, T.L.

Paper Title Page
WPAE065 Jefferson Lab's Trim Card II 3670
 
  • T.L. Allison, H. Higgins, E. Martin, W. Merz, S. Philip
    Jefferson Lab, Newport News, Virginia
 
  Funding: This work was supported by DOE contract DE-AC05-84ER40150 Modification No. M175, under which the Southeastern Universities Research Association (SURA) operates the Thomas Jefferson National Accelerator Facility.

Jefferson Lab’s Continuous Electron Beam Accelerator Facility (CEBAF) uses Trim Card I power supplies to drive approximately 1900 correction magnets. These trim cards have had a long and illustrious service record. However, some of the employed technology is now obsolete, making it difficult to maintain the system and retain adequate spares. The Trim Card II is being developed to act as a transparent replacement for its aging predecessor. A modular approach has been taken in its development to facilitate the substitution of sections for future improvements and maintenance. The resulting design has been divided into a motherboard and 7 daughter cards which has also allowed for parallel development. The Trim Card II utilizes modern technologies such as a Field Programmable Gate Array (FPGA) and a microprocessor to embed trim card controls and diagnostics. These reprogrammable devices also provide the versatility to incorporate future requirements.

 
FPAT061 CEBAF Distributed Data Acquisition System 3541
 
  • T.L. Allison, T. Powers
    Jefferson Lab, Newport News, Virginia
 
  Funding: This work was supported by DOE contract DE-AC05-84ER40150 Modification No. M175, under which the Southeastern Universities Research Association (SURA) operates the Thomas Jefferson National Accelerator Facility.

There are thousands of signals distributed throughout Jefferson Lab’s Continuous Electron Beam Accelerator Facility (CEBAF) that are useful for troubleshooting and identifying instabilities. Many of these signals are only available locally or monitored by systems with small bandwidths that cannot identify fast transients. The Distributed Data Acquisition (Dist DAQ) system will sample and record these signals simultaneously at rates up to 40 Msps. Its primary function will be to provide waveform records from signals throughout CEBAF to the Experimental Physics and Industrial Control System (EPICS). The waveforms will be collected after the occurrence of an event trigger. These triggers will be derived from signals such as periodic timers or accelerator faults. The waveform data can then be processed to quickly identify beam transport issues, thus reducing down time and increasing CEBAF performance. The Dist DAQ system will be comprised of multiple standalone chassis distributed throughout CEBAF. They will be interconnected via a fiber optic network to facilitate the global triggering of events. All of the chassis will also be connected directly to the CEBAF Ethernet and run EPICS locally. This allows for more flexibility than the typical configuration of a single board computer and other custom printed circuit boards (PCB) installed in a card cage.

allison@jlab.org