Author: Neri, L.
Paper Title Page
MOPLR057 Commissioning of the High Intensity Proton Source Developed at INFN-LNS for the European Spallation Source 261
 
  • L. Neri, L. Allegra, A. Amato, G. Calabrese, A.C. Caruso, G. Castro, L. Celona, F. Chines, G. Gallo, S. Gammino, O. Leonardi, A. Longhitano, G. Manno, S. Marletta, D. Mascali, A. Massara, A. Maugeri, S. Passarello, G. Pastore, A. Seminara, A. Spartà, G. Torrisi, S. Vinciguerra
    INFN/LNS, Catania, Italy
  • M.J. Ferreira, O. Midttun
    ESS, Lund, Sweden
  • O. Midttun
    University of Bergen, Bergen, Norway
 
  At the Istituto Nazionale di Fisica Nucleare-Laboratori Nazionali del Sud (INFN-LNS) the commissioning of the high intensity Proton Source for the European Spallation Source (PS-ESS) started some weeks ago. Beam stability at high current intensity is one of the most important parameter for the first steps of the ongoing commissioning. Commissioning plan and preliminary characterization are also presented, with the aim to satisfy the requirement above.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-LINAC2016-MOPLR057  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPLR062 European Spallation Source (ESS) Normal Conducting Front End Status Report 274
 
  • W. Wittmer, P.O. Gustavsson, F. Hellström, G. Hulla
    ESS, Lund, Sweden
  • I. Bustinduy, P.J. González, G. Harper, S. Varnasseri, C. de la Cruz
    ESS Bilbao, Zamudio, Spain
  • L. Celona, S. Gammino, L. Neri
    INFN/LNS, Catania, Italy
  • A.C. Chauveau, D. Chirpaz-Cerbat
    CEA/IRFU, Gif-sur-Yvette, France
  • F. Grespan, A. Pisent
    INFN/LNL, Legnaro (PD), Italy
  • P. Mereu
    INFN-Torino, Torino, Italy
  • O. Midttun
    University of Bergen, Bergen, Norway
  • O. Piquet, B. Pottin
    CEA/DSM/IRFU, France
 
  The European Spallation Source (ESS) will deliver first protons on target by mid 2019. Civil construction of the accelerator tunnel has made good progress and will allow starting installation of the normal conducting frond end (NCFE) by end of 2017. To achieve these milestones the design of all major beam line components have been completed and the construction of the subsystems begun. We report on the advancement of the subsystems and the commissioning progress of the microwave discharge Proton Source (PS-ESS).  
poster icon Poster MOPLR062 [1.396 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-LINAC2016-MOPLR062  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)