Author: Roncolato, C. R.
Paper Title Page
MOPP087 Construction of the Modules of the IFMIF-EVEDA RFQ 257
 
  • A. Pepato, E. Fagotti, F. Grespan, A. Palmieri, A. Pisent, C. R. Roncolato
    INFN/LNL, Legnaro (PD), Italy
  • R. Dima, L. Ferrari, E. Udup
    INFN- Sez. di Padova, Padova, Italy
  • A. Margotti
    INFN-Bologna, Bologna, Italy
  • P. Mereu
    INFN-Torino, Torino, Italy
 
  The IFMIF project aims to produce an intense neutron flux to test and qualify materials suitable for the construction of fusion power plants. We are working on the engineering validation phase of the project, which consists on the construction of a linear accelerator prototype to be installed and commissioned in Rokkasho. The RFQ is composed of 18 modules flanged together for a total length of 9.8m designed to accelerate the 125mA D+ beam to 5MeV at a frequency of 175MHz. The mechanical specifications are very challenging, tight tolerances are required on the machining and on the brazing process. The line is subdivided into 3 Super Modules of 6 modules each. The production of the High Energy portion has been completed and delivered, while the Low Energy one is performing the acceptance test. They were commissioned to external firms. The production of the Intermediate Energy portion has been done in house (INFN) and will be commissioned soon. The 1st modules (16, 17 and 2) were produced adopting 2 brazing steps, while for all the remaining ones we adopted a single brazing step. In this paper the production status and the development of the brazing procedure will be described.  
 
TUPP093 The Couplers for the IFMIF-EVEDA RFQ High Power Test Stand at LNL: Design, Construction and Operation 643
 
  • E. Fagotti, L. Antoniazzi, M.G. Giacchini, F. Grespan, M. Montis, A. Palmieri, A. Pisent, C. R. Roncolato
    INFN/LNL, Legnaro (PD), Italy
 
  In order to assess the critical aspects of the IFMIF-EVEDA RFQ construction procedure and operation, it was decided to perform a High Power Test of a subset of the RFQ consisting in its last 550 mm three modules (out of 18) plus a Prototype Module, 390 mm long, used as RF plug. These modules are going to be tested at full power in CW of INFN LNL Labs, in the so-called RFQ High Power Test Stand. For such a purpose, a RF tube-based amplifier capable of 220 kW CW output power at the operational frequency of 175 MHz was purchased from an Italian company. A critical component of this test is the RF power coupler. Therefore INFN-LNL developed a design of two identical water-cooled loop antenna couplers, built with OFE copper and vacuum sealed with a commercially available 6”1/8 Alumina planar window. These couplers were tested separately on an aluminium coupling cavity. In particular one of them acts as a power feeder, while the other one, connected with a 200 kW water-cooled load, acts as a receiver. In this paper, the main aspects of the design, construction and tests performed on the couplers and coupling cavity will be described.  
 
THPP044 ESS Normal Conducting Linac Status and Plans 948
 
  • A. Ponton, B. Cheymol, R. De Prisco, M. Eshraqi, R. Miyamoto, E. Sargsyan
    ESS, Lund, Sweden
  • G. Bourdelle, M. Desmons, A. France, O. Piquet, B. Pottin
    CEA/DSM/IRFU, France
  • I. Bustinduy, P.J. González, J.L. Muñoz, I. Rueda, F. Sordo
    ESS Bilbao, Bilbao, Spain
  • L. Celona, S. Gammino, L. Neri
    INFN/LNS, Catania, Italy
  • M. Comunian, F. Grespan, A. Pisent, C. R. Roncolato
    INFN/LNL, Legnaro (PD), Italy
  • P. Mereu
    INFN-Torino, Torino, Italy
 
  The ESS Normal Conducting (NC) linac is composed of an ion source, a Low Energy Beam Transport line, a Radio Frequency Quarupole (RFQ), a Medium Energy Beam Transport Line (MEBT) and a Drift Tube Linac (DTL). It creates, bunches and accelerates the proton beam up to 90 MeV before injecting into the superconducting linac which will deliver a 5 MW beam onto the neutron production target. The construction of the NC linac is part of a broad collaboration involving experts of various Labs in Europe. The technical chalenges and the collaboration strategy for the NC linac will be presented.  
 
THPP087 ESS DTL Design and Drift Tube Prototypes 1050
 
  • F. Grespan, M. Comunian, A. Pisent, M. Poggi, C. R. Roncolato
    INFN/LNL, Legnaro (PD), Italy
  • P. Mereu
    INFN-Torino, Torino, Italy
 
  The Drift Tube Linac (DTL) for the ESS accelerator will accelerate protons up to 62.5 mA average pulse current from 3.62 to 90 MeV. The 5 tanks composing the DTL are designed to operate at 352.2 MHz in pulses of 2.86 ms long with a repetition rate of 14 Hz. The accelerating field is around 3.1 MV/m, constant in each tank. Permanent magnet quadrupoles (PMQs) are used as focusing element in a FODO lattice. The empty drift tubes accommodate Electro Magnetic Dipoles (EMDs) and Beam Position Monitors (BPMs) in order to implement beam corrective schemes. A complete set of Drift Tubes is under construction that is BPM, EMD and PMQ types. These prototypes are aimed to validate the design with the involved integration issues of the various components, as well as the overall technological and assembly process. This paper presents the main mechanical choices and the status of the prototyping program of the Drift Tubes.